Top Line Construction Corp.: NJDOT bid record
Top Line Construction Corp. submitted 12 bids on New Jersey DOT contracts in the data, from 28 SEP 2017 to 19 FEB 2026, and was the low bidder on 1 of them (8%). When it was not low, its total sat a median +29% above the low bid.
- Owner
- New Jersey DOT
- Low bid volume
- $8,386,039
- Latest bid
- 19 FEB 2026
- Data through
- 16 APR 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2017 | 2 | 0 | 0% |
| 2019 | 1 | 1 | 100% |
| 2020 | 2 | 0 | 0% |
| 2021 | 3 | 0 | 0% |
| 2023 | 2 | 0 | 0% |
| 2024 | 1 | 0 | 0% |
| 2026 | 1 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| N1 | 7 | 1 | 14% |
| C4 | 3 | 0 | 0% |
| C1 | 1 | 0 | 0% |
| N4 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Straw mulching | 809003M | SY | 12 | 11 (92%) | $0.24 | $1.00 |
| Bridge deck waterproof surface course | 555006M | T | 10 | 10 (100%) | $607.07 | $800.00 |
| Tack coat 76-22 | 401034M | GAL | 10 | 10 (100%) | $6.00 | $11.00 |
| Fertilizing and seeding, type A-3 | 806006P | SY | 11 | 9 (82%) | $0.25 | $1.75 |
| Detectable warning surface | 606084P | SY | 11 | 7 (64%) | $144.00 | $300.00 |
| Reset water valve box | 651255M | U | 10 | 7 (70%) | $29.12 | $75.00 |
| Reset gas valve box | 653084M | U | 10 | 7 (70%) | $29.12 | $60.00 |
| Fuel price adjustment | 160004M | DOL | 7 | 7 (100%) | $4,500.00 | $2,700.00 |
| Asphalt price adjustment | 160007M | DOL | 7 | 7 (100%) | $9,100.00 | $10,200 |
| Fertilizing and seeding, type F | 806018P | SY | 6 | 6 (100%) | $0.25 | $2.10 |
| Traffic stripes, latex, 4" | 159300M | LF | 13 | 4 (31%) | $0.22 | $0.26 |
| Full depth concrete pavement repair, HMA | 453006M | SY | 11 | 4 (36%) | $173.81 | $200.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Crisdel Group, Inc. | 12 | 7 of 12 |
| Schifano Construction Corp. | 10 | 7 of 10 |
| Black Rock Enterprises, LLC | 10 | 7 of 10 |
| Della Pello Paving, Inc. | 8 | 7 of 8 |
| D'Annunzio & Sons, Inc. | 6 | 4 of 6 |
| Tilcon New York, Inc. | 5 | 3 of 5 |
| South State, Inc. | 3 | 3 of 3 |
| Intercounty Paving Associates, LLC | 2 | 2 of 2 |
| Joseph Defino Trucking Co., Inc. T/A Defino Contrcting Co. | 2 | 1 of 2 |
| Green Construction, Inc. | 2 | 2 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 19 FEB 2026 | 26402 | N1 | Maintenance Roadway Contract N112 | 9 of 9 | $9,695,005 | +29% |
| 28 MAR 2024 | 24465 | C4 | ROUTE 1, CR522 TO THOMAS AVE HSR PILOT PROJECT | 4 of 5 | $7,378,589 | +12% |
| 23 FEB 2023 | 23405 | C4 | Maintenance Roadway Contract C217, DP 23405 | 8 of 8 | $12,797,918 | +27% |
| 24 JAN 2023 | 23401 | N4 | Maintenance Roadway Contract N110, DP 23401 | 6 of 7 | $12,913,661 | +37% |
| 08 APR 2021 | 21107 | N1 | Rt 31, Franklin Rd (CR 634) to Route 46 | 2 of 8 | $7,275,116 | +18% |
| 18 MAR 2021 | 21403 | C4 | Maintenance Roadway Contract C213, DP 21403 | 6 of 8 | $16,222,851 | +42% |
| 21 JAN 2021 | 20146 | N1 | ROUTE 1, COLLEGE RD TO CR 522 (STOUTS LANE/PROMENADE BLVD) | 7 of 7 | $4,344,878 | +50% |
| 18 JUN 2020 | 20125 | N1 | Rt 202, Childs Rd/N Maple to Academy Pl | 9 of 9 | $8,883,567 | +48% |
| 09 APR 2020 | 20111 | N1 | ROUTE 171 FROM ROUTE 130 TO LINCOLN AVENUE | 5 of 7 | $4,204,878 | +54% |
| 07 FEB 2019 | 18152 | N1 | ROUTE 57 FROM ROUTRE 22 TO ROUTE 31 | 1 of 6 | $8,386,039 | Low, 7.0% under the second |
| 17 OCT 2017 | 17142 | C1 | ROUTE 27 BRIDGE STREET TO FREDERIC ST | 7 of 7 | $4,012,963 | +22% |
| 28 SEP 2017 | 17141 | N1 | ROUTE 181 NORTHBOUND AND SOUTHBOUND | 2 of 5 | $1,774,097 | +8.0% |
How this record was read
NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
- Every bid counted here matched its published total to within one dollar; NJDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.