MoDOT contract 260116-D03 bid tabulation
JCD0021, JCD0335 - ROUTES 63, 179, U, 54 - BOONE, MONITEAU, COLE COUNTIES. Let by Missouri DOT on January 16, 2026, Moniteau, Central. 8 bids received; low bid $748,900 by International Rigging Group, LLC.
- Owner
- Missouri DOT
- Letting
- 16 JAN 2026
- Pay items
- 24
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | International Rigging Group, LLC | $748,900 | Low |
| 2 | Omega Coatings & Construction, LLC | $833,550 | +11% |
| 3 | Steel City Contractors, LLC | $1,189,200 | +59% |
| 4 | Thomas Industrial Coatings, Inc. | $1,602,808 | +114% |
| 5 | Olympus Painting Contractors, Inc. | $1,745,180 | +133% |
| 6 | Southern Road & Bridge, LLC | $1,838,300 | +145% |
| 7 | Gemstone, LLC dba Gemstone, LLC MO | $1,875,500 | +150% |
| 8 | Monoko, LLC | $2,177,200 | +191% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. International Rigging Group, LLC | 2. Omega Coatings & Construction, LLC | 3. Steel City Contractors, LLC | 4. Thomas Industrial Coatings, Inc. | 5. Olympus Painting Contractors, Inc. | 6. Southern Road & Bridge, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 4 | $2,400.00 | $2,500.00 | $2,500.00 | $2,500.00 | $4,000.00 | $5,000.00 |
| 0020 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $15,200 | $15,000 | $40,000 | $21,964 | $169,000 | $25,000 |
| 0030 | Mobilization (6181000) | LS | 1 | $25,000 | $45,000 | $75,000 | $31,300 | $55,000 | $100,000 |
| 0040 | Surface preparation for recoating structural steel (7125200) | SF | 17,900 | $6.00 | $7.00 | $8.00 | $10.00 | $11.40 | $8.00 |
| 0050 | Field application of inorganic zinc primer (7125210) | SF | 17,900 | $2.00 | $2.50 | $4.00 | $5.00 | $4.00 | $4.00 |
| 0060 | Finished field coat (system L) (7125397) | SF | 17,900 | $2.00 | $1.75 | $3.00 | $5.00 | $5.00 | $7.00 |
| 0070 | Surface preparation for recoating structural steel (7125200) | SF | 14,300 | $6.00 | $7.00 | $8.00 | $10.00 | $11.20 | $8.00 |
| 0080 | Field application of inorganic zinc primer (7125210) | SF | 14,300 | $2.00 | $2.50 | $4.00 | $5.00 | $5.00 | $4.00 |
| 0090 | Finished field coat (system L) (7125397) | SF | 14,300 | $2.00 | $1.75 | $3.00 | $5.00 | $5.00 | $7.00 |
| 0100 | Surface preparation for recoating structural steel (7125200) | SF | 13,800 | $6.00 | $7.00 | $8.00 | $10.00 | $12.20 | $10.00 |
| 0110 | Field application of inorganic zinc primer (7125210) | SF | 13,800 | $2.00 | $2.50 | $4.00 | $5.00 | $5.00 | $6.00 |
| 0120 | Finished field coat (system L) (7125397) | SF | 13,800 | $2.00 | $1.75 | $3.00 | $5.00 | $5.00 | $9.00 |
| 0130 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 3 | $2,200.00 | $2,500.00 | $2,500.00 | $2,500.00 | $4,000.00 | $3,500.00 |
| 0140 | Misc.misc. lump sum traffic control (6169901) | LS | 1 | $13,500 | $10,000 | $25,000 | $9,744.00 | $48,000 | $25,000 |
| 0150 | Mobilization (6181000) | LS | 1 | $25,000 | $20,000 | $30,000 | $30,000 | $35,000 | $100,000 |
| 0160 | Surface preparation for recoating structural steel (7125200) | SF | 12,500 | $6.00 | $6.50 | $8.00 | $19.50 | $10.00 | $10.00 |
| 0170 | Field application of inorganic zinc primer (7125210) | SF | 12,500 | $2.00 | $2.50 | $4.00 | $5.00 | $4.00 | $7.00 |
| 0180 | Finished field coat (system L) (7125397) | SF | 12,500 | $2.00 | $1.75 | $3.00 | $5.00 | $4.00 | $9.00 |
| 0190 | Surface preparation for recoating structural steel (7125200) | SF | 4,300 | $6.00 | $6.50 | $10.00 | $19.50 | $17.00 | $20.00 |
| 0200 | Field application of inorganic zinc primer (7125210) | SF | 4,300 | $2.00 | $2.50 | $5.00 | $5.00 | $6.00 | $8.00 |
| 0210 | Finished field coat (system L) (7125397) | SF | 4,300 | $2.00 | $1.75 | $3.00 | $5.00 | $6.00 | $12.00 |
| 0220 | Surface preparation for recoating structural steel (7125200) | SF | 2,600 | $6.00 | $6.50 | $10.00 | $19.50 | $21.00 | $20.00 |
| 0230 | Field application of inorganic zinc primer (7125210) | SF | 2,600 | $2.00 | $2.50 | $5.00 | $5.00 | $6.00 | $8.00 |
| 0240 | Finished field coat (system L) (7125397) | SF | 2,600 | $2.00 | $1.75 | $3.00 | $5.00 | $6.00 | $12.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of January 16, 2026. Compiled by Mirage Metrics.