NYSDOT contract D265719 bid tabulation
I-86 Paving Friendship to Belvidere. Let by New York State DOT on March 12, 2026, Allegany, Region 06. 3 bids received; low bid $6,989,167 by Dolomite Products Co Inc.
- Owner
- New York State DOT
- Letting
- 12 MAR 2026
- Pay items
- 51
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dolomite Products Co Inc | $6,989,167 | Low |
| 2 | Dalrymple Gravel & Contracting Co Inc | $7,414,072 | +6.0% |
| 3 | D&H Excavating Inc | $8,407,000 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dolomite Products Co Inc | 2. Dalrymple Gravel & Contracting Co Inc | 3. D&H Excavating Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $10,000 | $5,000.00 | $4,500.00 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 994 | $45.00 | $45.00 | $1.00 |
| 3 | Subbase Course, Optional Type (304.15) | CY | 513 | $115.00 | $125.00 | $215.00 |
| 4 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1,120 | $95.00 | $95.00 | $95.00 |
| 5 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 744 | $95.00 | $95.00 | $95.00 |
| 6 | (404.1989) | TON | 111 | $200.00 | $160.00 | $500.00 |
| 7 | (404.3789) | TON | 137 | $200.00 | $160.00 | $500.00 |
| 8 | (406.0952) | TON | 37,553 | $118.50 | $115.00 | $140.00 |
| 9 | (406.0982) | TON | 238 | $200.00 | $115.00 | $160.00 |
| 10 | Diluted Tack Coat (407.0102) | GAL | 31,997 | $2.40 | $5.00 | $6.25 |
| 11 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 242,431 | $0.20 | $0.25 | $0.60 |
| 12 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 355,517 | $1.55 | $2.20 | $2.00 |
| 13 | (607.91000011) | 10 | $300.00 | $550.00 | $525.00 | |
| 14 | Concrete Sidewalks and Driveways (608.0101) | CY | 145 | $1,145.00 | $1,200.00 | $1,500.00 |
| 15 | (608.01050909) | 3 | $8,500.00 | $21,000 | $11,500 | |
| 16 | (608.21000003) | 6 | $900.00 | $480.00 | $600.00 | |
| 17 | Stone Curb – Near Vertical Face (NVF) (609.0212) | LF | 158 | $100.00 | $90.00 | $110.00 |
| 18 | Resetting Existing Curb (609.15) | LF | 695 | $60.00 | $42.00 | $125.00 |
| 19 | (615.02010224) | 13 | $390.00 | $500.00 | $400.00 | |
| 20 | (615.02020124) | 12 | $355.00 | $500.00 | $350.00 | |
| 21 | (615.03070108) | 2 | $390.00 | $500.00 | $1,200.00 | |
| 22 | (615.03070208) | 2 | $390.00 | $500.00 | $1,200.00 | |
| 23 | (618.72135124) | 2 | $3,250.00 | $3,500.00 | $2,100.00 | |
| 24 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $305,000 | $498,000 | $212,586 |
| 25 | (619.0901) | LF | 259,554 | $0.03 | $0.28 | $0.20 |
| 26 | (619.110511) | EACH | 4 | $2,750.00 | $2,000.00 | $4,100.00 |
| 27 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $100.00 | $35,000 | $1.00 |
| 28 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 1,000 | $10.00 | $1.00 | $11.00 |
| 29 | Survey Operations (625.01) | LS | 1 | $10,000 | $15,000 | $26,000 |
| 30 | (627.50140008) | 850 | $8.50 | $3.50 | $7.50 | |
| 31 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $2,950.00 | $2,000.00 | $750.00 |
| 32 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 6 | $3,000.00 | $2,800.00 | $2,200.00 |
| 33 | Office Technology and Supplies (637.34) | DOL | 200 | $1.00 | $1.00 | $1.00 |
| 34 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 |
| 35 | Construction Testing supplies – Consumables (637.36) | DOL | 200 | $1.00 | $1.00 | $1.00 |
| 36 | (637.41000115) | 6 | $400.00 | $400.00 | $350.00 | |
| 37 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 6 | $65.00 | $64.00 | $73.00 |
| 38 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 43 | $40.00 | $40.00 | $46.00 |
| 39 | Type A Sign Posts (645.81) | EACH | 3 | $300.00 | $252.00 | $290.00 |
| 40 | (645.830203) | EACH | 2 | $7,500.00 | $7,420.00 | $8,500.00 |
| 41 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 118,517 | $0.30 | $0.40 | $0.45 |
| 42 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 152,948 | $0.30 | $0.29 | $0.35 |
| 43 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 110,523 | $0.30 | $0.29 | $0.35 |
| 44 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 21,186 | $1.45 | $1.40 | $1.60 |
| 45 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 5 | $250.00 | $200.00 | $230.00 |
| 46 | (691.04000020) | 50,000 | $1.00 | $1.00 | $1.00 | |
| 47 | Field Change Payment (FCP) (697.03) | DOL | 300,000 | $1.00 | $1.00 | $1.00 |
| 48 | Asphalt Price Adjustment (698.04) | DOL | 33,673 | $1.00 | $1.00 | $1.00 |
| 49 | Fuel Price Adjustment (698.05) | DOL | 4,275 | $1.00 | $1.00 | $1.00 |
| 50 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 51 | Mobilization (699.040001) | LS | 1 | $267,500 | $205,000 | $320,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.