MoDOT contract 260116-C03 bid tabulation
JKU0135 - ROUTE E,H - PLATTE COUNTY. Let by Missouri DOT on January 16, 2026, Platte, Kansas City. 4 bids received; low bid $1,205,666 by T&B Trucking and Excavating, LLC.
- Owner
- Missouri DOT
- Letting
- 16 JAN 2026
- Pay items
- 42
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | T&B Trucking and Excavating, LLC | $1,205,666 | Low |
| 2 | Epic Concrete Construction, Inc. | $1,271,355 | +5.0% |
| 3 | C.P. Excavating, LLC | $1,599,528 | +33% |
| 4 | Amino Bros. Co., Inc. | $2,001,090 | +66% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. T&B Trucking and Excavating, LLC | 2. Epic Concrete Construction, Inc. | 3. C.P. Excavating, LLC | 4. Amino Bros. Co., Inc. |
|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (2013000) | ACRE | 1 | $15,000 | $16,500 | $15,780 | $99,500 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $35,000 | $47,795 | $71,650 | $104,000 |
| 0030 | Unclassified excavation (2035000) | CY | 2,886 | $25.00 | $6.00 | $39.20 | $62.00 |
| 0040 | Compacting embankment (2036000) | CY | 1,750 | $15.00 | $5.00 | $40.50 | $0.01 |
| 0050 | Class 3 excavation (2063000) | CY | 39 | $50.00 | $12.00 | $30.00 | $25.00 |
| 0060 | Class 4 excavation (2063300) | CY | 1,035 | $20.00 | $12.00 | $10.00 | $146.50 |
| 0070 | Class 4 excavation in rock (2063400) | CY | 38 | $100.00 | $180.00 | $29.00 | $334.50 |
| 0080 | Culvert cleanout (2063500) | EACH | 1 | $5,000.00 | $1,709.00 | $5,000.00 | $2,500.00 |
| 0090 | Linear grading class 2 (2072000) | STA | 0.40 | $2,500.00 | $4,502.00 | $1,402.00 | $3,700.00 |
| 0100 | Subgrade compaction (6-inch depth) (2101006A) | 100F | 7 | $1,000.00 | $1,384.00 | $1,923.00 | $4,100.00 |
| 0110 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 1,712 | $20.00 | $12.00 | $22.50 | $30.50 |
| 0120 | Misc.optional pavement (3049905) | SY | 1,657 | $100.00 | $100.00 | $111.10 | $89.50 |
| 0130 | Misc.witness post assemblies (6029902) | EACH | 29 | $450.00 | $440.00 | $833.50 | $300.00 |
| 0140 | Misc.temporary fence (6079903) | LF | 631 | $10.00 | $28.00 | $31.10 | $19.50 |
| 0150 | Furnishing type 1 rock ditch liner (6096010A) | CY | 2 | $50.00 | $99.00 | $75.00 | $126.00 |
| 0160 | Furnishing type 2 rock ditch liner (6096020) | CY | 246 | $50.00 | $99.00 | $71.00 | $126.00 |
| 0170 | Placing type 1 rock ditch liner (6096041) | CY | 2 | $50.00 | $300.00 | $5,620.00 | $380.00 |
| 0180 | Placing type 2 rock ditch liner (6096042) | CY | 246 | $35.00 | $10.00 | $20.96 | $71.00 |
| 0190 | Rock lining (6097000) | CY | 920 | $85.00 | $107.00 | $20.80 | $141.00 |
| 0200 | Construction signs (6161005) | SF | 1,971 | $7.25 | $7.00 | $11.20 | $12.50 |
| 0210 | Channelizer (trim-line) (6161025) | EACH | 76 | $18.50 | $16.00 | $28.00 | $32.00 |
| 0220 | Type 3 moveable barricade (6161030) | EACH | 12 | $190.00 | $153.00 | $195.00 | $250.00 |
| 0230 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 8 | $4,500.00 | $3,145.00 | $4,000.00 | $4,600.00 |
| 0240 | Temporary long-term rumble strips (6162002) | EACH | 12 | $1,500.00 | $1,365.00 | $890.00 | $1,000.00 |
| 0250 | Mobilization (6181000) | LS | 1 | $90,000 | $58,300 | $134,080 | $110,000 |
| 0260 | Additional mobilization for seeding (6181020) | EACH | 6 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0270 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 1,146 | $1.00 | $0.14 | $0.25 | $0.25 |
| 0280 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 5,092 | $6.00 | $0.14 | $0.25 | $0.25 |
| 0290 | Permanent erosion control geotextile (6240103A) | SY | 1,919 | $6.00 | $2.00 | $8.50 | $13.00 |
| 0300 | Contractor furnished surveying and staking (6274000) | LS | 1 | $15,000 | $24,860 | $33,330 | $20,500 |
| 0310 | Class B-1 concrete (culverts) (7034041) | CY | 447.90 | $725.00 | $1,111.00 | $1,050.00 | $1,150.00 |
| 0320 | Reinforcing steel (culverts) (7061030) | LB | 66,030 | $1.65 | $1.80 | $2.00 | $2.30 |
| 0330 | 18 in. pipe group B (7250318A) | LF | 58 | $80.00 | $164.00 | $79.00 | $107.00 |
| 0340 | 18 in. or allowed substitute group B flared end section (7320018A) | EACH | 1 | $1,000.00 | $1,506.00 | $2,630.00 | $1,850.00 |
| 0350 | Pipe liner for existing culvert (7350001) | LF | 30 | $90.00 | $135.00 | $445.00 | $1,250.00 |
| 0360 | Mulching (8025006) | ACRE | 0.90 | $1,800.00 | $1,575.00 | $1,750.00 | $11,500 |
| 0370 | Seeding - cool season grasses (8051000A) | ACRE | 0.90 | $2,800.00 | $3,045.00 | $3,170.00 | $2,550.00 |
| 0380 | Sediment trap rock (8061004) | CY | 49 | $100.00 | $98.00 | $160.00 | $200.00 |
| 0390 | Rock ditch check (8061005) | LF | 258 | $65.00 | $15.00 | $47.00 | $100.00 |
| 0400 | Alternate ditch check (8061006) | LF | 240 | $10.50 | $11.00 | $267.00 | $13.00 |
| 0410 | Sediment removal (8061016) | CY | 116 | $5.00 | $16.00 | $23.00 | $75.00 |
| 0420 | Silt fence (8061019) | LF | 1,576 | $2.85 | $4.20 | $3.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of January 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.