ODOT contract 250059 bid tabulation

MIA-SR 571-00.00/07.18/13.26 (TWO LANE RESURFACING). Let by Ohio DOT on January 30, 2025, MIA. 2 bids received; low bid $2,957,850 by Walls Bros Asphalt Co Inc, +0.5% against the engineer's estimate of $2,942,000.

Owner
Ohio DOT
Letting
30 JAN 2025
Pay items
39
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Walls Bros Asphalt Co Inc$2,957,850Low+1.0%
2Barrett Paving Materials Inc$3,379,000+14%+15%
ODOT contract 250059: bids by rank

Engineer's estimate: $2,942,000.

Bid tabulation

LinePay itemUnitQuantity1. Walls Bros Asphalt Co Inc2. Barrett Paving Materials Inc
1Preparing subgrade for shoulder paving (209E72050)MI19.46$591.00$700.00
2Special - mailbox removed and reset (690E50350)EACH6$530.00$240.00
3Manhole adjusted to grade (611E99654)EACH12$1,319.00$650.00
4Partial depth pavement repair (asphalt concrete base), as per plan (251E01041)SY675$58.50$78.00
5Pavement planing, asphalt concrete, 1 1/2"depth (254E01000)SY224,614$1.35$2.00
6Patching planed surface, as per plan (254E01601)SY275$15.00$10.00
7Asphalt concrete base, (449), as per plan, PG64-22 (301E56001)CY26$518.00$800.00
8Non-tracking tack coat (407E20000)GAL19,100$2.50$2.00
9Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100)CY9,417$219.00$235.00
10Compacted aggregate (617E10100)CY676$110.00$95.00
11Rumble stripes, edge line (asphalt concrete) (618E41000)MI8.42$1,685.00$1,500.00
12Rumble stripes, center line (asphalt concrete) (618E43000)MI6$1,685.00$1,300.00
13Longitudinal joint preparation (874E21000)MI6$4,975.00$4,000.00
14Valve box adjusted to grade (638E10800)EACH22$992.00$300.00
15RPM (621E00100)EACH666$37.00$36.50
16Raised pavement marker removed (621E54000)EACH666$15.50$6.00
17Edge line, 6", type 1 (642E00104)MI21.17$950.00$920.00
18Center line, type 1 (642E00300)MI12.04$1,170.00$775.00
19Lane line, 6" (644E00204)MI0.52$4,000.00$1,600.00
20Channelizing line, 12" (644E00404)FT2,010$5.60$2.15
21Stop line (644E00500)FT905$7.00$7.25
22Crosswalk line, 12" (644E00620)FT1,726$3.50$3.60
23Crosswalk line, 24" (644E00630)FT48$15.00$5.80
24Transverse/diagonal line (644E00700)FT236$7.00$7.25
25Lane arrow (644E01300)EACH44$120.00$119.00
26Detector loop, as per plan (632E26501)EACH33$1,430.00$1,300.00
27Loop detector tie in, as per plan (632E27201)EACH33$110.00$100.00
28Law enforcement officer with patrol car for assistance (614E11110)HR100$75.00$80.00
29Work zone marking sign (614E12460)EACH118$85.00$84.80
30Work zone lane line, class III, 6", 642 paint (614E20560)MI1.04$900.00$830.00
31Work zone center line, class I, 642 paint (614E21100)MI24.06$1,050.00$1,860.00
32Work zone channelizing line, class III, 12", 642 paint (614E23690)FT3,870$0.65$1.55
33Work zone stop line, class III, 642 paint (614E26610)FT1,810$3.50$5.20
34Work zone arrow, class III, 642 paint (614E30650)EACH88$60.00$62.25
35Patching concrete bridge deck - type B (519E12300)SY6$1,961.00$718.00
36Joint sealer, as per plan (516E31001)FT88$33.00$25.74
37Premium for contract performance bond and for payment bond (103E05000)LS1$9,750.00$9,116.03
38Maintaining traffic (614E11000)LS1$31,000$185,600
39Mobilization (624E10000)LS1$40,000$50,000
ODOT contract 250059: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy