MoDOT contract 261016-F03 bid tabulation
JSL0172, JSL0249-ROUTES 115, I-70 SOR-ST LOUIS COUNTY. Let by Missouri DOT on October 16, 2026, St Louis, St. Louis. 4 bids received; low bid $3,272,777 by Pace Construction Company, LLC.
- Owner
- Missouri DOT
- Letting
- 16 OCT 2026
- Pay items
- 110
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pace Construction Company, LLC | $3,272,777 | Low |
| 2 | Gershenson Construction Co., Inc. | $3,518,540 | +8.0% |
| 3 | Byrne & Jones Enterprises, Inc. dba Byrne & Jones Construction | $3,606,143 | +10% |
| 4 | N.B. West Contracting Company | $3,838,464 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pace Construction Company, LLC | 2. Gershenson Construction Co., Inc. | 3. Byrne & Jones Enterprises, Inc. dba Byrne & Jones Construction | 4. N.B. West Contracting Company |
|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $39,977 | $37,920 | $40,000 | $40,000 |
| 0020 | Culvert cleanout (2063500) | EACH | 2 | $3,450.00 | $3,234.00 | $5,000.00 | $9,150.00 |
| 0030 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 2,058 | $94.50 | $105.00 | $105.00 | $118.00 |
| 0040 | Asphaltic concrete mixture PG 76-22 (SP125BLP mix) (4030124) | TON | 5,253.90 | $131.50 | $129.00 | $124.00 | $150.00 |
| 0050 | Tack coat - non-tracking (4071007) | GAL | 4,043 | $3.85 | $3.15 | $6.00 | $4.00 |
| 0060 | Adjusting manhole (6042010) | EACH | 1 | $250.00 | $263.00 | $2,000.00 | $2,140.00 |
| 0070 | Misc.concrete manhole apron (6049902) | EACH | 1 | $4,600.00 | $2,199.00 | $5,000.00 | $2,810.00 |
| 0080 | Concrete gutter type A (6091041) | LF | 9 | $715.00 | $65.90 | $630.00 | $295.00 |
| 0090 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 4 | $2,200.00 | $2,310.00 | $2,200.00 | $2,200.00 |
| 0100 | Misc.lump sum traffic control (6169901) | LS | 1 | $11,000 | $33,990 | $11,000 | $32,100 |
| 0110 | Mobilization (6181000) | LS | 1 | $80,400 | $106,000 | $200,000 | $150,000 |
| 0120 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 847 | $18.00 | $26.30 | $18.00 | $18.00 |
| 0130 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 112 | $18.00 | $26.30 | $18.00 | $18.00 |
| 0140 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 22 | $275.00 | $368.00 | $275.00 | $275.00 |
| 0150 | Preformed thermoplastic pavement marking, straight arrow (6200024) | EACH | 24 | $225.00 | $263.00 | $225.00 | $225.00 |
| 0160 | Preformed thermoplastic pavement marking, combination STR/LT/RT (6200027) | EACH | 4 | $350.00 | $578.00 | $350.00 | $350.00 |
| 0170 | Preformed thermoplastic pavement marking, 24 in. X 36 in., yield line triangle (6200042A) | EACH | 9 | $70.00 | $78.80 | $70.00 | $70.00 |
| 0180 | 4 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205901B) | LF | 757 | $0.22 | $5.25 | $0.22 | $0.22 |
| 0190 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 18,630 | $0.29 | $0.30 | $0.29 | $0.29 |
| 0200 | 6 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205903B) | LF | 12,720 | $0.29 | $0.30 | $0.29 | $0.29 |
| 0210 | Misc.tier II inlaid pavement arrown system (6209902) | EACH | 2 | $5,900.00 | $7,089.00 | $5,900.00 | $5,900.00 |
