NYSDOT contract D265579 bid tabulation
INTERSECTION IMPROVEMENT PROJECT-Rt 46/Wright Settlement Rd. Let by New York State DOT on December 4, 2025, Oneida, Region 02. 3 bids received; low bid $1,895,588 by Central Paving Inc..
- Owner
- New York State DOT
- Letting
- 04 DEC 2025
- Pay items
- 128
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Central Paving Inc. | $1,895,588 | Low |
| 2 | Cci Companies Inc | $2,384,752 | +26% |
| 3 | Barrett Paving Materials Inc | $2,660,976 | +40% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Central Paving Inc. | 2. Cci Companies Inc | 3. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 1,195 | $40.00 | $95.50 | $80.00 |
| 2 | Embankment In Place (203.03) | CY | 55 | $100.00 | $130.00 | $14.00 |
| 3 | Select Granular Fill (203.07) | CY | 600 | $65.00 | $120.00 | $110.00 |
| 4 | (203.24010017) | 17 | $75.00 | $240.00 | $95.00 | |
| 5 | (203.98080015) | 150 | $15.00 | $18.00 | $13.50 | |
| 6 | Controlled Low Strength Material (CLSM) (204.01) | CY | 30 | $450.00 | $300.00 | $400.00 |
| 7 | (205.0201) | LS | 1 | $3,500.00 | $4,000.00 | $4,455.00 |
| 8 | Field Organic Vapor Monitoring of Contaminated Soil (205.03) | HR | 6 | $200.00 | $300.00 | $202.50 |
| 9 | (205.050201) | TON | 12 | $250.00 | $180.00 | $220.00 |
| 10 | Trench and Culvert Excavation (206.0201) | CY | 745 | $60.00 | $118.00 | $75.00 |
| 11 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 625 | $15.00 | $55.00 | $35.00 |
| 12 | Test Pit Excavation (206.05) | EACH | 3 | $1,000.00 | $1,700.00 | $1,600.00 |
| 13 | Geotextile Separation (207.21) | SY | 60 | $8.00 | $14.00 | $4.00 |
| 14 | Sediment Filter Log, 12″ (209.2301) | LF | 2,125 | $10.00 | $11.00 | $8.00 |
| 15 | Subbase Course, Type 2 (304.12) | CY | 625 | $80.00 | $240.00 | $160.00 |
| 16 | (404.0189) | TON | 15 | $250.00 | $550.00 | $250.00 |
| 17 | (404.1272) | TON | 800 | $120.00 | $170.00 | $170.00 |
| 18 | (404.1979) | TON | 165 | $225.00 | $250.00 | $310.00 |
| 19 | (404.3779) | TON | 250 | $250.00 | $205.00 | $225.00 |
| 20 | Straight Tack Coat (407.0103) | GAL | 475 | $12.00 | $2.90 | $2.62 |
| 21 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 10,400 | $1.00 | $1.40 | $0.60 |
| 22 | (490.17011018) | 6,500 | $2.00 | $10.00 | $9.00 | |
| 23 | PCC Foundation for Pavement, PEM Concrete (503.1013) | CY | 65 | $715.00 | $680.00 | $850.00 |
| 24 | (520.60900002) | 15 | $100.00 | $18.00 | $80.00 | |
| 25 | Shields and Shoring (552.17) | SF | 2,825 | $1.00 | $1.30 | $1.20 |
| 26 | (603.171216) | EACH | 1 | $500.00 | $700.00 | $205.00 |
| 27 | (603.17161801) | 1 | $1,750.00 | $2,100.00 | $1,190.00 | |
| 28 | (603.6002) | LF | 376 | $50.00 | $65.00 | $80.00 |
| 29 | (603.6003) | LF | 642 | $60.00 | $68.00 | $90.00 |
| 30 | (603.9818) | LF | 110 | $30.00 | $52.00 | $60.00 |
| 31 | (604.070202) | EACH | 4 | $1,700.00 | $1,600.00 | $4,500.00 |
| 32 | (604.13000011) | 1 | $300.00 | $1,000.00 | $1,500.00 | |
| 33 | (604.301873) | LF | 40 | $550.00 | $670.00 | $1,000.00 |
| 34 | (605.03010015) | 1,750 | $25.00 | $28.00 | $25.00 | |
| 35 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $90.00 | $90.00 | $90.00 |
| 36 | Concrete Sidewalks and Driveways (608.0101) | CY | 160 | $1,100.00 | $930.00 | $1,100.00 |
| 37 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 70 | $225.00 | $365.00 | $220.00 |
| 38 | (608.21000003) | 15 | $225.00 | $80.00 | $425.00 | |
| 39 | Stone Curb – Near Vertical Face (NVF) (609.0212) | LF | 50 | $100.00 | $130.00 | $200.00 |
| 40 | (609.0401) | LF | 2,250 | $45.00 | $58.00 | $85.00 |
| 41 | Compost (610.10) | CY | 50 | $125.00 | $38.00 | $130.00 |
| 42 | Mulch for Planting Type E – Pine Nugget (610.1103) | CY | 2 | $150.00 | $240.00 | $200.00 |
| 43 | Permeable Weed Control Landscape Fabric (610.1201) | SY | 20 | $10.00 | $6.15 | $5.00 |
| 44 | Topsoil - Roadside (610.1402) | CY | 150 | $90.00 | $120.00 | $120.00 |
| 45 | Turf Establishment – Performance (610.1605) | SY | 875 | $2.00 | $7.30 | $15.00 |
| 46 | Sodding (610.18) | SY | 825 | $13.00 | $16.00 | $13.00 |
| 47 | Watering Vegetation (610.19) | 1,000 GALLONS | 3 | $100.00 | $120.00 | $100.00 |
| 48 | (611.0341) | EACH | 1 | $550.00 | $300.00 | $250.00 |
| 49 | (611.0422) | EACH | 24 | $90.00 | $100.00 | $85.00 |
| 50 | (611.0451) | EACH | 3 | $150.00 | $310.00 | $85.00 |
| 51 | (611.19030024) | 1 | $20.00 | $60.00 | $50.00 | |
| 52 | (611.19040024) | 27 | $5.00 | $24.00 | $20.00 | |
| 53 | (616.20000024) | 280 | $80.00 | $100.00 | $55.00 | |
| 54 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $152,000 | $65,000 | $463,109 |
| 55 | Type III Construction Barricades (619.04) | EACH | 10 | $100.00 | $165.00 | $20.00 |
| 56 | (619.0901) | LF | 13,000 | $0.35 | $0.45 | $0.35 |
| 57 | (619.110513) | EACH | 2 | $6,000.00 | $5,000.00 | $9,600.00 |
| 58 | Maintain Traffic Signal Equipment (Requirement C) Intersection (619.1613) | MONTH | 20 | $200.00 | $215.00 | $175.00 |
| 59 | Stone Filling (Medium) (620.04) | CY | 15 | $190.00 | $240.00 | $185.00 |
| 60 | Cleaning Closed Drainage Systems (621.03) | LF | 360 | $15.00 | $19.00 | $13.50 |
| 61 | (621.51050003) | 200 | $10.00 | $37.00 | $20.00 | |
| 62 | Crushed Stone (In-Place Measure) (623.12) | CY | 75 | $250.00 | $120.00 | $160.00 |
| 63 | Survey Operations (625.01) | LS | 1 | $20,000 | $50,000 | $33,275 |
| 64 | Steel Pin and Cap Right of Way Markers (625.05) | EACH | 9 | $450.00 | $600.00 | $360.00 |
| 65 | (627.50140008) | 1,525 | $6.00 | $9.50 | $4.65 | |
| 66 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1,000.00 | $1,400.00 | $50.00 |
| 67 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 12 | $3,000.00 | $3,800.00 | $4,575.00 |
| 68 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 |
| 69 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 230 | $51.00 | $48.00 | $40.00 |
| 70 | Overhead Sign Panels (645.61) | SF | 96 | $85.00 | $82.00 | $81.75 |
| 71 | Type A Sign Posts (645.81) | EACH | 36 | $180.00 | $240.00 | $195.00 |
| 72 | (645.81090003) | 2 | $182.00 | $55.00 | $46.00 | |
| 73 | Reference Marker Panel (646.21) | EACH | 6 | $44.00 | $38.00 | $32.00 |
| 74 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 2 | $24.00 | $20.00 | $17.00 |
| 75 | Steel Post, 1.1 lb/ft (646.31) | EACH | 3 | $90.00 | $67.00 | $55.00 |
| 76 | Steel Post, 2.0 lb/ft (646.32) | EACH | 2 | $105.00 | $79.00 | $65.00 |
| 77 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 32 | $7.00 | $60.00 | $50.00 |
| 78 | (647.83001002) | 5 | $6.00 | $36.00 | $30.00 | |
| 79 | (655.05010010) | 1 | $2,500.00 | $600.00 | $2,187.88 | |
| 80 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 8 | $2,500.00 | $3,200.00 | $3,008.19 |
| 81 | Manhole Frame & Cover (655.1202) | EACH | 1 | $600.00 | $1,500.00 | $1,200.00 |
| 82 | (662.01000007) | LS | 1 | $5,000.00 | $8,500.00 | $3,854.00 |
| 83 | (663.0106) | LF | 116 | $65.00 | $200.00 | $85.00 |
| 84 | (663.07060108) | 1 | $22,000 | $22,000 | $9,000.00 | |
| 85 | (663.1806) | EACH | 2 | $1,100.00 | $625.00 | $1,600.00 |
| 86 | Iron Water Main Fittings (3 - 8 inch diameter) (663.2001) | LB | 160 | $7.00 | $6.75 | $6.50 |
| 87 | (663.2106) | EACH | 7 | $200.00 | $210.00 | $100.00 |
| 88 | Adjust Existing Valve Box Elevation (663.33) | EACH | 3 | $180.00 | $1,000.00 | $260.00 |
| 89 | Remove and Dispose of Existing Water Valve & Valve Box (663.42) | EACH | 1 | $400.00 | $1,350.00 | $1,100.00 |
| 90 | (670.42110002) | 1 | $17,000 | $22,500 | $16,965 | |
| 91 | (670.91000010) | 7 | $815.00 | $955.00 | $815.00 | |
| 92 | (680.05031002) | 1 | $40,550 | $39,000 | $40,550 | |
| 93 | (680.05033002) | 1 | $20,000 | $23,500 | $19,390 | |
| 94 | (680.11131014) | 4 | $6,350.00 | $6,500.00 | $6,350.00 | |
| 95 | (680.11141014) | 2 | $8,815.00 | $10,500 | $8,815.00 | |
| 96 | Pole Excavation and Concrete Foundation (680.5001) | CY | 9 | $2,275.00 | $2,800.00 | $2,275.00 |
| 97 | Concrete Base for Controller Cabinet (680.5002) | EACH | 2 | $3,325.00 | $6,500.00 | $3,325.00 |
| 98 | Concrete Work Pad (5 feet x 5 feet x 4 inches) (680.5003) | EACH | 2 | $565.00 | $730.00 | $565.00 |
| 99 | (680.510501) | EACH | 5 | $1,895.00 | $2,000.00 | $1,895.00 |
| 100 | (680.520106) | LF | 325 | $15.00 | $21.00 | $14.90 |
| 101 | (680.520108) | LF | 775 | $28.00 | $34.00 | $27.65 |
| 102 | (680.621845) | EACH | 1 | $16,400 | $26,500 | $16,400 |
| 103 | (680.622156) | EACH | 1 | $25,100 | $29,500 | $25,100 |
| 104 | (680.632146) | EACH | 1 | $42,300 | $46,500 | $42,300 |
| 105 | Riser Assembly, 2-inch Diameter (680.700606) | EACH | 1 | $625.00 | $600.00 | $625.00 |
| 106 | (680.730514) | LF | 3,200 | $3.10 | $4.30 | $3.10 |
| 107 | (680.730714) | LF | 400 | $5.70 | $6.50 | $5.70 |
| 108 | (680.78000001) | LS | 1 | $5,770.00 | $8,000.00 | $5,770.00 |
| 109 | Battery Backup System (680.80) | EACH | 1 | $7,725.00 | $11,500 | $7,725.00 |
| 110 | (680.80324515) | 1 | $1,725.00 | $2,900.00 | $1,725.00 | |
| 111 | (680.80324708) | 2 | $1,200.00 | $2,900.00 | $1,200.00 | |
| 112 | Install Ball/Arrow LED Traffic Signal Module (680.810308) | EACH | 30 | $22.30 | $90.00 | $22.30 |
| 113 | Traffic Signal Section - Polycarbonate, Type I, 12-inch (680.810601) | EACH | 30 | $225.00 | $235.00 | $225.00 |
| 114 | (680.81210004) | 10 | $455.00 | $800.00 | $455.00 | |
| 115 | Backplates for Traffic Signal Heads (680.8199) | EACH | 10 | $173.00 | $360.00 | $173.00 |
| 116 | (680.8207) | EACH | 2 | $575.00 | $960.00 | $575.00 |
| 117 | (680.950306) | LF | 210 | $7.90 | $5.10 | $7.90 |
| 118 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $13.50 | $13.50 | $13.50 |
| 119 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 1,850 | $1.00 | $1.15 | $0.95 |
| 120 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 4,300 | $1.00 | $1.15 | $0.95 |
| 121 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 4,150 | $2.25 | $2.65 | $2.25 |
| 122 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 1,900 | $2.25 | $2.65 | $2.25 |
| 123 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 10 | $225.00 | $260.00 | $225.00 |
| 124 | Field Change Payment (FCP) (697.03) | DOL | 92,400 | $1.00 | $1.00 | $1.00 |
| 125 | Asphalt Price Adjustment (698.04) | DOL | 637.41 | $1.00 | $1.00 | $1.00 |
| 126 | Fuel Price Adjustment (698.05) | DOL | 222 | $1.00 | $1.00 | $1.00 |
| 127 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 128 | Mobilization (699.040001) | LS | 1 | $72,000 | $90,000 | $102,345 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of December 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.