ODOT contract 250345 bid tabulation
MAH-IR 680-12.12 (FOUR LANE RESURFACING). Let by Ohio DOT on July 17, 2025, MAH. 3 bids received; low bid $4,233,691 by Shelly & Sands Inc.
- Owner
- Ohio DOT
- Letting
- 17 JUL 2025
- Pay items
- 95
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Shelly & Sands Inc | $4,233,691 | Low |
| 2 | Shelly Company | $4,312,330 | +2.0% |
| 3 | Karvo Companies Inc | $4,575,000 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Shelly Company | 3. Karvo Companies Inc |
|---|---|---|---|---|---|---|
| 1 | Removal misc.: barrier reflector (202E98100) | EACH | 52 | $2.50 | $2.50 | $2.50 |
| 2 | Excavation (203E10000) | CY | 28 | $50.00 | $30.00 | $10.00 |
| 3 | Linear grading (209E60200) | STA | 464 | $35.00 | $45.00 | $40.00 |
| 4 | Special - as-built construction plans (690E91000) | LS | 1 | $2,000.00 | $10,000 | $750.00 |
| 5 | Special - vertical clearance (690E98000) | EACH | 4 | $1,200.00 | $640.00 | $640.00 |
| 6 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 |
| 7 | Partial depth pavement repair (441) (251E01000) | SY | 1,250 | $58.00 | $55.00 | $50.00 |
| 8 | Partial depth pavement repair (441) (251E01000) | SY | 250 | $65.00 | $140.00 | $100.00 |
| 9 | Full depth pavement sawing (252E01500) | FT | 2,250 | $3.80 | $4.00 | $5.00 |
| 10 | Pavement planing, asphalt concrete (T = 2") (254E01000) | SY | 218,855 | $0.75 | $1.00 | $1.00 |
| 11 | Full depth pavement removal and rigid replacement, type 1, class QC RS (255E19000) | SY | 500 | $400.00 | $275.00 | $125.00 |
| 12 | Aggregate base (304E20000) | CY | 28 | $45.00 | $80.00 | $25.00 |
| 13 | Non-tracking tack coat (407E20000) | GAL | 19,698 | $3.05 | $2.50 | $2.75 |
| 14 | Prime coat, as per plan (408E10001) | GAL | 8,684 | $3.50 | $4.25 | $4.75 |
| 15 | Anti-segregation equipment (442E00100) | CY | 7,986 | $6.00 | $5.00 | $5.75 |
| 16 | Asphalt concrete surface course, 12.5 MM, type A (447) (442E10300) | CY | 12,159 | $208.00 | $206.00 | $230.00 |
| 17 | Compacted aggregate, as per plan (617E10101) | CY | 580 | $110.00 | $85.00 | $50.00 |
| 18 | Rumble strips, transverse (asphalt concrete) (618E39000) | EACH | 7 | $1,250.00 | $1,000.00 | $1,000.00 |
| 19 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 18 | $765.00 | $765.00 | $765.00 |
| 20 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 26.91 | $1,500.00 | $1,700.00 | $1,500.00 |
| 21 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 6,515 | $0.75 | $0.70 | $0.75 |
| 22 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 11,860 | $1.25 | $1.30 | $1.25 |
| 23 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 0.14 | $2,750.00 | $4,000.00 | $2,750.00 |
| 24 | RPM (621E00100) | EACH | 366 | $47.80 | $47.80 | $45.00 |
| 25 | RPM, as per plan (621E00101) | EACH | 574 | $42.30 | $42.30 | $40.00 |
| 26 | Raised pavement marker removed (621E54000) | EACH | 606 | $5.00 | $5.00 | $1.66 |
| 27 | Barrier reflector, type 1 (bidirectional) (626E00102) | EACH | 8 | $15.00 | $15.00 | $15.00 |
| 28 | Barrier reflector, type 1 (one-way) (626E00102) | EACH | 39 | $15.00 | $15.00 | $15.00 |
| 29 | Barrier reflector, type 2 (one-way) (626E00110) | EACH | 160 | $40.00 | $40.00 | $40.00 |
| 30 | Edge line, 6" (646E10010) | MI | 0.27 | $7,500.00 | $4,000.00 | $7,500.00 |
| 31 | Center line (646E10200) | MI | 0.13 | $12,500 | $5,000.00 | $12,500 |
| 32 | Stop line (646E10400) | FT | 78 | $10.00 | $11.00 | $10.00 |
| 33 | Transverse/diagonal line (646E10600) | FT | 676 | $10.00 | $9.00 | $10.00 |
| 34 | Lane arrow (646E20300) | EACH | 16 | $185.00 | $140.00 | $185.00 |
| 35 | Wrong way arrow (646E20320) | EACH | 4 | $250.00 | $500.00 | $250.00 |
| 36 | Dotted line, 6" (646E20504) | FT | 399 | $1.50 | $1.20 | $1.50 |
| 37 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 18.90 | $4,000.00 | $4,340.00 | $4,000.00 |
| 38 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 8.15 | $2,250.00 | $3,000.00 | $2,250.00 |
| 39 | Wet reflective epoxy pavement marking, channelizing line, 12" (807E12310) | FT | 11,860 | $2.00 | $1.75 | $2.00 |
| 40 | Wet reflective epoxy pavement marking, dotted line, 6" (807E12410) | FT | 6,515 | $1.75 | $2.25 | $1.75 |
| 41 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 200 | $95.00 | $120.00 | $100.00 |
| 42 | Work zone marking sign (614E12460) | EACH | 6 | $85.00 | $85.00 | $85.00 |
| 43 | Work zone increased penalties sign (614E12484) | EACH | 16 | $175.00 | $175.00 | $175.00 |
| 44 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $600.00 | $150.00 | $100.00 |
| 45 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $900.00 | $900.00 | $900.00 |
| 46 | Work zone lane line, class I, 6" (614E20010) | MI | 8.15 | $550.00 | $550.00 | $550.00 |
| 47 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 8.15 | $650.00 | $650.00 | $650.00 |
| 48 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.13 | $1,000.00 | $1,000.00 | $1,000.00 |
| 49 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 38.07 | $750.00 | $750.00 | $750.00 |
| 50 | Work zone channelizing line, class I, 12" (614E23010) | FT | 11,860 | $0.50 | $0.50 | $0.50 |
| 51 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 11,860 | $0.50 | $0.50 | $0.50 |
| 52 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 6,515 | $0.45 | $0.45 | $0.45 |
| 53 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 6,914 | $0.45 | $0.45 | $0.45 |
| 54 | Work zone stop line, class I (614E26000) | FT | 78 | $4.00 | $4.00 | $4.00 |
| 55 | Work zone stop line, class III, 642 paint (614E26610) | FT | 78 | $4.00 | $4.00 | $4.00 |
| 56 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 24 | $600.00 | $600.00 | $600.00 |
| 57 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 58 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 2,527 | $12.00 | $12.00 | $12.00 |
| 59 | Removal of existing pavement marking (512E74500) | FT | 1,616 | $5.00 | $5.00 | $5.00 |
| 60 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 61 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 62 | Pavement planing, asphalt concrete (T = 1 1/2") (254E01000) | SY | 356 | $30.00 | $15.00 | $8.00 |
| 63 | Non-tracking tack coat (407E20000) | GAL | 32 | $3.05 | $2.50 | $2.75 |
| 64 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 14 | $500.00 | $500.00 | $375.00 |
| 65 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 10 | $175.00 | $175.00 | $175.00 |
| 66 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 1,113 | $12.00 | $12.00 | $12.00 |
| 67 | Removal of existing pavement marking (512E74500) | FT | 937 | $5.00 | $5.00 | $5.00 |
| 68 | Patching concrete structure, as per plan (519E11101) | SF | 85 | $225.00 | $225.00 | $225.00 |
| 69 | Galvanic anode protection (844E20000) | EACH | 204 | $100.00 | $100.00 | $100.00 |
| 70 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 71 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 5 | $175.00 | $175.00 | $175.00 |
| 72 | Patching concrete structure, as per plan (519E11101) | SF | 40 | $225.00 | $225.00 | $225.00 |
| 73 | Galvanic anode protection (844E20000) | EACH | 96 | $100.00 | $100.00 | $100.00 |
| 74 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 75 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 726 | $12.00 | $12.00 | $12.00 |
| 76 | Removal of existing pavement marking (512E74500) | FT | 466 | $5.00 | $5.00 | $5.00 |
| 77 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 78 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 726 | $12.00 | $12.00 | $12.00 |
| 79 | Removal of existing pavement marking (512E74500) | FT | 468 | $5.00 | $5.00 | $5.00 |
| 80 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $20,000 | $32,000 |
| 81 | Maintaining traffic (614E11000) | LS | 1 | $201,464 | $295,000 | $250,000 |
| 82 | Field office, type B (619E16010) | MNTH | 12 | $3,000.00 | $3,000.00 | $3,000.00 |
| 83 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,000.00 | $13,500 | $3,772.99 |
| 84 | Mobilization (624E10000) | LS | 1 | $80,000 | $100,000 | $250,000 |
| 100 | Surface preparation of existing structural steel (514E00100) | LS | 1 | $75,000 | $50,000 | $50,000 |
| 101 | Field painting of existing structural steel, prime coat (514E00200) | LS | 1 | $12,000 | $10,000 | $10,000 |
| 102 | Field painting structural steel, intermediate coat (514E00300) | LS | 1 | $12,000 | $10,000 | $10,000 |
| 103 | Field painting structural steel, finish coat (514E00400) | LS | 1 | $12,000 | $10,000 | $10,000 |
| 104 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 2 | $100.00 | $150.00 | $150.00 |
| 105 | Final inspection repair (514E10000) | EACH | 1 | $100.00 | $250.00 | $250.00 |
| 106 | Edge line, 6" (646E10010) | MI | 0.12 | $7,500.00 | $6,000.00 | $7,500.00 |
| 107 | Center line (646E10200) | MI | 0.06 | $12,500 | $11,000 | $12,500 |
| 108 | Edge line, 6" (646E10010) | MI | 0.14 | $7,500.00 | $6,000.00 | $7,500.00 |
| 109 | Center line (646E10200) | MI | 0.07 | $12,500 | $11,000 | $12,500 |
| 110 | Dotted line, 6" (646E20504) | FT | 370 | $1.50 | $1.20 | $1.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 17, 2025. Compiled by Mirage Metrics.