| 0220 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 67,198 | $3.10 | $4.25 | $4.05 | $3.65 |
| 0230 | Contractor furnished surveying and staking (6274000) | LS | 1 | $500.00 | $5,251.00 | $5,000.00 | $2,500.00 |
| 0240 | Curb modification (7034535) | LF | 10 | $645.00 | $63.80 | $565.00 | $247.00 |
| 0270 | Base mounted control station 240 volt - 4 circuit (9012230) | EACH | 2 | $452.00 | $475.00 | $452.00 | $452.00 |
| 0280 | Conduit, 3 in. rigid, in trench (9013003) | LF | 2,394 | $20.10 | $21.10 | $20.10 | $20.10 |
| 0290 | Conduit, 3 in. rigid, pushed (9014003) | LF | 2,983 | $33.35 | $35.00 | $33.35 | $33.35 |
| 0310 | Cable, 2 AWG 1 conductor (9017002) | LF | 690 | $6.00 | $6.30 | $6.00 | $6.00 |
| 0320 | Cable, 4 AWG 1 conductor (9017004) | LF | 12,060 | $4.30 | $4.50 | $4.30 | $4.30 |
| 0330 | Cable, 10 AWG 1 conductor, pole and bracket (9017110) | LF | 3,240 | $1.50 | $1.60 | $1.50 | $1.50 |
| 0340 | Wire, 4 AWG, bare neutral (9017204) | LF | 5,740 | $3.40 | $3.55 | $3.40 | $3.40 |
| 0350 | Pole foundation (45 FT. mounting height) (9018245) | EACH | 12 | $2,520.00 | $2,646.00 | $2,520.00 | $2,520.00 |
| 0355 | Power supply assembly, type 2, 240/120 volt service, lighting only (9018612) | EACH | 2 | $14,800 | $15,540 | $16,280 | $14,800 |
| 0357 | Misc.45 FT. top mount light pole (9019902) | EACH | 12 | $4,012.00 | $4,213.00 | $4,413.20 | $4,012.00 |
| 0358 | Misc.118 W top mounted LED-C luminaire (9019902) | EACH | 12 | $627.00 | $658.00 | $689.70 | $627.00 |
| 0360 | SH-flat sheet - signal sign (9020833) | SF | 101 | $61.25 | $64.30 | $61.25 | $61.25 |
| 0370 | Misc.retroreflective backplates (9029902) | EACH | 7 | $327.00 | $343.00 | $327.00 | $327.00 |
| 0380 | Concrete footings, embedded (9031010) | CY | 4.60 | $3,200.00 | $3,361.00 | $3,200.00 | $3,200.00 |
| 0390 | I-beam posts (9031210) | LB | 350 | $10.00 | $10.50 | $10.00 | $10.00 |
| 0400 | Pipe posts (9031220) | LB | 1,960 | $12.00 | $12.60 | $12.00 | $12.00 |
| 0410 | Breakaway assembly (perforated square steel tube) (9031241) | EACH | 8 | $400.00 | $420.00 | $400.00 | $400.00 |
| 0420 | 2 in. PSST post - 12 GA. (9031270A) | LF | 1,108 | $38.00 | $39.90 | $38.00 | $38.00 |
| 0430 | Driven post anchor for 2 in. PSST - 7 GA. (9031273A) | EACH | 118 | $300.00 | $315.00 | $300.00 | $300.00 |
| 0440 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 395 | $44.00 | $46.20 | $44.00 | $44.00 |
| 0450 | Driven post anchor for 2.5 in. PSST - 7 GA. (9031281A) | EACH | 32 | $350.00 | $368.00 | $350.00 | $350.00 |
| 0460 | SH-flat sheet (9035004A) | SF | 1,473 | $40.00 | $42.00 | $40.00 | $40.00 |
| 0470 | ST-structural (9035011A) | SF | 49 | $60.00 | $63.00 | $60.00 | $60.00 |
| 0480 | Aluminum backing bars (9035030) | LF | 283 | $12.00 | $12.60 | $12.00 | $12.00 |
| 0485 | Pull box, preformed class 1 (9016110) | EACH | 16 | $1,713.00 | $1,799.00 | $1,884.30 | $1,713.00 |
| 0500 | Removal of improvements (2022010) | LS | 1 | $60,000 | $82,660 | $110,000 | $100,000 |
| 0510 | Class 3 excavation (2063000) | CY | 34 | $205.00 | $13.60 | $150.00 | $47.00 |
