NYSDOT contract D265587 bid tabulation
I-90 Pavement Resurfacing from I-87 to Corporate Woods. Let by New York State DOT on November 6, 2025, Albany, Region 01. 2 bids received; low bid $10,635,412 by Callanan Industries Inc.
- Owner
- New York State DOT
- Letting
- 06 NOV 2025
- Pay items
- 73
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Callanan Industries Inc | $10,635,412 | Low |
| 2 | Rifenburg Construction Inc | $11,483,115 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Callanan Industries Inc | 2. Rifenburg Construction Inc |
|---|---|---|---|---|---|
| 1 | (203.24010017) | 755 | $112.00 | $102.00 | |
| 2 | (206.03060005) | 625 | $24.00 | $30.00 | |
| 3 | (404.0001) | TON | 1,769 | $95.00 | $95.00 |
| 4 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1,740 | $95.00 | $95.00 |
| 5 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 2,161 | $95.00 | $95.00 |
| 6 | (404.0589) | TON | 99 | $800.00 | $980.00 |
| 7 | (404.0983) | TON | 63 | $330.00 | $280.00 |
| 8 | (404.1989) | TON | 528 | $115.50 | $174.00 |
| 9 | (406.0952) | TON | 34,767 | $122.50 | $134.00 |
| 10 | Straight Tack Coat (407.0103) | GAL | 17,536 | $7.60 | $3.00 |
| 11 | (407.01120007) | 11,218 | $3.50 | $6.25 | |
| 12 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 285,155 | $0.60 | $0.65 |
| 13 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 296,770 | $3.30 | $4.00 |
| 14 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 526 | $20.00 | $60.50 |
| 15 | Transition Bridge Railing (568.70) | LF | 128 | $265.00 | $287.00 |
| 16 | Bridge Railing Removal and Disposal (587.01) | LF | 24 | $8.00 | $26.50 |
| 17 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 104 | $5.00 | $5.00 |
| 18 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,200,000 | $1,368,604 |
| 19 | Type III Construction Barricades (619.04) | EACH | 101 | $50.00 | $75.00 |
| 20 | (619.0901) | LF | 221,136.50 | $0.24 | $0.70 |
| 21 | (619.111113) | EACH | 6 | $5,000.00 | $6,000.00 |
| 22 | Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611) | MONTH | 1 | $75.00 | $75.00 |
| 23 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $450,000 | $402,000 |
| 24 | Pavement Patching (Force Acount) (619.2601) | DOL | 5,000 | $1.00 | $1.00 |
| 25 | Pavement Patching (Tonnage) (619.2602) | TON | 38 | $650.00 | $582.00 |
| 26 | Survey Operations (625.01) | LS | 1 | $5,000.00 | $13,500 |
| 27 | (627.50140008) | 3,120 | $30.00 | $21.00 | |
| 28 | Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401) | SY | 231 | $120.00 | $103.00 |
| 29 | Removal and Repair of Deteriorated Asphalt Pavement – Greater than 4 Square Yards and less than 20 Square Yards (633.1402) | SY | 116 | $110.00 | $85.00 |
| 30 | Removal and Repair of Deteriorated Asphalt Pavement – 20 Square Yards or Greater (633.1403) | SY | 39 | $95.00 | $85.00 |
| 31 | Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15) | SY | 193 | $25.00 | $121.00 |
| 32 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 12 | $3,500.00 | $3,500.00 |
| 33 | Office Technology and Supplies (637.34) | DOL | 1,500 | $1.00 | $1.00 |
| 34 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 |
| 35 | (637.41000115) | 14 | $200.00 | $400.00 | |
| 36 | (637.41000215) | 14 | $200.00 | $400.00 | |
| 37 | (637.41000315) | 14 | $200.00 | $400.00 | |
| 38 | (637.41000415) | 14 | $200.00 | $400.00 | |
| 39 | (637.41000515) | 14 | $200.00 | $400.00 | |
| 40 | (637.41000615) | 14 | $200.00 | $400.00 | |
| 41 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 1,351 | $41.50 | $35.00 |
| 42 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 1,980 | $39.50 | $33.00 |
| 43 | Type A Sign Posts (645.81) | EACH | 233 | $275.00 | $197.00 |
| 44 | (645.830302) | EACH | 3 | $4,650.00 | $3,750.00 |
| 45 | (645.830402) | EACH | 2 | $6,675.00 | $4,400.00 |
| 46 | (645.830502) | EACH | 4 | $6,875.00 | $4,600.00 |
| 47 | (645.830702) | EACH | 9 | $10,650 | $7,000.00 |
| 48 | Reference Marker Panel (646.21) | EACH | 82 | $43.50 | $33.00 |
| 49 | Steel Post, 1.1 lb/ft (646.31) | EACH | 82 | $82.00 | $61.00 |
| 50 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 116 | $50.00 | $65.00 |
| 51 | Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65) | EACH | 9 | $800.00 | $350.00 |
| 52 | Pavement Ride Quality Adjustment to Asphalt Level 1 (653.1010) | QUALITY UNIT | 2,052 | $95.00 | $95.00 |
| 53 | (680.05010007) | 1 | $22,200 | $22,200 | |
| 54 | (680.05020007) | 1 | $4,690.00 | $4,690.00 | |
| 55 | (680.520106) | LF | 625 | $15.00 | $15.00 |
| 56 | (680.80320014) | 1 | $5,580.00 | $5,580.00 | |
| 57 | (680.92111208) | 675 | $9.10 | $9.10 | |
| 58 | (683.84029310) | 1 | $115,900 | $115,900 | |
| 59 | (683.96100705) | 2 | $2,700.00 | $2,700.00 | |
| 60 | (683.99902004) | 1 | $11,700 | $11,700 | |
| 61 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 814 | $1.00 | $1.00 |
| 62 | (685.16010014) | 258,993 | $1.20 | $1.20 | |
| 63 | (685.17010014) | 111,422 | $1.20 | $1.20 | |
| 64 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 59,743 | $1.90 | $1.90 |
| 65 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 960 | $1.90 | $1.90 |
| 66 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 24 | $74.00 | $74.00 |
| 67 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 23 | $195.00 | $195.00 |
| 68 | (691.04000020) | 21,000 | $1.00 | $1.00 | |
| 69 | Field Change Payment (FCP) (697.03) | DOL | 449,000 | $1.00 | $1.00 |
| 70 | Asphalt Price Adjustment (698.04) | DOL | 62,137.82 | $1.00 | $1.00 |
| 71 | Fuel Price Adjustment (698.05) | DOL | 10,874 | $1.00 | $1.00 |
| 72 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 73 | Mobilization (699.040001) | LS | 1 | $375,000 | $441,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of November 6, 2025. Compiled by Mirage Metrics.