ODOT contract 250382 bid tabulation
MRG-SR 78-18.91 (TWO LANE RESURFACING). Let by Ohio DOT on August 14, 2025, MRG. 2 bids received; low bid $5,463,646 by Shelly & Sands Inc, +4.6% against the engineer's estimate of $5,222,000.
- Owner
- Ohio DOT
- Letting
- 14 AUG 2025
- Pay items
- 39
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $5,463,646 | Low | +5.0% |
| 2 | NLS Paving, Inc | $5,514,855 | +1.0% | +6.0% |
Engineer's estimate: $5,222,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. NLS Paving, Inc |
|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 1,113 | $4.75 | $8.00 |
| 2 | Curb removed (202E32000) | FT | 76 | $16.75 | $35.00 |
| 3 | Excavation (203E10000) | CY | 250 | $150.00 | $90.00 |
| 4 | Subgrade compaction (204E10000) | SY | 750 | $5.50 | $4.50 |
| 5 | Preparing subgrade for shoulder paving (209E72050) | MI | 25.96 | $1,500.00 | $1,400.00 |
| 6 | Curb ramp (608E52000) | SF | 1,138 | $30.00 | $31.00 |
| 7 | Catch basin adjusted to grade (611E98630) | EACH | 3 | $1,100.00 | $1,850.00 |
| 8 | Manhole adjusted to grade (611E99654) | EACH | 2 | $1,100.00 | $1,500.00 |
| 9 | Full depth pavement sawing (252E01500) | FT | 1,620 | $5.35 | $1.60 |
| 10 | Pavement repair (253E02000) | CY | 1,480 | $350.00 | $400.00 |
| 11 | Pavement planing, asphalt concrete , 1.50" (254E01000) | SY | 7,623 | $5.00 | $3.50 |
| 12 | Pavement planing, asphalt concrete, 3.25" (254E01000) | SY | 10,559 | $6.00 | $3.75 |
| 13 | Pavement planing, asphalt concrete, bridge (254E01000) | SY | 3,674 | $6.50 | $4.00 |
| 14 | Pavement planing, portland cement concrete, variab (254E01010) | SY | 223 | $5.00 | $25.00 |
| 15 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 98 | $325.00 | $320.00 |
| 16 | Aggregate base (304E20000) | CY | 112 | $175.00 | $180.00 |
| 17 | Tack coat, 702.13 (407E13900) | GAL | 18 | $3.50 | $3.20 |
| 18 | Non-tracking tack coat (407E20000) | GAL | 25,117 | $3.50 | $3.20 |
| 19 | Prime coat (408E10000) | GAL | 11,536 | $5.00 | $4.50 |
| 20 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 8,464 | $225.00 | $220.00 |
| 21 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 9,158 | $200.00 | $210.00 |
| 22 | Curb, type 6 (609E26000) | FT | 16 | $83.50 | $120.00 |
| 23 | Compacted aggregate (617E10100) | CY | 1,307 | $100.00 | $100.00 |
| 24 | Valve box adjusted to grade (638E10800) | EACH | 6 | $1,100.00 | $350.00 |
| 25 | RPM (621E00100) | EACH | 1,525 | $36.00 | $36.00 |
| 26 | Raised pavement marker removed (621E54000) | EACH | 1,525 | $19.50 | $20.00 |
| 27 | Edge line, 6", type 1 (642E00104) | MI | 26.82 | $795.00 | $815.00 |
| 28 | Center line, type 1 (642E00300) | MI | 13.41 | $1,190.00 | $1,050.00 |
| 29 | Stop line (644E00500) | FT | 536 | $9.50 | $13.00 |
| 30 | Crosswalk line, 24" (644E00630) | FT | 168 | $8.15 | $14.00 |
| 31 | Parking lot stall marking (644E01200) | FT | 92 | $3.00 | $6.00 |
| 32 | Work zone marking sign (614E12460) | EACH | 107 | $80.00 | $80.00 |
| 33 | Work zone center line, class I, 642 paint (614E21100) | MI | 27.51 | $1,245.00 | $1,255.00 |
| 34 | Work zone center line, class II, 642 paint (614E21500) | MI | 27.51 | $290.00 | $450.00 |
| 35 | Polymer modified asphalt expansion joint system (846E00110) | CF | 23 | $800.00 | $895.00 |
| 36 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $28,500 | $25,000 |
| 37 | Maintaining traffic (614E11000) | LS | 1 | $336,718 | $220,000 |
| 38 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $6,500.00 | $10,000 |
| 39 | Mobilization (624E10000) | LS | 1 | $42,450 | $150,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.