MoDOT contract 251114-C04 bid tabulation

JKU0041-ROUTE 273-PLATTE COUNTY. Let by Missouri DOT on November 14, 2025, Platte, Kansas City. 3 bids received; low bid $1,822,269 by Ideker, Inc..

Owner
Missouri DOT
Letting
14 NOV 2025
Pay items
40
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ideker, Inc.$1,822,269Low
2Superior Bowen Asphalt Company, LLC$2,064,724+13%
3J. M. Fahey Construction Co.$2,116,660+16%
MoDOT contract 251114-C04: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ideker, Inc.2. Superior Bowen Asphalt Company, LLC3. J. M. Fahey Construction Co.
0010Removal of improvements (2022010)LS1$57,920$39,600$60,000
0020Class A excavation (2031000)CY1,317$38.30$38.30$40.50
0030Linear grading class 1 (2071000)STA1.60$2,600.00$2,600.00$2,800.00
0040Shaping slopes, class III (2153000)100F3$1,375.00$1,375.00$1,510.00
0050Furnishing rock base material (3030600)SY1,175$43.40$43.40$45.75
0060Placing rock base (3030610A)SY1,175$13.20$13.20$14.00
0070Type 5 aggregate for base (6 in. thick) (3040506)SY285$30.10$30.10$32.00
0080Misc.permanent aggregate edge treatment (3049910)TON1,186$91.55$45.70$48.25
0090Type A2 shoulder (4010150)SY69.80$513.43$350.00$135.25
0100Bituminous pavement mixture PG64-22, (BP-2) (4011211)TON12,288.90$72.38$93.00$93.00
0110Bituminous pavement mixture PG64-22 (base) (4013000)TON537.70$125.57$185.00$145.00
0120Tack coat - non-tracking (4071007)GAL11,689$4.20$4.50$4.00
0130Misc.modified tack coat (4079912)GAL3,981$4.20$4.50$4.00
0140Furnishing and placing concrete material for full depth pavement repair (6131010)SY102.70$374.65$374.65$395.00
0150Subgrade compaction (6 in. depth) (pavement repair) (6131012)SY103$2.30$2.30$2.50
0160Type 1 or 5 aggregate for base (4 in. thick) (pavement repair) (6131013)SY103$8.05$8.05$8.50
0170Full depth pavement repair saw cut (for perimeter and internal saw cuts) (6131014)LF282$1.45$1.45$1.50
0180Dowel bar (drilling, furnishing and installation) for full depth pavement repair (6131015)EACH120$5.35$5.35$5.50
0190Construction signs (6161005)SF1,727$6.00$6.50$6.50
0200Channelizer (trim-line) (6161025)EACH200$10.00$17.00$10.50
0210Type 3 moveable barricade (6161030)EACH10$75.00$145.00$79.00
0220Changeable message sign without communication interface, contractor furnished retained (6161098A)EACH5$2,100.00$1,750.00$2,216.00
0230Mobilization (6181000)LS1$97,400$180,000$160,000
0240Preformed thermoplastic pavement marking, 24 in. white (6200015)LF318$20.00$20.00$21.00
0250Preformed thermoplastic pavement marking, 24 in. yellow (6200018)LF255$20.00$20.00$21.00
0260Preformed thermoplastic pavement marking, left/right arrow (6200021)EACH13$350.00$295.00$369.00
02704 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D)LF59,622$0.11$0.14$0.15
02804 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D)LF46,730$0.11$0.14$0.15
0290Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001)SY83,107$2.55$1.85$3.00
0300Modified coldmilling (depth transitions) (6224010)SY1,801$15.48$19.50$5.25
0310Bituminous shoulder rumble strip (6261000A)STA319.70$22.00$18.50$31.00
0320Bituminous centerline rumble strip (6261001)STA197.40$22.00$18.50$31.00
0330Mulching (8025006)ACRE0.10$10,000$10,000$10,500
0340Seeding - cool season grasses (8051000A)ACRE0.10$10,000$10,000$10,500
0350Alternate ditch check (8061006)LF80$14.51$24.15$10.50
0360Sediment removal (8061016)CY17$24.01$24.00$75.50
0370Silt fence (8061019)LF880$3.76$6.25$2.75
0380MGS guardrail (6061060)LF112.50$28.00$28.00$43.00
0390MGS bridge approach transition section (regular/no curb) (6061069)EACH2$3,500.00$3,500.00$4,654.00
0400Type A crashworthy end terminal (MASH) (6063014)EACH2$2,900.00$2,900.00$4,225.00
MoDOT contract 251114-C04: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of November 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy