NYSDOT contract D265680 bid tabulation
CONCRETE PAVEMENT PRESERVATION ON CBE & BQE IN NYC. Let by New York State DOT on March 12, 2026, Bronx, Kings, New York, Region 11. 9 bids received; low bid $17,861,000 by Es II Enterprises LLC /DBA El Sol Enterprises.
- Owner
- New York State DOT
- Letting
- 12 MAR 2026
- Pay items
- 59
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Es II Enterprises LLC /DBA El Sol Enterprises | $17,861,000 | Low |
| 2 | Triumph Construction Corp | $24,381,214 | +37% |
| 3 | Tully Construction Company Inc | $24,541,901 | +37% |
| 4 | Restani Construction Corp | $25,487,716 | +43% |
| 5 | Defoe Corporation | $26,426,887 | +48% |
| 6 | Oliveira Contracting Inc | $26,977,731 | +51% |
| 7 | John Civetta & Sons Inc | $28,736,500 | +61% |
| 8 | Jrcruz Corp | $30,767,946 | +72% |
| 9 | Paul J Scariano Inc | $32,302,916 | +81% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Es II Enterprises LLC /DBA El Sol Enterprises | 2. Triumph Construction Corp | 3. Tully Construction Company Inc | 4. Restani Construction Corp | 5. Defoe Corporation | 6. Oliveira Contracting Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | (209.11010024) | 21 | $500.00 | $193.25 | $650.00 | $500.00 | $550.00 | $400.00 | |
| 2 | (304.00010018) | 165,779 | $1.00 | $2.00 | $5.00 | $0.10 | $3.50 | $0.50 | |
| 3 | Subbase Course, Type 1 (304.11) | CY | 104 | $350.00 | $210.75 | $670.00 | $128.00 | $310.00 | $42.00 |
| 4 | (404.0981) | TON | 34 | $1,000.00 | $2,504.50 | $1,400.00 | $500.00 | $500.00 | $880.00 |
| 5 | Diluted Tack Coat (407.0102) | GAL | 28 | $15.00 | $34.00 | $100.00 | $4.00 | $10.00 | $29.00 |
| 6 | (490.30110011) | 268 | $150.00 | $334.25 | $200.00 | $50.00 | $30.00 | $11.00 | |
| 7 | (502.10010018) | LS | 1 | $30,000 | $100,000 | $20,000 | $50,000 | $15,000 | $10,000 |
| 8 | Sealing Transverse Joints- Highway Joint Sealant (502.9210) | LF | 1,541 | $20.00 | $19.00 | $12.50 | $13.90 | $14.30 | $15.00 |
| 9 | Sealing Longitudinal Joints-Highway Joint Sealant (502.9310) | LF | 904 | $20.00 | $19.00 | $19.00 | $13.90 | $14.30 | $15.00 |
| 10 | Bump Grinding - PCC with Slurry Removal (505.0102) | SY | 19,769 | $18.00 | $15.00 | $17.00 | $38.00 | $21.00 | $35.00 |
| 11 | (510.00210018) | 417 | $2,250.00 | $950.00 | $800.00 | $1,600.00 | $1,025.00 | $1,150.00 | |
| 12 | (510.01210018) | 95 | $2,500.00 | $1,400.00 | $1,750.00 | $1,800.00 | $1,700.00 | $1,150.00 | |
| 13 | (510.02210018) | 116 | $2,750.00 | $1,000.00 | $1,300.00 | $2,000.00 | $1,400.00 | $1,150.00 | |
| 14 | (510.11000018) | 5,171 | $1,700.00 | $2,800.00 | $2,200.00 | $2,600.00 | $2,600.00 | $2,875.00 | |
| 15 | (510.20000018) | 7,767 | $275.00 | $200.00 | $250.00 | $200.00 | $192.00 | $250.00 | |
| 16 | (510.81000018) | 1,236 | $100.00 | $60.00 | $70.00 | $150.00 | $61.00 | $12.00 | |
| 17 | (510.81100018) | 2,760 | $30.00 | $70.00 | $70.00 | $100.00 | $78.00 | $12.00 | |
| 18 | (510.90010018) | 636 | $5.00 | $13.75 | $90.00 | $13.90 | $21.00 | $20.00 | |
| 19 | (510.91000018) | 1,541 | $30.00 | $40.00 | $27.00 | $80.00 | $24.00 | $15.00 | |
| 20 | (510.91100018) | 904 | $30.00 | $50.00 | $20.00 | $40.00 | $25.00 | $12.00 | |
| 21 | (511.50000018) | 77 | $600.00 | $463.25 | $630.00 | $250.00 | $200.00 | $500.00 | |
| 22 | (604.07210110) | 16 | $2,000.00 | $391.25 | $5,200.00 | $1,200.00 | $4,600.00 | $1,718.00 | |
| 23 | (604.07290010) | 30 | $1,500.00 | $391.25 | $475.00 | $125.00 | $200.00 | $250.00 | |
| 24 | (609.06000008) | 4,822 | $15.00 | $15.75 | $5.00 | $10.00 | $67.00 | $50.00 | |
| 25 | Optional Curb (Precast Concrete Type PT4 or Cast-In-Place Concrete Type T4) (609.0903) | LF | 4,822 | $50.00 | $44.00 | $95.00 | $50.00 | $175.00 | $50.00 |
| 26 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $750,000 | $1,550,000 | $3,950,000 | $3,500,000 | $2,909,000 | $2,191,145 |
| 27 | Type III Construction Barricades (619.04) | EACH | 56 | $200.00 | $329.75 | $25.00 | $200.00 | $250.00 | $375.00 |
| 28 | (619.080102) | LF | 35,473 | $0.50 | $3.75 | $1.75 | $1.57 | $1.65 | $1.60 |
| 29 | (619.100102) | LF | 35,473 | $0.50 | $3.75 | $0.75 | $0.68 | $0.75 | $0.70 |
| 30 | (619.10050020) | 810 | $39.83 | $29.00 | $100.00 | $105.00 | $36.00 | $15.00 | |
| 31 | (619.110511) | EACH | 2 | $20,000 | $30,936 | $11,000 | $30,000 | $22,000 | $30,000 |
| 32 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $287,588 | $320,000 | $450,000 | $500,000 | $600,000 | $2,225,137 |
| 33 | Cleaning Drainage Structures (621.04) | EACH | 21 | $1,000.00 | $1,570.75 | $1,500.00 | $1,000.00 | $840.00 | $1,500.00 |
| 34 | Survey Operations (625.01) | LS | 1 | $50,000 | $225,000 | $200,000 | $100,000 | $1,000,000 | $30,000 |
| 35 | Stress Relieving Pavement Repairs (633.16) | SY | 18 | $1,500.00 | $1,521.75 | $1,640.00 | $1,000.00 | $410.00 | $275.00 |
| 36 | Cleaning and Preparation of Pavement Surfaces-Lines (635.0103) | LF | 35,473 | $1.60 | $3.50 | $1.60 | $1.57 | $1.65 | $1.60 |
| 37 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $3,000.00 | $8,587.00 | $4,000.00 | $10,000 | $2,000.00 | $4,381.00 |
| 38 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 27 | $6,000.00 | $16,000 | $15,000 | $9,000.00 | $10,000 | $12,250 |
| 39 | (637.31020020) | 27 | $900.00 | $1,000.00 | $965.00 | $1,000.00 | $1,000.00 | $1,000.00 | |
| 40 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 41 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 42 | Construction Testing supplies – Consumables (637.36) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 43 | (639.10210011) | LS | 1 | $80,000 | $75,000 | $75,000 | $75,000 | $125,000 | $75,000 |
| 44 | (655.00040011) | 5 | $750.00 | $1,541.50 | $675.00 | $700.00 | $3,000.00 | $800.00 | |
| 45 | (655.00120011) | 5 | $750.00 | $1,763.75 | $395.00 | $450.00 | $3,100.00 | $467.00 | |
| 46 | (655.16000011) | 5 | $1,000.00 | $804.75 | $1,250.00 | $1,100.00 | $1,500.00 | $500.00 | |
| 47 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 14,284 | $1.75 | $3.50 | $3.50 | $0.84 | $1.00 | $0.85 |
| 48 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 4,802 | $2.00 | $2.50 | $0.65 | $0.63 | $1.00 | $0.65 |
| 49 | (685.15000025) | 10,245 | $2.25 | $3.75 | $2.00 | $1.95 | $2.00 | $1.95 | |
| 50 | (685.16010014) | 13,102 | $2.00 | $2.75 | $1.80 | $1.88 | $2.00 | $1.84 | |
| 51 | (685.17010014) | 7,796 | $2.00 | $2.75 | $1.80 | $1.84 | $2.00 | $1.84 | |
| 52 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 24 | $300.00 | $200.00 | $350.00 | $150.00 | $160.00 | $150.00 |
| 53 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 3 | $400.00 | $200.00 | $175.00 | $175.00 | $185.00 | $175.00 |
| 54 | (691.04000020) | 504,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 55 | Field Change Payment (FCP) (697.03) | DOL | 1,150,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 56 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | Fuel Price Adjustment (698.05) | DOL | 31,896 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 58 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 59 | Mobilization (699.040001) | LS | 1 | $600,000 | $930,000 | $890,000 | $980,000 | $990,000 | $993,799 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 12, 2026. Compiled by Mirage Metrics.