| 0520 | Culvert cleanout (2063500) | EACH | 1 | $3,200.00 | $3,603.00 | $5,000.00 | $9,500.00 |
| 0530 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 1,041 | $96.00 | $113.00 | $108.00 | $125.00 |
| 0540 | Asphaltic concrete mixture PG 76-22 (SP125BLP mix) (4030124) | TON | 3,049.70 | $131.00 | $131.00 | $120.00 | $145.00 |
| 0550 | Tack coat - non-tracking (4071007) | GAL | 3,898 | $3.45 | $3.15 | $5.00 | $3.50 |
| 0560 | Adjusting manhole (6042010) | EACH | 8 | $250.00 | $263.00 | $1,000.00 | $2,140.00 |
| 0570 | Misc.concrete manhole apron (6049902) | EACH | 8 | $4,425.00 | $2,199.00 | $2,500.00 | $2,810.00 |
| 0580 | Chain-link fence (48 in.) (6071011A) | LF | 5,484 | $48.00 | $50.40 | $48.00 | $48.00 |
| 0590 | 6 in. concrete median strip (6083006) | SY | 191 | $152.00 | $123.00 | $115.00 | $204.00 |
| 0600 | Misc.encapsulated median strip (6089905) | SY | 199 | $108.00 | $122.00 | $142.00 | $222.00 |
| 0610 | Grate and bearing plate (3 FT. X 2 FT. or 914 MM X 610 MM) (6141021) | EACH | 1 | $7,400.00 | $2,379.00 | $5,000.00 | $2,030.00 |
| 0620 | Manhole frame and cover, type 3 (6143013) | EACH | 1 | $1,950.00 | $420.00 | $5,000.00 | $414.00 |
| 0630 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 5 | $2,200.00 | $2,310.00 | $2,200.00 | $2,200.00 |
| 0640 | Misc.lump sum traffic control (6169901) | LS | 1 | $8,826.00 | $21,060 | $8,826.00 | $55,000 |
| 0650 | Mobilization (6181000) | LS | 1 | $61,000 | $55,720 | $120,000 | $125,000 |
| 0660 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 353 | $18.00 | $26.30 | $18.00 | $18.00 |
| 0670 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 208 | $18.00 | $26.30 | $18.00 | $18.00 |
| 0680 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 16 | $275.00 | $368.00 | $275.00 | $275.00 |
| 0690 | Preformed thermoplastic pavement marking, straight arrow (6200024) | EACH | 7 | $225.00 | $263.00 | $225.00 | $225.00 |
| 0700 | Preformed thermoplastic pavement marking, combination STR/LT/RT (6200027) | EACH | 1 | $350.00 | $578.00 | $350.00 | $350.00 |
| 0710 | Preformed thermoplastic pavement marking, 24 in. X 36 in., yield line triangle (6200042A) | EACH | 20 | $70.00 | $78.80 | $70.00 | $70.00 |
| 0720 | 4 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205901B) | LF | 12,566 | $0.22 | $0.24 | $0.22 | $0.22 |
| 0730 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 17,145 | $0.29 | $0.30 | $0.29 | $0.29 |
| 0740 | 6 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205903B) | LF | 3,905 | $0.29 | $0.30 | $0.29 | $0.29 |
| 0750 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 38,964 | $3.00 | $4.25 | $4.05 | $3.65 |
| 0760 | Contractor furnished surveying and staking (6274000) | LS | 1 | $500.00 | $5,251.00 | $5,000.00 | $10,000 |
| 0770 | Penetrating concrete sealer (7033013) | SY | 269 | $51.75 | $10.20 | $27.50 | $35.00 |
| 0780 | Select granular backfill for structural systems (7201200) | CY | 6 | $65.00 | $31.50 | $250.00 | $255.00 |
| 0790 | 15 in. pipe group A (7261015) | LF | 55 | $118.00 | $110.00 | $215.00 | $169.00 |
| 0800 | 18 in. pipe group A (7261018) | LF | 9 | $355.00 | $139.00 | $650.00 | $266.00 |
