MoDOT contract 251212-C05 bid tabulation

JKU0110 - ROUTE F - JACKSON COUNTY. Let by Missouri DOT on December 12, 2025, Jackson, Kansas City. 4 bids received; low bid $960,346 by Widel, Inc..

Owner
Missouri DOT
Letting
12 DEC 2025
Pay items
44
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Widel, Inc.$960,346Low
2Epic Concrete Construction, Inc.$963,1010.0%
3Louis-Company, LLC$1,222,487+27%
4Realm Construction Inc.$1,294,578+35%
MoDOT contract 251212-C05: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Widel, Inc.2. Epic Concrete Construction, Inc.3. Louis-Company, LLC4. Realm Construction Inc.
0010Clearing and grubbing (2013000)ACRE1$3,700.00$12,600$20,000$38,588
0020Removal of improvements (2022010)LS1$30,000$18,542$10,000$30,828
0030Class A excavation (2031000)CY2,472$8.00$17.70$21.72$36.00
0040Compacting embankment (2036000)CY1,544$2.50$15.60$25.85$23.00
0050Compacting in cut (2037075)STA2$850.00$4,796.60$1,611.02$4,296.00
0060Type 5 aggregate for base (6 in. thick) (3040506)SY512$20.00$11.00$20.20$18.30
0070Misc.optional pavement (11" BP VS. 9" JCPC) (4019905)SY512$120.00$112.70$162.26$148.20
0080Furnishing type 3 rock ditch liner (6096030A)CY39$115.00$86.10$118.82$118.00
0090Placing type 3 rock ditch liner (6096043)CY39$12.00$72.40$45.74$77.00
0100Furnishing type 2 rock blanket (6113020)CY557$110.00$86.10$86.60$75.50
0110Placing type 2 rock blanket (6113040)CY557$13.00$26.70$28.82$77.00
0120Construction signs (6161005)SF855$10.00$8.30$10.65$6.60
0130Type 3 moveable barricade (6161030)EACH14$125.00$103.00$133.17$138.00
0140Changeable message sign without communication interface, contractor furnished retained (6161098A)EACH7$3,500.00$2,575.00$3,329.14$2,514.00
0150Mobilization (6181000)LS1$45,000$57,383$100,000$155,611
01604 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D)LF580$0.75$0.70$0.80$0.65
01704 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D)LF363$0.75$0.70$0.80$0.80
0180Separation geotextile (6240104A)SY836$10.00$2.60$3.33$14.60
0190Misc.optional rumble strip (6269909)STA3.20$5,200.00$515.00$665.83$575.00
0200Contractor furnished surveying and staking (6274000)LS1$11,000$11,220$11,985$7,130.00
0210Mulching (8025006)ACRE1$4,800.00$4,120.00$1,864.32$2,185.00
0220Seeding - cool season grasses (8051000A)ACRE1$3,300.00$3,090.00$3,528.88$2,185.00
0230Rock ditch check (8061005)LF10$300.00$93.10$133.17$68.40
0240Alternate ditch check (8061006)LF110$13.50$20.60$15.98$17.80
0250Sediment removal (8061016)CY20$50.00$18.90$104.52$52.05
0260Temporary seeding (8061017)ACRE0.20$1,750.00$7,725.00$2,130.60$11,500
0270Silt fence (8061019)LF860$3.50$4.20$3.99$3.05
0280Type C berm (8061050)LF186$10.00$15.70$46.61$44.00
0290Type 3B erosion control blanket (8064140)SY581$3.25$5.30$3.99$2.00
0300MGS guardrail (6061060)LF250$30.00$25.80$33.29$28.75
0310MGS bridge approach transition section (regular/no curb) (6061069)EACH4$4,400.00$3,914.00$5,060.29$4,370.00
0320Type A crashworthy end terminal (MASH) (6063014)EACH4$4,000.00$3,502.00$4,527.63$3,910.00
0330Class 1 excavation (2061000)CY100$17.50$23.30$35.68$62.00
0340Removal of bridges (2160500)LS1$25,500$22,885$45,000$48,859
0350Bridge approach slab (minor road) (5031011A)SY136$225.00$289.10$388.61$263.90
0360Galvanized structural steel piles (12 in) (7021212)LF365$135.00$90.40$131.16$101.35
0370Pile point reinforcement (7027000)EACH10$122.50$120.80$153.14$320.00
0380Class B concrete (substructure) (7032003)CY29.20$2,250.00$1,114.80$1,379.17$1,351.70
0390Type D barrier (7034219A)LF237$225.00$178.00$231.38$261.50
0400Slab on concrete NU-girder (7034221)SY350$400.00$595.30$609.58$608.20
0410NU 53, prestressed concrete NU-girder (7056023)LF379$510.00$447.90$589.94$489.00
0420Steel intermediate diaphragm for P/S concrete girders (7123301)EACH6$1,300.00$1,076.40$1,361.55$1,225.10
0430Vertical drain at end bents (7151001)EACH2$1,900.00$1,223.30$5,384.64$2,918.35
0440Laminated neoprene bearing pad (tapered) (7161003)EACH8$700.00$498.40$712.77$629.85
MoDOT contract 251212-C05: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of December 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy