NYSDOT contract D265397 bid tabulation
LARGE CULVERT REPLACEMENTS MULTI SITE - CONTRACT 1. Let by New York State DOT on March 27, 2025, Herkimer, Montgomery, Region 02. 3 bids received; low bid $5,745,408 by BP Excavation LLC.
- Owner
- New York State DOT
- Letting
- 27 MAR 2025
- Pay items
- 130
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | BP Excavation LLC | $5,745,408 | Low |
| 2 | Slate Hill Constructors Inc | $6,030,164 | +5.0% |
| 3 | Bothar Construction LLC | $6,100,701 | +6.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BP Excavation LLC | 2. Slate Hill Constructors Inc | 3. Bothar Construction LLC |
|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $40,000 | $125,000 | $35,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 2,770 | $19.00 | $40.00 | $32.50 |
| 3 | Embankment In Place (203.03) | CY | 4,980 | $34.00 | $30.00 | $44.80 |
| 4 | Select Granular Fill (203.07) | CY | 1,573 | $61.00 | $95.00 | $92.80 |
| 5 | Select Structural Fill (203.21) | CY | 130 | $85.00 | $135.00 | $82.25 |
| 6 | (203.24010017) | 88 | $50.00 | $60.00 | $78.95 | |
| 7 | Sand Backfill (203.25) | CY | 5 | $190.00 | $205.00 | $158.75 |
| 8 | Structure Excavation (206.01) | CY | 9,058 | $13.00 | $40.00 | $35.00 |
| 9 | Trench and Culvert Excavation (206.0201) | CY | 314 | $35.00 | $50.00 | $31.50 |
| 10 | Geotextile Bedding (207.20) | SY | 932 | $2.50 | $12.00 | $6.00 |
| 11 | Geotextile Separation (207.21) | SY | 194 | $6.00 | $7.00 | $3.50 |
| 12 | Prefabricated Composite Structural Drain (207.26) | SY | 659 | $15.50 | $15.00 | $19.50 |
| 13 | Seed and Mulch – Temporary (209.1003) | SY | 3,582 | $3.50 | $4.00 | $2.50 |
| 14 | Check Dam, Prefabricated – Temporary (209.1105) | LF | 80 | $50.00 | $35.00 | $52.00 |
| 15 | Drainage Structure Inlet Protection, Prefabricated – Temporary (209.1703) | LF | 152 | $15.00 | $20.00 | $45.65 |
| 16 | Rolled Erosion Control Product, Class II Type B, Intermediate (209.190201) | SY | 800 | $8.00 | $8.00 | $5.35 |
| 17 | (209.23010009) | 1,460 | $11.90 | $12.00 | $12.00 | |
| 18 | Grouted Tiebacks (Temporary) (211.10) | EACH | 5 | $23,000 | $13,000 | $28,476 |
| 19 | Subbase Course, Type 2 (304.12) | CY | 1,404 | $77.00 | $95.00 | $88.00 |
| 20 | (404.0001) | TON | 81 | $90.00 | $90.00 | $90.00 |
| 21 | (404.0189) | TON | 159 | $193.00 | $205.00 | $178.00 |
| 22 | (404.0982) | TON | 487 | $278.00 | $205.00 | $168.00 |
| 23 | (404.2589) | TON | 935 | $207.00 | $200.00 | $140.00 |
| 24 | (404.4389) | TON | 235 | $182.00 | $145.00 | $127.00 |
| 25 | (404.4589) | TON | 370 | $140.00 | $145.00 | $142.00 |
| 26 | Diluted Tack Coat (407.0102) | GAL | 690 | $4.50 | $45.00 | $6.65 |
| 27 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,438 | $2.10 | $2.00 | $1.15 |
| 28 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 3,100 | $13.00 | $19.00 | $12.25 |
| 29 | Temporary Steel Sheeting (552.13) | SF | 1,800 | $55.00 | $20.00 | $31.05 |
| 30 | Interim Steel Sheeting (552.15) | SF | 2,360 | $55.00 | $30.00 | $41.80 |
| 31 | Shields and Shoring (552.17) | SF | 400 | $25.00 | $1.00 | $4.65 |
| 32 | (553.020001) | EACH | 1 | $10,000 | $1.00 | $17,300 |
| 33 | (553.020002) | EACH | 1 | $10,000 | $1.00 | $17,300 |
| 34 | (553.030001) | EACH | 1 | $40,000 | $1.00 | $17,300 |
| 35 | (553.030002) | EACH | 1 | $32,000 | $1.00 | $17,800 |
| 36 | (553.030003) | EACH | 1 | $12,000 | $1.00 | $17,800 |
| 37 | (553.030004) | EACH | 1 | $30,000 | $1.00 | $38,000 |
| 38 | (554.3001) | SF | 690 | $86.00 | $65.00 | $44.35 |
| 39 | Footing Concrete, Performance (555.0011) | CY | 125 | $1,100.00 | $1,080.00 | $1,071.75 |
| 40 | Concrete for Structures, Performance (555.0021) | CY | 56 | $2,100.00 | $2,800.00 | $2,441.50 |
| 41 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 1 | $6.00 | $6.00 | $6.00 |
| 42 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $12.00 | $12.00 | $12.00 |
| 43 | Uncoated Bar Reinforcement for Concrete Structures (556.0201) | LB | 6,100 | $3.00 | $2.00 | $2.15 |
| 44 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 5,819 | $3.00 | $2.25 | $2.15 |
| 45 | (562.0101) | SY | 95 | $2,000.00 | $1,500.00 | $2,104.95 |
| 46 | Performance Concrete Quality Adjustment (562.99) | QUALITY UNIT | 1 | $17.00 | $17.00 | $17.00 |
| 47 | Steel Bridge Railing (Three-Rail) (568.54) | LF | 111 | $270.00 | $285.00 | $305.10 |
| 48 | Transition Bridge Railing (568.70) | LF | 320 | $188.00 | $200.00 | $211.90 |
| 49 | Removal of Structural Concrete (580.01) | CY | 23 | $110.00 | $1,200.00 | $500.00 |
| 50 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 240 | $26.00 | $42.00 | $42.30 |
| 51 | (595.50000018) | 5,125 | $3.00 | $10.00 | $4.50 | |
| 52 | (603.171116) | EACH | 2 | $515.00 | $500.00 | $510.00 |
| 53 | (603.171614) | EACH | 2 | $1,000.00 | $750.00 | $2,175.35 |
| 54 | (603.63130715) | 56 | $4,600.00 | $3,750.00 | $5,076.25 | |
| 55 | (603.63190915) | 34 | $7,940.00 | $6,250.00 | $8,587.00 | |
| 56 | (603.64100615) | 72 | $2,600.00 | $2,600.00 | $2,917.75 | |
| 57 | (603.65171015) | 46 | $8,560.00 | $5,750.00 | $7,102.25 | |
| 58 | (603.67000001) | 219 | $1,700.00 | $1,500.00 | $1,366.85 | |
| 59 | (603.9812) | LF | 30 | $51.00 | $32.00 | $61.25 |
| 60 | (603.9815) | LF | 48 | $47.00 | $30.00 | $49.00 |
| 61 | (604.300673) | LF | 10 | $1,100.00 | $750.00 | $1,287.00 |
| 62 | Underdrain Filter, Type II (605.1001) | CY | 27 | $56.00 | $115.00 | $110.00 |
| 63 | (605.1701) | LF | 289 | $10.00 | $7.50 | $11.75 |
| 64 | Box Beam Guide Railing (606.10) | LF | 2,582 | $48.00 | $49.00 | $53.35 |
| 65 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 8 | $4,400.00 | $4,600.00 | $4,938.10 |
| 66 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 6 | $2,200.00 | $2,310.00 | $2,457.75 |
| 67 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 1,578 | $4.00 | $4.50 | $3.15 |
| 68 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 9 | $500.00 | $350.00 | $659.15 |
| 69 | (607.41010010) | 213 | $2.00 | $12.50 | $9.65 | |
| 70 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $90.00 | $90.00 | $90.00 |
| 71 | Concrete Sidewalks and Driveways (608.0101) | CY | 50 | $1,100.00 | $1,200.00 | $1,760.00 |
| 72 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 24 | $325.00 | $263.00 | $220.00 |
| 73 | Stone Curb – Near Vertical Face (NVF) (609.0212) | LF | 177 | $260.00 | $210.00 | $275.00 |
| 74 | (609.0401) | LF | 340 | $80.00 | $80.00 | $78.00 |
| 75 | Topsoil – Reuse On-Site Materials (610.1401) | CY | 26 | $25.00 | $45.00 | $53.75 |
| 76 | Turf Establishment – Performance (610.1605) | SY | 3,923 | $6.00 | $20.00 | $12.75 |
| 77 | (611.0311) | EACH | 1 | $875.00 | $900.00 | $988.75 |
| 78 | (613.04000001) | 358 | $40.00 | $50.00 | $39.00 | |
| 79 | (617.10000024) | 150 | $20.00 | $40.00 | $55.85 | |
| 80 | (617.11000024) | LS | 1 | $1,000.00 | $1,000.00 | $14,500 |
| 81 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $80,000 | $580,000 | $249,944 |
| 82 | Type III Construction Barricades (619.04) | EACH | 65 | $50.00 | $50.00 | $120.00 |
| 83 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 1,700 | $7.00 | $8.00 | $7.90 |
| 84 | (619.100103) | LF | 6,500 | $6.00 | $7.00 | $6.80 |
| 85 | (619.110513) | EACH | 8 | $6,000.00 | $6,200.00 | $3,966.00 |
| 86 | (619.1301) | EACH | 1 | $65,000 | $35,000 | $67,461 |
| 87 | (619.1302) | EACH | 1 | $80,000 | $45,000 | $58,760 |
| 88 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 232 | $70.00 | $40.00 | $57.35 |
| 89 | Temporary Positive Barrier – Category 3 (Pinning Prohibited) (619.1713) | LF | 129 | $90.00 | $40.00 | $85.85 |
| 90 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 880 | $100.00 | $50.00 | $79.00 |
| 91 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 3,900 | $85.00 | $50.00 | $52.50 |
| 92 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 120 | $50.00 | $63.00 | $59.20 |
| 93 | Temporary Rumble Strips (619.22) | LF | 360 | $16.00 | $17.00 | $18.10 |
| 94 | Stone Filling (Light) (620.03) | CY | 23 | $160.00 | $210.00 | $145.00 |
| 95 | Stone Filling (Medium) (620.04) | CY | 110 | $128.00 | $135.00 | $144.00 |
| 96 | Stone Filling (Heavy) (620.05) | CY | 445 | $132.00 | $140.00 | $159.00 |
| 97 | Bedding Material, Type 1 (620.0801) | CY | 165 | $90.00 | $115.00 | $124.55 |
| 98 | Bedding Material, Type 2 (620.0802) | CY | 31 | $70.00 | $140.00 | $120.60 |
| 99 | (621.51000015) | 25 | $15.00 | $13.00 | $23.65 | |
| 100 | Survey Operations (625.01) | LS | 1 | $75,000 | $58,000 | $95,400 |
| 101 | Concrete Right of Way Markers Type H (High) (625.03) | EACH | 17 | $2,000.00 | $800.00 | $1,136.00 |
| 102 | (625.09010015) | LS | 1 | $16,500 | $5,000.00 | $3,000.00 |
| 103 | (627.50140008) | 1,564 | $4.00 | $5.50 | $6.75 | |
| 104 | Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401) | SY | 20 | $300.00 | $240.00 | $265.00 |
| 105 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $500.00 | $2,000.00 | $7,000.00 |
| 106 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 24 | $1,500.00 | $3,800.00 | $2,500.00 |
| 107 | Office Technology and Supplies (637.34) | DOL | 2,500 | $1.00 | $1.00 | $1.00 |
| 108 | (637.41000115) | 24 | $1,000.00 | $70.00 | $105.00 | |
| 109 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 21 | $43.00 | $45.00 | $47.75 |
| 110 | Type A Sign Posts (645.81) | EACH | 4 | $235.00 | $250.00 | $265.55 |
| 111 | Reference Marker Panel (646.21) | EACH | 1 | $55.00 | $55.00 | $59.05 |
| 112 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 32 | $21.00 | $22.00 | $23.45 |
| 113 | Reference Marker, Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels Relocation (646.24) | EACH | 3 | $39.00 | $40.00 | $43.50 |
| 114 | Steel Post, 2.0 lb/ft (646.32) | EACH | 27 | $86.00 | $90.00 | $96.65 |
| 115 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 2 | $133.00 | $140.00 | $149.75 |
| 116 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 26 | $51.00 | $53.00 | $56.50 |
| 117 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 2 | $2,500.00 | $2,500.00 | $2,446.00 |
| 118 | (662.01000107) | LS | 1 | $3,000.00 | $5,000.00 | $21,357 |
| 119 | (663.0110) | LF | 75 | $156.00 | $200.00 | $208.00 |
| 120 | (663.0420) | LF | 23 | $210.00 | $150.00 | $230.70 |
| 121 | (663.1010) | EACH | 2 | $3,500.00 | $5,500.00 | $6,050.00 |
| 122 | Iron Water Main Fittings (10 - 16 inch diameter) (663.2002) | LB | 520 | $6.25 | $8.00 | $4.75 |
| 123 | (663.2110) | EACH | 8 | $225.00 | $500.00 | $152.45 |
| 124 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 5,596 | $5.50 | $6.00 | $6.25 |
| 125 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 3,468 | $5.50 | $6.00 | $6.25 |
| 126 | Field Change Payment (FCP) (697.03) | DOL | 230,000 | $1.00 | $1.00 | $1.00 |
| 127 | Asphalt Price Adjustment (698.04) | DOL | 2,602 | $1.00 | $1.00 | $1.00 |
| 128 | Fuel Price Adjustment (698.05) | DOL | 2,893 | $1.00 | $1.00 | $1.00 |
| 129 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 130 | Mobilization (699.040001) | LS | 1 | $150,000 | $200,000 | $230,584 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 27, 2025. Compiled by Mirage Metrics.