MoDOT contract 261016-F05 bid tabulation
JSLM0077 - ROUTE 141 OR - JEFFERSON COUNTY. Let by Missouri DOT on October 16, 2026, Jefferson, St. Louis. 5 bids received; low bid $396,589 by Jokerst Paving & Contracting, Inc..
- Owner
- Missouri DOT
- Letting
- 16 OCT 2026
- Pay items
- 39
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jokerst Paving & Contracting, Inc. | $396,589 | Low |
| 2 | K.J.U., Inc. dba K.J. Unnerstall Construction Co. | $422,244 | +6.0% |
| 3 | Gershenson Construction Co., Inc. | $432,419 | +9.0% |
| 4 | Pace Construction Company, LLC | $508,737 | +28% |
| 5 | Lamke Trenching & Excavating, Inc. | $586,823 | +48% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jokerst Paving & Contracting, Inc. | 2. K.J.U., Inc. dba K.J. Unnerstall Construction Co. | 3. Gershenson Construction Co., Inc. | 4. Pace Construction Company, LLC | 5. Lamke Trenching & Excavating, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $37,000 | $20,000 | $66,000 | $42,830 | $38,460 |
| 0020 | Embankment in place (2035500) | CY | 73 | $107.00 | $30.00 | $43.00 | $135.00 | $117.00 |
| 0030 | Class 3 excavation (2063000) | CY | 563 | $31.60 | $25.00 | $34.00 | $36.00 | $29.00 |
| 0040 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 74 | $21.10 | $19.00 | $25.00 | $72.00 | $25.00 |
| 0050 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 193.20 | $158.00 | $175.00 | $165.00 | $210.00 | $157.00 |
| 0060 | Tack coat - non-tracking (4071007) | GAL | 178 | $7.50 | $10.00 | $10.00 | $0.01 | $8.50 |
| 0070 | Concrete curb (6 in. height and under) type S (6091010) | LF | 22 | $58.00 | $73.00 | $137.00 | $114.00 | $337.00 |
| 0080 | Curb and gutter type A (6091051) | LF | 214 | $75.00 | $77.00 | $92.00 | $114.00 | $48.30 |
| 0090 | Integral curb (6 in. height and under) type A (6092011) | LF | 24 | $54.00 | $50.00 | $22.00 | $22.00 | $152.00 |
| 0100 | Integral curb type M (6092013) | LF | 58 | $32.90 | $40.00 | $116.00 | $22.00 | $128.00 |
| 0110 | Furnishing and placing concrete material for full depth pavement repair (6131010) | SY | 169.10 | $304.00 | $260.00 | $175.00 | $168.00 | $238.00 |
| 0120 | Subgrade compaction (6 in. depth) (pavement repair) (6131012) | SY | 169 | $6.00 | $10.00 | $1.00 | $25.00 | $1.00 |
| 0130 | Type 1 or 5 aggregate for base (4 in. thick) (pavement repair) (6131013) | SY | 169 | $16.10 | $20.00 | $1.00 | $48.00 | $1.00 |
| 0140 | Full depth pavement repair saw cut (for perimeter and internal saw cuts) (6131014) | LF | 356 | $4.83 | $8.50 | $3.00 | $6.00 | $7.00 |
| 0150 | Dowel bar (drilling, furnishing and installation) for full depth pavement repair (6131015) | EACH | 248 | $8.60 | $22.00 | $1.00 | $17.50 | $7.00 |
| 0160 | Curved vane grate and frame (2 FT. X 2 FT. or 600MM X 600MM) (6141120) | EACH | 2 | $1,020.00 | $1,500.00 | $1,114.00 | $3,500.00 | $1,200.00 |
| 0170 | Manhole frame and cover, type 1-A (6143010) | EACH | 1 | $900.00 | $800.00 | $1,162.00 | $510.00 | $857.00 |
| 0180 | Manhole frame and cover, type 3 (6143013) | EACH | 2 | $840.00 | $450.00 | $737.00 | $305.00 | $630.00 |
| 0190 | Work zone traffic signal system (6162000A) | EACH | 1 | $3,500.00 | $6,000.00 | $2,500.00 | $5,600.00 | $5,600.00 |
| 0200 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $6,400.00 | $22,000 | $5,600.00 | $6,204.00 | $6,204.00 |
| 0210 | Temporary traffic barrier, contractor furnished retained (6173600D) | LF | 375 | $28.60 | $31.00 | $5.00 | $27.76 | $27.76 |
| 0220 | Relocating temporary traffic barrier (6175010A) | LF | 375 | $12.10 | $13.00 | $1.00 | $11.68 | $11.68 |
| 0230 | Mobilization (6181000) | LS | 1 | $54,200 | $79,560 | $65,000 | $87,401 | $62,828 |
| 0240 | Temporary removable marking tape, 24 in., white (6205309) | LF | 48 | $10.30 | $50.00 | $10.00 | $10.00 | $10.00 |
| 0250 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 1,123 | $2.06 | $2.20 | $2.00 | $2.00 | $2.00 |
| 0260 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 1,122 | $2.06 | $2.20 | $2.00 | $2.00 | $2.00 |
| 0270 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 1,774 | $7.50 | $7.00 | $5.75 | $12.00 | $9.00 |
| 0280 | Contractor furnished surveying and staking (6274000) | LS | 1 | $2,500.00 | $2,500.00 | $20,000 | $100.00 | $2,000.00 |
| 0290 | 15 in. pipe group A (7261015) | LF | 441 | $129.00 | $130.00 | $153.00 | $226.00 | $397.00 |
| 0300 | 18 in. pipe group A (7261018) | LF | 116 | $137.00 | $143.00 | $191.00 | $242.00 | $478.00 |
| 0310 | Misc.reconnection of existing pipe to structure (7279901) | LS | 1 | $1,340.00 | $4,600.00 | $3,727.00 | $6,380.00 | $4,600.00 |
| 0320 | Precast concrete manhole - 48 in. (7310048) | FT | 10 | $650.00 | $550.00 | $670.00 | $339.00 | $811.00 |
| 0330 | Precast concrete drop inlet 2 FT X 2 FT (7311022) | FT | 14 | $910.00 | $850.00 | $898.00 | $628.00 | $1,600.00 |
| 0340 | Precast concrete drop inlet 3 FT X 2 FT-6 in. (7311030) | FT | 16 | $720.00 | $850.00 | $716.00 | $457.00 | $1,370.00 |
| 0350 | Turf type tall fescue sodding (8031000A) | SY | 307 | $21.00 | $15.00 | $16.25 | $16.25 | $16.25 |
| 0360 | Curb inlet check (8061007A) | EACH | 7 | $125.00 | $145.00 | $50.00 | $150.00 | $150.00 |
| 0370 | Sediment removal (8061016) | CY | 12 | $60.00 | $50.00 | $1.00 | $21.00 | $10.00 |
| 0380 | Silt fence (8061019) | LF | 353 | $4.00 | $2.00 | $2.00 | $9.00 | $9.00 |
| 0390 | Misc.remove and relocate existing ground mount sign (9039902) | EACH | 2 | $900.00 | $1,200.00 | $950.00 | $1,200.00 | $1,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of October 16, 2026. Compiled by Mirage Metrics.