| 0810 | Precast concrete drop inlet 3 FT X 2 FT-6 in. (7311030) | FT | 5 | $1,140.00 | $829.00 | $2,000.00 | $1,240.00 |
| 0820 | Precast concrete drop inlet 3 FT X 2 FT (7311032) | FT | 4 | $1,400.00 | $936.00 | $2,000.00 | $1,410.00 |
| 0830 | MGS guardrail (6061060) | LF | 150 | $42.00 | $44.10 | $42.00 | $42.00 |
| 0840 | MGS end anchor (6061080) | EACH | 1 | $2,400.00 | $2,520.00 | $2,400.00 | $2,400.00 |
| 0850 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 1 | $4,200.00 | $4,411.00 | $4,200.00 | $4,200.00 |
| 0860 | Lighting pole, 45 FT. type at design 2 (9011062) | EACH | 1 | $4,012.00 | $4,213.00 | $4,012.00 | $4,012.00 |
| 0870 | Bracket arm, 15 FT. (9011115) | EACH | 1 | $1,037.00 | $1,089.00 | $1,037.00 | $1,037.00 |
| 0880 | Luminaire, LED-C (9011313) | EACH | 1 | $466.00 | $489.00 | $466.00 | $466.00 |
| 0890 | Conduit, 3 in. rigid, in trench (9013003) | LF | 49 | $20.10 | $21.10 | $20.10 | $20.10 |
| 0900 | Conduit, 3 in. rigid, pushed (9014003) | LF | 102 | $33.35 | $35.00 | $33.35 | $33.35 |
| 0920 | Pull box, preformed class 1 (9016110) | EACH | 2 | $1,713.00 | $1,799.00 | $1,713.00 | $1,713.00 |
| 0930 | Cable, 4 AWG 1 conductor (9017004) | LF | 80 | $4.30 | $4.50 | $4.30 | $4.30 |
| 0940 | Cable, 10 AWG 1 conductor, pole and bracket (9017110) | LF | 270 | $1.50 | $1.60 | $1.50 | $1.50 |
| 0950 | Wire, 4 AWG, bare neutral (9017204) | LF | 40 | $3.40 | $3.55 | $3.40 | $3.40 |
| 0960 | Pole foundation (45 FT. mounting height) (9018245) | EACH | 1 | $2,520.00 | $2,646.00 | $2,520.00 | $2,520.00 |
| 0970 | SH-flat sheet - signal sign (9020833) | SF | 96 | $61.25 | $64.30 | $61.25 | $61.25 |
| 0980 | Video detection system (9024975) | EACH | 1 | $25,950 | $27,250 | $25,950 | $25,950 |
| 0990 | Misc.retroreflective backplates (9029902) | EACH | 28 | $327.00 | $343.00 | $327.00 | $327.00 |
| 1000 | Concrete footings, embedded (9031010) | CY | 0.60 | $3,200.00 | $3,361.00 | $3,200.00 | $3,200.00 |
| 1010 | I-beam posts (9031210) | LB | 280 | $10.00 | $10.50 | $10.00 | $10.00 |
| 1020 | Pipe posts (9031220) | LB | 160 | $12.00 | $12.60 | $12.00 | $12.00 |
| 1030 | Breakaway assembly (perforated square steel tube) (9031241) | EACH | 1 | $400.00 | $420.00 | $400.00 | $400.00 |
| 1040 | 2 in. PSST post - 12 GA. (9031270A) | LF | 449 | $38.00 | $39.90 | $38.00 | $38.00 |
| 1050 | Driven post anchor for 2 in. PSST - 7 GA. (9031273A) | EACH | 32 | $300.00 | $315.00 | $300.00 | $300.00 |
| 1060 | Concrete post anchor for 2 in. PSST. - 7 GA. (9031274) | EACH | 9 | $350.00 | $368.00 | $350.00 | $350.00 |
| 1070 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 102 | $44.00 | $46.20 | $44.00 | $44.00 |
| 1080 | Driven post anchor for 2.5 in. PSST - 7 GA. (9031281A) | EACH | 9 | $350.00 | $368.00 | $350.00 | $350.00 |
| 1090 | SH-flat sheet (9035004A) | SF | 494 | $40.00 | $42.00 | $40.00 | $40.00 |
| 1100 | ST-structural (9035011A) | SF | 186 | $60.00 | $63.00 | $60.00 | $60.00 |
| 1110 | Aluminum backing bars (9035030) | LF | 5 | $12.00 | $12.60 | $12.00 | $12.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of October 16, 2026. Compiled by Mirage Metrics.