NYSDOT contract D265767 bid tabulation
RESURFACING - Route 931G & Route 370. Let by New York State DOT on May 7, 2026, Onondaga, Region 03. 2 bids received; low bid $3,838,235 by Barrett Paving Materials Inc.
- Owner
- New York State DOT
- Letting
- 07 MAY 2026
- Pay items
- 106
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Barrett Paving Materials Inc | $3,838,235 | Low |
| 2 | Seneca Stone Corp | $6,040,000 | +57% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Barrett Paving Materials Inc | 2. Seneca Stone Corp |
|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 1,935 | $116.00 | $300.00 |
| 2 | (205.0201) | LS | 1 | $1,200.00 | $2,000.00 |
| 3 | (205.0202) | LS | 1 | $1,250.00 | $2,000.00 |
| 4 | (205.0203) | LS | 1 | $1,050.00 | $2,000.00 |
| 5 | (205.0204) | LS | 1 | $1,180.00 | $2,000.00 |
| 6 | (205.0205) | LS | 1 | $1,250.00 | $2,000.00 |
| 7 | (205.0206) | LS | 1 | $800.00 | $2,000.00 |
| 8 | Field Organic Vapor Monitoring of Contaminated Soil (205.03) | HR | 77 | $152.00 | $250.00 |
| 9 | (205.050201) | TON | 21 | $132.00 | $190.00 |
| 10 | (205.050202) | TON | 23 | $131.00 | $190.00 |
| 11 | (205.050203) | TON | 15 | $137.00 | $190.00 |
| 12 | (205.050204) | TON | 20 | $133.00 | $190.00 |
| 13 | (205.050205) | TON | 23 | $131.00 | $190.00 |
| 14 | (205.050206) | TON | 13 | $140.00 | $190.00 |
| 15 | Trench and Culvert Excavation (206.0201) | CY | 302 | $150.00 | $200.00 |
| 16 | (206.03010010) | 50 | $57.00 | $60.00 | |
| 17 | Geotextile Drainage (207.22) | SY | 2,406 | $1.10 | $3.00 |
| 18 | Drainage Structure Inlet Protection, Silt Fence – Temporary (209.1701) | LF | 16 | $16.41 | $25.00 |
| 19 | Drainage Structure Inlet Protection, Gravel Bag – Temporary (209.1702) | CY | 8 | $415.60 | $800.00 |
| 20 | Subbase Course, Optional Type (304.15) | CY | 907 | $195.00 | $250.00 |
| 21 | (404.0189) | TON | 68 | $190.00 | $150.00 |
| 22 | (404.2589) | TON | 285 | $212.00 | $360.00 |
| 23 | (406.0972) | TON | 1,416 | $187.00 | $250.00 |
| 24 | (406.1979) | TON | 2,359 | $158.00 | $180.00 |
| 25 | Diluted Tack Coat (407.0102) | GAL | 2,760 | $2.32 | $5.00 |
| 26 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 9,744 | $0.60 | $1.00 |
| 27 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 13,978 | $4.30 | $10.00 |
| 28 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 2,008 | $22.00 | $20.00 |
| 29 | (604.070301) | EACH | 20 | $1,620.00 | $4,000.00 |
| 30 | (604.070302) | EACH | 9 | $1,500.00 | $4,200.00 |
| 31 | Underdrain Filter, Type I (605.0901) | CY | 302 | $190.00 | $70.00 |
| 32 | (605.1502) | LF | 3,606 | $10.00 | $25.00 |
| 33 | (607.41010010) | 552 | $6.00 | $15.00 | |
| 34 | Concrete Sidewalks and Driveways (608.0101) | CY | 279 | $1,250.00 | $1,600.00 |
| 35 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 115 | $225.00 | $400.00 |
| 36 | Brick Paved Sidewalks and Driveways (Sand Setting Bed) (608.03) | SY | 32 | $297.00 | $320.00 |
| 37 | (608.03000001) | 6 | $450.00 | $600.00 | |
| 38 | (608.03040008) | 293 | $350.00 | $400.00 | |
| 39 | (608.10080008) | 2,048 | $27.50 | $60.00 | |
| 40 | Embedded Detectable Warning Units (608.21) | SY | 40 | $390.00 | $800.00 |
| 41 | Stone Curb – Near Vertical Face (NVF) (609.0212) | LF | 3,606 | $64.00 | $75.00 |
| 42 | Turf Establishment – Performance (610.1605) | SY | 712 | $22.00 | $20.00 |
| 43 | Care of Trees up to 12” Diam. at Breast Height – Pruning (614.0411) | EACH | 2 | $2,500.00 | $400.00 |
| 44 | (614.060304) | EACH | 1 | $4,900.00 | $1,000.00 |
| 45 | (615.03050108) | 4 | $500.00 | $3,000.00 | |
| 46 | (615.03050208) | 2 | $500.00 | $3,250.00 | |
| 47 | (615.03050308) | 2 | $500.00 | $3,250.00 | |
| 48 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $608,860 | $900,000 |
| 49 | Type III Construction Barricades (619.04) | EACH | 89 | $98.10 | $100.00 |
| 50 | (619.080101) | LF | 4,524 | $0.75 | $0.75 |
| 51 | (619.080102) | LF | 10,122 | $0.75 | $0.75 |
| 52 | (619.0901) | LF | 14,946 | $0.49 | $0.50 |
| 53 | (619.100101) | LF | 9,301 | $0.49 | $0.50 |
| 54 | (619.100201) | EACH | 10 | $150.00 | $150.00 |
| 55 | (619.110611) | WEEK | 3 | $984.00 | $2,000.00 |
| 56 | Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611) | MONTH | 8 | $125.00 | $150.00 |
| 57 | (619.161401) | EACH | 4 | $3,900.00 | $4,100.00 |
| 58 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $64,000 | $600,000 |
| 59 | Traffic Control Supervisor (619.25) | MONTH | 8 | $5,100.00 | $1,000.00 |
| 60 | Survey Operations (625.01) | LS | 1 | $45,005 | $200,000 |
| 61 | (627.50140008) | 4,276 | $5.65 | $10.00 | |
| 62 | Cleaning and Preparation of Pavement Surfaces-Lines (635.0103) | LF | 9,301 | $0.75 | $1.00 |
| 63 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1,500.00 | $4,000.00 |
| 64 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 9 | $3,300.00 | $4,500.00 |
| 65 | Office Technology and Supplies (637.34) | DOL | 2,500 | $1.00 | $1.00 |
| 66 | Construction Testing supplies – Consumables (637.36) | DOL | 200 | $1.00 | $1.00 |
| 67 | (637.41000115) | 9 | $222.22 | $350.00 | |
| 68 | (637.41000215) | 9 | $222.22 | $350.00 | |
| 69 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 227 | $46.00 | $50.00 |
| 70 | Type A Sign Posts (645.81) | EACH | 35 | $268.00 | $350.00 |
| 71 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 2 | $1,164.00 | $1,400.00 |
| 72 | Reference Marker Panel (646.21) | EACH | 3 | $44.00 | $40.00 |
| 73 | Steel Post, 2.0 lb/ft (646.32) | EACH | 1 | $114.00 | $80.00 |
| 74 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 1 | $183.00 | $300.00 |
| 75 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 2 | $40.00 | $300.00 |
| 76 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 31 | $37.00 | $250.00 |
| 77 | (647.83001002) | 1 | $29.00 | $30.00 | |
| 78 | Adjust Existing Valve Box Elevation (663.33) | EACH | 13 | $300.00 | $1,300.00 |
| 79 | (680.05010007) | 4 | $32,217 | $35,000 | |
| 80 | (680.05020007) | 4 | $4,610.00 | $5,000.00 | |
| 81 | Pole Excavation and Concrete Foundation (680.5001) | CY | 6 | $2,395.00 | $2,500.00 |
| 82 | (680.520106) | LF | 48 | $41.15 | $45.00 |
| 83 | (680.53010010) | 240 | $3.50 | $4.00 | |
| 84 | (680.670802) | EACH | 5 | $1,300.00 | $1,400.00 |
| 85 | (680.730714) | LF | 711 | $6.50 | $7.00 |
| 86 | (680.77000105) | 1 | $1,320.00 | $1,500.00 | |
| 87 | (680.77000205) | 1 | $1,736.00 | $2,000.00 | |
| 88 | (680.80324515) | 2 | $3,060.00 | $3,500.00 | |
| 89 | Pedestrian Signal Module - 12-inch, Bi-Modal Hand/Man Symbols, LED (680.813105) | EACH | 5 | $229.00 | $340.00 |
| 90 | Pedestrian Signal Section - Polycarbonate, Type I, 12-inch (680.813106) | EACH | 10 | $255.00 | $340.00 |
| 91 | Pedestrian Signal Post Top Mount Assembly (680.8142) | EACH | 5 | $325.00 | $400.00 |
| 92 | Pedestrian Signal Module - 12-inch Countdown Timer, LED (680.815001) | EACH | 5 | $274.00 | $300.00 |
| 93 | (680.8151) | EACH | 5 | $1,190.00 | $1,300.00 |
| 94 | (680.82250308) | 5 | $130.00 | $150.00 | |
| 95 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $9.81 | $9.81 |
| 96 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 2,648 | $1.50 | $2.00 |
| 97 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 4,825 | $1.50 | $2.00 |
| 98 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 13,307 | $2.50 | $3.00 |
| 99 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 3,780 | $2.50 | $3.00 |
| 100 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 16 | $74.00 | $100.00 |
| 101 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 10 | $200.00 | $210.00 |
| 102 | Field Change Payment (FCP) (697.03) | DOL | 237,000 | $1.00 | $1.00 |
| 103 | Asphalt Price Adjustment (698.04) | DOL | 8,960 | $1.00 | $1.00 |
| 104 | Fuel Price Adjustment (698.05) | DOL | 2,730 | $1.00 | $1.00 |
| 105 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 106 | Mobilization (699.040001) | LS | 1 | $145,000 | $222,145 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of May 7, 2026. Compiled by Mirage Metrics.