MoDOT contract 260116-C03 bid tabulation

JKU0135 - ROUTE E,H - PLATTE COUNTY. Let by Missouri DOT on January 16, 2026, Platte, Kansas City. 4 bids received; low bid $1,205,666 by T&B Trucking and Excavating, LLC.

Owner
Missouri DOT
Letting
16 JAN 2026
Pay items
42
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1T&B Trucking and Excavating, LLC$1,205,666Low
2Epic Concrete Construction, Inc.$1,271,355+5.0%
3C.P. Excavating, LLC$1,599,528+33%
4Amino Bros. Co., Inc.$2,001,090+66%
MoDOT contract 260116-C03: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. T&B Trucking and Excavating, LLC2. Epic Concrete Construction, Inc.3. C.P. Excavating, LLC4. Amino Bros. Co., Inc.
0010Clearing and grubbing (2013000)ACRE1$15,000$16,500$15,780$99,500
0020Removal of improvements (2022010)LS1$35,000$47,795$71,650$104,000
0030Unclassified excavation (2035000)CY2,886$25.00$6.00$39.20$62.00
0040Compacting embankment (2036000)CY1,750$15.00$5.00$40.50$0.01
0050Class 3 excavation (2063000)CY39$50.00$12.00$30.00$25.00
0060Class 4 excavation (2063300)CY1,035$20.00$12.00$10.00$146.50
0070Class 4 excavation in rock (2063400)CY38$100.00$180.00$29.00$334.50
0080Culvert cleanout (2063500)EACH1$5,000.00$1,709.00$5,000.00$2,500.00
0090Linear grading class 2 (2072000)STA0.40$2,500.00$4,502.00$1,402.00$3,700.00
0100Subgrade compaction (6-inch depth) (2101006A)100F7$1,000.00$1,384.00$1,923.00$4,100.00
0110Type 5 aggregate for base (6 in. thick) (3040506)SY1,712$20.00$12.00$22.50$30.50
0120Misc.optional pavement (3049905)SY1,657$100.00$100.00$111.10$89.50
0130Misc.witness post assemblies (6029902)EACH29$450.00$440.00$833.50$300.00
0140Misc.temporary fence (6079903)LF631$10.00$28.00$31.10$19.50
0150Furnishing type 1 rock ditch liner (6096010A)CY2$50.00$99.00$75.00$126.00
0160Furnishing type 2 rock ditch liner (6096020)CY246$50.00$99.00$71.00$126.00
0170Placing type 1 rock ditch liner (6096041)CY2$50.00$300.00$5,620.00$380.00
0180Placing type 2 rock ditch liner (6096042)CY246$35.00$10.00$20.96$71.00
0190Rock lining (6097000)CY920$85.00$107.00$20.80$141.00
0200Construction signs (6161005)SF1,971$7.25$7.00$11.20$12.50
0210Channelizer (trim-line) (6161025)EACH76$18.50$16.00$28.00$32.00
0220Type 3 moveable barricade (6161030)EACH12$190.00$153.00$195.00$250.00
0230Changeable message sign with communication interface, contractor furnished retained (6161099)EACH8$4,500.00$3,145.00$4,000.00$4,600.00
0240Temporary long-term rumble strips (6162002)EACH12$1,500.00$1,365.00$890.00$1,000.00
0250Mobilization (6181000)LS1$90,000$58,300$134,080$110,000
0260Additional mobilization for seeding (6181020)EACH6$600.00$600.00$600.00$600.00
02704 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D)LF1,146$1.00$0.14$0.25$0.25
02804 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D)LF5,092$6.00$0.14$0.25$0.25
0290Permanent erosion control geotextile (6240103A)SY1,919$6.00$2.00$8.50$13.00
0300Contractor furnished surveying and staking (6274000)LS1$15,000$24,860$33,330$20,500
0310Class B-1 concrete (culverts) (7034041)CY447.90$725.00$1,111.00$1,050.00$1,150.00
0320Reinforcing steel (culverts) (7061030)LB66,030$1.65$1.80$2.00$2.30
033018 in. pipe group B (7250318A)LF58$80.00$164.00$79.00$107.00
034018 in. or allowed substitute group B flared end section (7320018A)EACH1$1,000.00$1,506.00$2,630.00$1,850.00
0350Pipe liner for existing culvert (7350001)LF30$90.00$135.00$445.00$1,250.00
0360Mulching (8025006)ACRE0.90$1,800.00$1,575.00$1,750.00$11,500
0370Seeding - cool season grasses (8051000A)ACRE0.90$2,800.00$3,045.00$3,170.00$2,550.00
0380Sediment trap rock (8061004)CY49$100.00$98.00$160.00$200.00
0390Rock ditch check (8061005)LF258$65.00$15.00$47.00$100.00
0400Alternate ditch check (8061006)LF240$10.50$11.00$267.00$13.00
0410Sediment removal (8061016)CY116$5.00$16.00$23.00$75.00
0420Silt fence (8061019)LF1,576$2.85$4.20$3.00$5.00
MoDOT contract 260116-C03: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of January 16, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way