ODOT contract 250318 bid tabulation

ADA-SR 125/SR 136/SR 247-00.00/20.40/18.17 (MICROSURFACING). Let by Ohio DOT on June 26, 2025, ADA. 1 bid received; low bid $1,574,787 by Strawser Construction Inc, +15% against the engineer's estimate of $1,364,000.

Owner
Ohio DOT
Letting
26 JUN 2025
Pay items
21
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Strawser Construction Inc$1,574,787Low+15%
ODOT contract 250318: bids by rank

Engineer's estimate: $1,364,000.

Bid tabulation

LinePay itemUnitQuantity1. Strawser Construction Inc
1Linear grading (209E60500)MI3.10$6,000.00
2Partial depth pavement repair (441), as per plan (251E01001)SY2,000$45.00
3Microsurfacing, surface course (421E10010)SY211,798$3.55
4Compacted aggregate (617E10100)CY304$155.00
5RPM (621E00100)EACH1,564$36.00
6Raised pavement marker removed (621E54000)EACH1,564$25.00
7Edge line, 6" (644E00104)MI30.91$3,800.00
8Center line (644E00300)MI15.46$4,500.00
9Stop line (644E00500)FT12$12.00
10Removal of pavement marking (644E30000)FT12$5.00
11Removal of pavement marking (644E30030)MI46.47$1,300.00
12Edge line, 6" (646E10010)MI0.07$15,000
13Center line (646E10200)MI0.03$15,000
14Work zone marking sign (614E12460)EACH44$115.00
15Work zone center line, class III, 642 paint (614E21550)MI30.98$950.00
16Work zone edge line, class III, 6", 642 paint (614E22360)MI61.96$850.00
17Work zone stop line, class III, 642 paint (614E26610)FT24$10.00
18Premium for contract performance bond, payment bond and maintenance bond (103E06000)LS1$9,500.00
19Maintaining traffic (614E11000)LS1$98,575
20Construction layout stakes and surveying (623E10000)LS1$2,500.00
21Mobilization (624E10000)LS1$124,665
ODOT contract 250318: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy