NYSDOT contract D265530 bid tabulation
PAVEMENT REHABILITATION - Rte 46, Lansingkill to Holmes Rd. Let by New York State DOT on July 10, 2025, Oneida, Region 02. 3 bids received; low bid $7,312,132 by Dolomite Products Co Inc.
- Owner
- New York State DOT
- Letting
- 10 JUL 2025
- Pay items
- 111
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dolomite Products Co Inc | $7,312,132 | Low |
| 2 | Sealand Contractors Corp. | $9,504,000 | +30% |
| 3 | Barrett Paving Materials Inc | $9,727,626 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dolomite Products Co Inc | 2. Sealand Contractors Corp. | 3. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|
| 1 | (201.07000004) | 18,125 | $6.25 | $7.50 | $7.00 | |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 2,300 | $39.00 | $60.00 | $81.00 |
| 3 | Embankment In Place (203.03) | CY | 220 | $39.00 | $30.00 | $88.00 |
| 4 | Select Granular Fill (203.07) | CY | 420 | $115.00 | $85.00 | $161.00 |
| 5 | (203.24010017) | 1,000 | $61.00 | $75.00 | $58.00 | |
| 6 | Trench and Culvert Excavation (206.0201) | CY | 1,000 | $78.00 | $62.00 | $83.50 |
| 7 | Geotextile Separation (207.21) | SY | 290 | $1.00 | $5.00 | $0.80 |
| 8 | Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301) | SY | 2,000 | $5.76 | $6.05 | $5.76 |
| 9 | Stabilized Construction Access (209.22) | SY | 250 | $20.00 | $70.00 | $33.02 |
| 10 | Sediment Filter Log, 12″ (209.2301) | LF | 3,800 | $10.00 | $8.50 | $8.00 |
| 11 | (210.290201) | SF | 50 | $250.00 | $105.00 | $20.00 |
| 12 | Subbase Course, Type 2 (304.12) | CY | 1,800 | $70.00 | $91.00 | $88.00 |
| 13 | (404.0001) | TON | 801 | $90.00 | $90.00 | $90.00 |
| 14 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1 | $90.00 | $90.00 | $90.00 |
| 15 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 260 | $90.00 | $90.00 | $90.00 |
| 16 | (404.0962) | TON | 9,200 | $103.00 | $136.00 | $127.00 |
| 17 | (404.1969) | TON | 15,500 | $88.00 | $116.00 | $108.00 |
| 18 | (404.2589) | TON | 520 | $275.00 | $230.00 | $156.00 |
| 19 | Straight Tack Coat (407.0103) | GAL | 11,000 | $7.00 | $9.80 | $2.35 |
| 20 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 36,000 | $0.95 | $1.65 | $0.63 |
| 21 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 105,000 | $1.75 | $4.65 | $4.50 |
| 22 | (553.020001) | EACH | 1 | $7,500.00 | $5,000.00 | $15,000 |
| 23 | Concrete for Structures, Performance (555.0021) | CY | 3 | $5,000.00 | $12,500 | $11,000 |
| 24 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $9.89 | $9.89 | $9.89 |
| 25 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 1,650 | $5.00 | $6.00 | $15.00 |
| 26 | Protective Sealing of New Structural Concrete (559.02) | SF | 235 | $10.00 | $8.00 | $4.00 |
| 27 | Steel Bridge Railing (Three-Rail) (568.54) | LF | 44 | $310.00 | $355.00 | $281.00 |
| 28 | Transition Bridge Railing (568.70) | LF | 128 | $188.00 | $195.00 | $176.00 |
| 29 | Removal of Structural Concrete (580.01) | CY | 1 | $10,000 | $9,000.00 | $6,600.00 |
| 30 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 250 | $80.00 | $150.00 | $65.00 |
| 31 | Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test (586.0301) | EACH | 106 | $100.00 | $200.00 | $151.00 |
| 32 | Bridge Railing Removal and Disposal (587.01) | LF | 36 | $75.00 | $30.00 | $75.00 |
| 33 | (603.171016) | EACH | 6 | $500.00 | $1,050.00 | $210.00 |
| 34 | (603.171116) | EACH | 2 | $700.00 | $1,075.00 | $120.00 |
| 35 | (603.171416) | EACH | 46 | $600.00 | $1,100.00 | $540.00 |
| 36 | (603.171614) | EACH | 6 | $1,000.00 | $1,500.00 | $820.00 |
| 37 | (603.17161501) | 6 | $900.00 | $1,600.00 | $690.00 | |
| 38 | (603.17161801) | 10 | $1,300.00 | $2,100.00 | $1,630.00 | |
| 39 | (603.171814) | EACH | 2 | $1,400.00 | $1,900.00 | $1,300.00 |
| 40 | (603.172012) | EACH | 2 | $3,000.00 | $3,800.00 | $4,400.00 |
| 41 | (603.182310) | EACH | 1 | $7,000.00 | $6,500.00 | $6,200.00 |
| 42 | (603.6005) | LF | 107 | $130.00 | $250.00 | $154.00 |
| 43 | (603.87020015) | 70 | $120.00 | $160.00 | $232.00 | |
| 44 | (603.97000002) | 5 | $350.00 | $1,400.00 | $480.00 | |
| 45 | (603.9824) | LF | 327 | $100.00 | $220.00 | $110.00 |
| 46 | (603.9830) | LF | 53 | $110.00 | $300.00 | $129.00 |
| 47 | (604.070201) | EACH | 4 | $1,800.00 | $5,000.00 | $2,000.00 |
| 48 | (604.070202) | EACH | 6 | $2,000.00 | $7,000.00 | $3,600.00 |
| 49 | (604.300611) | LF | 22 | $1,250.00 | $1,400.00 | $1,450.00 |
| 50 | Box Beam Guide Railing (606.10) | LF | 3,700 | $43.00 | $49.00 | $44.60 |
| 51 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 600 | $47.00 | $61.00 | $54.85 |
| 52 | Box Beam Guide Railing (Shop Mitered) (606.100003) | LF | 12 | $135.00 | $116.00 | $105.00 |
| 53 | Box Beam Guide Railing With Extra Long Posts (606.1001) | LF | 19,000 | $47.00 | $51.50 | $46.80 |
| 54 | Box Beam Guide Railing with Extra Long Posts (Shop Bent or Shop Mitered) (606.100102) | LF | 2,100 | $50.00 | $60.50 | $54.75 |
| 55 | Box Beam End Piece (606.120101) | EACH | 5 | $700.00 | $630.00 | $570.00 |
| 56 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 20 | $4,035.00 | $4,500.00 | $4,090.00 |
| 57 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 16 | $1,930.00 | $2,400.00 | $2,160.00 |
| 58 | Box Beam End Assembly Type III (606.1203) | EACH | 2 | $7,500.00 | $7,100.00 | $6,400.00 |
| 59 | Removing and Disposing Cable Guide Railing (606.70) | LF | 300 | $3.00 | $1.80 | $1.55 |
| 60 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 23,750 | $2.50 | $2.25 | $2.00 |
| 61 | Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79) | EACH | 2 | $700.00 | $150.00 | $125.00 |
| 62 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 49 | $150.00 | $29.00 | $25.00 |
| 63 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 100 | $275.00 | $450.00 | $184.00 |
| 64 | Resetting Existing Curb (609.15) | LF | 35 | $100.00 | $200.00 | $57.00 |
| 65 | Turf Establishment – Performance (610.1605) | SY | 3,200 | $1.60 | $24.00 | $17.00 |
| 66 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $518,763 | $643,874 | $1,300,000 |
| 67 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 2,520 | $7.75 | $8.15 | $3.50 |
| 68 | (619.0901) | LF | 197,000 | $0.25 | $0.25 | $0.25 |
| 69 | (619.100101) | LF | 8,300 | $0.25 | $0.46 | $0.25 |
| 70 | (619.110513) | EACH | 2 | $15,000 | $22,000 | $14,950 |
| 71 | (619.130201) | EACH | 1 | $20,000 | $30,000 | $22,000 |
| 72 | (619.130202) | EACH | 1 | $20,000 | $30,000 | $22,000 |
| 73 | (619.130203) | EACH | 1 | $10,000 | $30,000 | $14,000 |
| 74 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 620 | $40.00 | $60.00 | $20.00 |
| 75 | Pavement Patching (Tonnage) (619.2602) | TON | 150 | $600.00 | $450.00 | $670.00 |
| 76 | Mailboxes (619.27) | EACH | 1 | $1,000.00 | $1,200.00 | $740.00 |
| 77 | Stone Filling (Light) (620.03) | CY | 200 | $150.00 | $180.00 | $147.00 |
| 78 | Stone Filling (Medium) (620.04) | CY | 375 | $160.00 | $220.00 | $210.00 |
| 79 | (620.14020009) | 22 | $500.00 | $500.00 | $1,000.00 | |
| 80 | Cleaning Culverts with Span of 50 in. or Less (621.01) | LF | 3,050 | $5.50 | $6.00 | $5.35 |
| 81 | Cleaning Drainage Structures (621.04) | EACH | 15 | $215.00 | $240.00 | $215.00 |
| 82 | (621.51050003) | 28,500 | $5.00 | $12.00 | $21.00 | |
| 83 | (621.51970008) | 260 | $30.00 | $45.00 | $54.00 | |
| 84 | (624.01) | 1,300 | $40.00 | $60.00 | $28.00 | |
| 85 | Survey Operations (625.01) | LS | 1 | $60,000 | $94,000 | $69,820 |
| 86 | (625.09010015) | LS | 1 | $15,000 | $22,000 | $63,995 |
| 87 | (627.50140008) | 4,150 | $5.00 | $6.00 | $4.80 | |
| 88 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1,000.00 | $10,000 | $6,100.00 |
| 89 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 18 | $3,000.00 | $2,500.00 | $3,900.00 |
| 90 | Office Technology and Supplies (637.34) | DOL | 1,000 | $1.00 | $1.00 | $1.00 |
| 91 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 510 | $37.00 | $59.00 | $36.00 |
| 92 | Type A Sign Posts (645.81) | EACH | 80 | $270.00 | $288.00 | $210.00 |
| 93 | (645.81090003) | 4 | $75.00 | $80.00 | $81.00 | |
| 94 | Reference Marker Panel (646.21) | EACH | 70 | $43.00 | $57.00 | $25.00 |
| 95 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 800 | $24.00 | $26.50 | $25.00 |
| 96 | Steel Post, 1.1 lb/ft (646.31) | EACH | 60 | $88.00 | $90.00 | $75.00 |
| 97 | Steel Post, 2.0 lb/ft (646.32) | EACH | 355 | $100.00 | $105.00 | $100.00 |
| 98 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 1 | $185.00 | $220.00 | $150.00 |
| 99 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 12 | $65.00 | $44.00 | $45.00 |
| 100 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 81 | $60.00 | $22.00 | $45.00 |
| 101 | (647.83001002) | 87 | $12.00 | $14.00 | $25.00 | |
| 102 | Welded Frame & Reticuline Grate 11 (655.1111) | EACH | 9 | $1,500.00 | $1,400.00 | $1,250.00 |
| 103 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 100,000 | $0.30 | $0.30 | $0.55 |
| 104 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 64,000 | $0.30 | $0.30 | $0.55 |
| 105 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 250 | $8.00 | $8.50 | $2.50 |
| 106 | (691.04000020) | 55,000 | $1.00 | $1.00 | $1.00 | |
| 107 | Field Change Payment (FCP) (697.03) | DOL | 360,000 | $1.00 | $1.00 | $1.00 |
| 108 | Asphalt Price Adjustment (698.04) | DOL | 21,419.45 | $1.00 | $1.00 | $1.00 |
| 109 | Fuel Price Adjustment (698.05) | DOL | 9,765 | $1.00 | $1.00 | $1.00 |
| 110 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 111 | Mobilization (699.040001) | LS | 1 | $275,000 | $365,000 | $374,096 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of July 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way