NYSDOT contract D265544 bid tabulation
REPLACEMENT OF ROUTE 30 CULVERT OVER HATCHERY BROOK. Let by New York State DOT on September 11, 2025, Hamilton, Region 02. 2 bids received; low bid $2,095,459 by Kubricky-Jointa Lime LLC.
- Owner
- New York State DOT
- Letting
- 11 SEP 2025
- Pay items
- 70
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Kubricky-Jointa Lime LLC | $2,095,459 | Low |
| 2 | Slate Hill Constructors Inc | $2,414,025 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kubricky-Jointa Lime LLC | 2. Slate Hill Constructors Inc |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $23,300 | $30,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 600 | $29.00 | $35.00 |
| 3 | Embankment In Place (203.03) | CY | 3,900 | $15.50 | $50.00 |
| 4 | Select Structural Fill (203.21) | CY | 825 | $98.50 | $85.00 |
| 5 | (203.24010017) | 8 | $235.00 | $160.00 | |
| 6 | Structure Excavation (206.01) | CY | 6,800 | $13.00 | $45.00 |
| 7 | Trench and Culvert Excavation (206.0201) | CY | 90 | $24.00 | $45.00 |
| 8 | Geotextile Bedding (207.20) | SY | 225 | $5.95 | $8.00 |
| 9 | Prefabricated Composite Structural Drain (207.26) | SY | 210 | $17.00 | $18.00 |
| 10 | Seed and Mulch – Temporary (209.1003) | SY | 2,300 | $1.65 | $1.75 |
| 11 | Rolled Erosion Control Product, Class II Type B, Intermediate (209.190201) | SY | 115 | $6.85 | $14.00 |
| 12 | (209.23010009) | 1,010 | $9.40 | $12.00 | |
| 13 | Subbase Course, Type 2 (304.12) | CY | 715 | $125.00 | $90.00 |
| 14 | (404.0001) | TON | 22 | $90.00 | $90.00 |
| 15 | (404.0189) | TON | 12 | $280.00 | $270.00 |
| 16 | (404.0982) | TON | 120 | $180.00 | $175.00 |
| 17 | (404.2589) | TON | 310 | $170.00 | $165.00 |
| 18 | (404.4389) | TON | 110 | $180.00 | $175.00 |
| 19 | (404.4589) | TON | 210 | $180.00 | $170.00 |
| 20 | Diluted Tack Coat (407.0102) | GAL | 145 | $39.00 | $38.00 |
| 21 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 400 | $5.60 | $6.00 |
| 22 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 390 | $58.50 | $22.00 |
| 23 | (553.020001) | EACH | 1 | $7,100.00 | $1.00 |
| 24 | (553.020002) | EACH | 1 | $7,100.00 | $1.00 |
| 25 | (554.3001) | SF | 1,600 | $88.00 | $70.00 |
| 26 | Footing Concrete, Performance (555.0011) | CY | 51 | $1,100.00 | $1,500.00 |
| 27 | Concrete for Structures, Performance (555.0021) | CY | 50 | $2,050.00 | $2,250.00 |
| 28 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 1 | $6.00 | $6.00 |
| 29 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $11.00 | $11.00 |
| 30 | Uncoated Bar Reinforcement for Concrete Structures (556.0201) | LB | 8,325 | $2.35 | $2.25 |
| 31 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 1,960 | $3.15 | $2.75 |
| 32 | (562.0101) | SY | 124 | $1,750.00 | $1,600.00 |
| 33 | Invert Slab With Cut-Off Wall (562.02) | SY | 138 | $1,150.00 | $1,200.00 |
| 34 | Performance Concrete Quality Adjustment (562.99) | QUALITY UNIT | 1 | $13.31 | $13.31 |
| 35 | (595.50000018) | 2,200 | $4.95 | $4.00 | |
| 36 | (603.171614) | EACH | 2 | $1,450.00 | $800.00 |
| 37 | (603.9824) | LF | 20 | $100.00 | $50.00 |
| 38 | Box Beam Guide Railing (606.10) | LF | 1,188 | $49.00 | $45.00 |
| 39 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 4 | $4,500.00 | $4,200.00 |
| 40 | Topsoil – Reuse On-Site Materials (610.1401) | CY | 50 | $120.00 | $40.00 |
| 41 | (610.16020224) | 850 | $3.70 | $3.50 | |
| 42 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $256,000 | $300,000 |
| 43 | Type III Construction Barricades (619.04) | EACH | 8 | $61.50 | $50.00 |
| 44 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 1,100 | $6.60 | $7.00 |
| 45 | (619.100103) | LF | 5,100 | $5.50 | $6.00 |
| 46 | (619.110513) | EACH | 2 | $1,900.00 | $6,750.00 |
| 47 | (619.130201) | EACH | 1 | $21,300 | $40,000 |
| 48 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 1,660 | $53.00 | $55.00 |
| 49 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 63 | $26.50 | $15.00 |
| 50 | Temporary Rumble Strips (619.22) | LF | 176 | $11.50 | $20.00 |
| 51 | Stone Filling (Light) (620.03) | CY | 16 | $350.00 | $150.00 |
| 52 | Stone Filling (Heavy) (620.05) | CY | 210 | $170.00 | $160.00 |
| 53 | Bedding Material, Type 1 (620.0801) | CY | 52 | $160.00 | $110.00 |
| 54 | (620.29110009) | 125 | $210.00 | $125.00 | |
| 55 | Crushed Stone (In-Place Measure) (623.12) | CY | 60 | $205.00 | $115.00 |
| 56 | Survey Operations (625.01) | LS | 1 | $17,200 | $20,000 |
| 57 | (627.50140008) | 68 | $8.35 | $10.00 | |
| 58 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $560.00 | $100.00 |
| 59 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 5 | $4,850.00 | $2,550.00 |
| 60 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 |
| 61 | (637.41000115) | 5 | $1,100.00 | $600.00 | |
| 62 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 8 | $27.50 | $26.00 |
| 63 | Steel Post, 2.0 lb/ft (646.32) | EACH | 6 | $110.00 | $100.00 |
| 64 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 1,550 | $6.70 | $5.50 |
| 65 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 650 | $6.70 | $5.50 |
| 66 | Field Change Payment (FCP) (697.03) | DOL | 89,600 | $1.00 | $1.00 |
| 67 | Asphalt Price Adjustment (698.04) | DOL | 488 | $1.00 | $1.00 |
| 68 | Fuel Price Adjustment (698.05) | DOL | 450 | $1.00 | $1.00 |
| 69 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 70 | Mobilization (699.040001) | LS | 1 | $75,000 | $80,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of September 11, 2025. Compiled by Mirage Metrics.