MoDOT contract 251212-C06 bid tabulation
JKU0095 - ROUTE I-635 - PLATTE COUNTY. Let by Missouri DOT on December 12, 2025, Platte, Kansas City. 3 bids received; low bid $1,989,827 by Southern Road & Bridge, LLC.
- Owner
- Missouri DOT
- Letting
- 12 DEC 2025
- Pay items
- 31
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Southern Road & Bridge, LLC | $1,989,827 | Low |
| 2 | Comanche Construction, Inc. | $2,269,807 | +14% |
| 3 | Gemstone, LLC dba Gemstone, LLC MO | $2,744,833 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Southern Road & Bridge, LLC | 2. Comanche Construction, Inc. | 3. Gemstone, LLC dba Gemstone, LLC MO |
|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $125,000 | $98,506 | $11,000 |
| 0020 | Impact attenuator 65 MPH (sand barrel array) (6122017) | EACH | 2 | $6,500.00 | $3,767.52 | $6,000.00 |
| 0030 | Replacement sand barrel (6122020) | EACH | 2 | $500.00 | $775.96 | $1,800.00 |
| 0040 | Impact attenuator (relocation) (6122030) | EACH | 2 | $950.00 | $808.25 | $5,000.00 |
| 0050 | Construction signs (6161005) | SF | 534 | $9.00 | $6.89 | $7.20 |
| 0060 | Channelizer (trim-line) (6161025) | EACH | 75 | $16.00 | $13.84 | $75.00 |
| 0070 | Flashing arrow panel (6161040) | EACH | 2 | $725.00 | $478.65 | $1,800.00 |
| 0080 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $4,500.00 | $1,648.66 | $3,000.00 |
| 0090 | Concrete traffic barrier, type A (6171000) | LF | 275 | $248.00 | $136.43 | $240.00 |
| 0100 | Temporary traffic barrier, contractor furnished retained (6173600D) | LF | 3,580 | $38.00 | $44.93 | $55.00 |
| 0110 | Relocating temporary traffic barrier (6175010A) | LF | 3,580 | $16.00 | $11.98 | $24.00 |
| 0120 | Mobilization (6181000) | LS | 1 | $185,000 | $183,796 | $90,000 |
| 0130 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 8,305 | $0.70 | $0.34 | $2.70 |
| 0140 | 6 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205903B) | LF | 6,352 | $0.70 | $0.34 | $2.70 |
| 0150 | Pavement marking removal (6207001) | LF | 27,948 | $0.75 | $0.19 | $1.30 |
| 0160 | 4 in temporary pavement marking paint (6208076) | LF | 13,291 | $0.50 | $0.32 | $2.10 |
| 0170 | Substructure repair (formed) (7040101) | SF | 80 | $450.00 | $2,515.07 | $280.00 |
| 0180 | Half-sole repair (7040104) | SF | 250 | $350.00 | $161.75 | $120.00 |
| 0190 | Cleaning and epoxy coating (7040113) | SF | 21,450 | $11.00 | $4.25 | $12.00 |
| 0200 | Concrete crack filler (7040163) | SY | 14,339 | $15.00 | $12.76 | $24.00 |
| 0210 | Misc.barrier curb repair (7049904) | SF | 400 | $205.00 | $172.72 | $140.00 |
| 0220 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $140,000 | $63,819 | $125,000 |
| 0230 | Surface preparation for recoating structural steel (7125200) | SF | 11,600 | $14.00 | $63.82 | $44.00 |
| 0240 | Field application of inorganic zinc primer (7125210) | SF | 11,600 | $10.00 | $5.32 | $7.50 |
| 0250 | Intermediate field coat (system G) (7125365A) | SF | 11,600 | $10.00 | $3.19 | $7.50 |
| 0260 | Finish field coat (system G) (7125370A) | SF | 11,600 | $10.00 | $3.19 | $7.50 |
| 0270 | Misc.bearing stiffener repair (7129902) | EACH | 2 | $3,000.00 | $20,472 | $60,000 |
| 0280 | Misc.fatigue crack repair (7129902) | EACH | 2 | $2,500.00 | $21,149 | $50,000 |
| 0290 | Misc.girder flange repair (7129902) | EACH | 1 | $2,500.00 | $17,536 | $100,000 |
| 0300 | Misc.stiffener repair (7129902) | EACH | 2 | $2,500.00 | $17,581 | $58,000 |
| 0310 | Strip seal (7172002) | LF | 151 | $150.00 | $340.23 | $690.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of December 12, 2025. Compiled by Mirage Metrics.