ODOT contract 250334 bid tabulation

NOB-CR 19-00.00 (TWO LANE RESURFACING). Let by Ohio DOT on June 26, 2025, NOB. 2 bids received; low bid $520,566 by Shelly & Sands Inc, -19% against the engineer's estimate of $645,000.

Owner
Ohio DOT
Letting
26 JUN 2025
Pay items
19
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly & Sands Inc$520,566Low-19%
2NLS Paving, Inc$605,650+16%-6.0%
ODOT contract 250334: bids by rank

Engineer's estimate: $645,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly & Sands Inc2. NLS Paving, Inc
1Linear grading (209E60500)MI1.37$2,850.00$3,850.00
2Seeding and mulching, class 1 (659E00500)SY2,411$2.22$1.60
3Commercial fertilizer (659E20000)TON0.33$891.00$1,250.00
4Lime (659E31000)ACRE0.50$155.50$160.00
5Water (659E35000)MGAL7$1.00$1.00
6Erosion control (832E30000)EACH4,000$1.00$1.00
7Pavement repair, as per plan (253E01001)SY1,919$51.00$76.00
8Tack coat (407E10000)GAL1,482$3.00$3.00
9Prime coat (408E10000)GAL1,072$5.00$4.50
10Asphalt concrete surface course, type 1, (448), as per plan (441E50101)CY1,647$196.00$205.00
11Compacted aggregate (617E10100)CY240$120.00$90.00
12Shoulder reconditioning, misc.:grading (617E98000)SY2,678$2.15$5.00
13Center line (643E00300)MI2.28$6,945.00$6,000.00
14Work zone marking sign (614E12460)EACH4$125.00$125.00
15Work zone center line, class II (614E21400)MI2.28$187.00$600.00
16Premium for contract performance bond and for payment bond (103E05000)LS1$1,875.00$2,981.40
17Maintaining traffic (614E11000)LS1$11,500$26,000
18Construction layout stakes and surveying, as per plan (623E10001)LS1$3,200.00$1,750.00
19Mobilization (624E10000)LS1$8,550.00$18,000
ODOT contract 250334: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy