ODOT contract 250145 bid tabulation

DAR-Shawnee Prairie Preserve Pvg (CHIP SEAL). Let by Ohio DOT on February 27, 2025, DAR. 4 bids received; low bid $33,697 by Wagner Paving Inc, -40% against the engineer's estimate of $56,000.

Owner
Ohio DOT
Letting
27 FEB 2025
Pay items
14
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Wagner Paving Inc$33,697Low-40%
2Henry W Bergman Inc$52,593+56%-6.0%
3Shelly Company$72,464+115%+29%
4Fillmore Construction$74,759+122%+33%
ODOT contract 250145: bids by rank

Engineer's estimate: $56,000.

Bid tabulation

LinePay itemUnitQuantity1. Wagner Paving Inc2. Henry W Bergman Inc3. Shelly Company4. Fillmore Construction
1Special - special-fog seal (690E98900)GAL530.30$6.75$8.00$12.25$8.00
2Erosion control (832E30000)EACH1,000$1.00$1.00$1.00$1.00
3Pavement repair (253E01000)SY40$142.75$150.00$395.00$100.00
4Aggregate, single chip seal, type A, as per plan (422E11001)SY4,419$0.60$2.00$3.45$5.00
5Emulsion, chip seal, as per plan (422E25001)GAL1,768$6.65$7.00$4.70$8.00
6Compacted aggregate (617E10100)CY12$266.00$200.00$185.00$300.00
7Removal of pavement marking (642E30000)FT1,500$2.00$2.06$1.87$1.97
8Transverse/diagonal line, type 1 (642E00700)FT450$1.00$2.20$2.00$2.50
9Handicap symbol marking, type 1 (642E01702)EACH2$100.00$125.40$114.00$83.00
10Parking lot stall marking, type 1 (642E01200)FT1,040$0.50$1.65$1.50$2.50
11Lane arrow, type 1 (642E01300)EACH4$100.00$110.00$100.00$83.00
12Premium for contract performance bond and for payment bond (103E05000)LS1$237.00$750.00$3,000.00$3,500.00
13Maintaining traffic (614E11000)LS1$500.00$3,000.00$4,500.00$5,000.00
14Mobilization (624E10000)LS1$500.00$7,500.00$10,000$10,000
ODOT contract 250145: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.