MoDOT contract 251212-H2B bid tabulation

JSE0007, JSE0008, JSE0009-ROUTES VV, WW, DD-TEXAS, DENT, HOWELL COUNTIES. Let by Missouri DOT on December 12, 2025, Howell, Southeast. 5 bids received; low bid $1,506,000 by Pace Construction Company, LLC.

Owner
Missouri DOT
Letting
12 DEC 2025
Pay items
31
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Pace Construction Company, LLC$1,506,000Low
2APAC-Central, Inc.$1,656,527+10%
3Magruder Paving, LLC$1,660,035+10%
4Apex Paving Co.$1,832,490+22%
5Capital Paving & Construction, LLC$2,071,386+38%
MoDOT contract 251212-H2B: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Pace Construction Company, LLC2. APAC-Central, Inc.3. Magruder Paving, LLC4. Apex Paving Co.5. Capital Paving & Construction, LLC
0010Misc.permanent aggregate edge treatment (3049910)TON446.60$89.50$20.00$60.14$49.57$117.01
0015Gravel (A) or crushed stone (B) (3105002)TON13$89.50$56.94$60.14$49.57$117.01
0030Bituminous pavement mixture PG64-22 (surface leveling) (4020520)TON8,725.80$77.65$87.60$89.62$103.95$108.20
0040Tack coat (4071005)GAL12,348$2.48$2.79$3.33$2.15$2.30
0050Prime-liquid asphalt MC 800 (4081018)GAL1,436$5.20$2.81$4.90$4.58$3.53
0060Misc.lump sum temporary traffic control (6169901)LS1$3,563.16$3,584.00$4,312.00$2,762.00$9,600.00
0070Mobilization (6181000)LS1$50,929$34,655$31,050$38,124$50,221
00804 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D)LF103,383$0.15$0.12$0.15$0.15$0.12
00904 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D)LF100,017$0.14$0.12$0.14$0.14$0.12
0100Modified coldmilling (depth transitions) (6224010)SY1,089$16.00$11.75$11.75$14.52$21.34
0110Misc.permanent aggregate edge treatment (3049910)TON170.80$91.59$20.00$62.61$60.78$135.79
0115Gravel (A) or crushed stone (B) (3105002)TON5$92.42$120.76$62.61$60.78$135.79
0130Bituminous pavement mixture PG64-22 (surface leveling) (4020520)TON3,354.40$73.75$94.90$87.69$99.50$118.49
0140Tack coat (4071005)GAL4,711$2.54$2.79$3.33$2.15$2.32
0150Prime-liquid asphalt MC 800 (4081018)GAL549$6.05$2.81$4.91$5.18$3.70
0160Misc.lump sum temporary traffic control (6169901)LS1$3,550.00$3,584.00$4,312.00$2,762.00$4,200.00
0170Mobilization (6181000)LS1$30,000$27,115$12,300$16,575$12,509
01804 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D)LF39,463$0.15$0.16$0.15$0.15$0.16
01904 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D)LF39,463$0.15$0.10$0.15$0.15$0.10
0200Modified coldmilling (depth transitions) (6224010)SY528$16.50$12.49$11.75$14.97$22.01
0210Misc.permanent aggregate edge treatment (3049910)TON169.30$92.00$20.00$61.78$56.88$75.80
0215Gravel (A) or crushed stone (B) (3105002)TON6$92.00$99.52$61.78$56.88$75.80
0230Bituminous pavement mixture PG64-22 (surface leveling) (4020520)TON3,329.60$69.00$92.48$82.15$93.31$110.12
0240Tack coat (4071005)GAL4,754$2.54$2.79$3.33$2.15$2.32
0250Prime-liquid asphalt MC 800 (4081018)GAL545$6.05$2.81$5.01$5.19$3.71
0260Misc.lump sum temporary trffic control (6169901)LS1$3,550.00$3,584.00$4,312.00$2,762.00$4,400.00
0270Mobilization (6181000)LS1$27,000$27,382$11,300$16,575$12,509
02804 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D)LF39,188$0.15$0.15$0.15$0.15$0.15
02904 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D)LF39,188$0.15$0.10$0.15$0.15$0.10
0300Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001)SY444$8.45$11.14$15.69$15.46$11.48
0310Modified coldmilling (depth transitions) (6224010)SY1,856$4.10$6.22$15.69$8.17$18.78
MoDOT contract 251212-H2B: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of December 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy