ODOT contract 250382 bid tabulation

MRG-SR 78-18.91 (TWO LANE RESURFACING). Let by Ohio DOT on August 14, 2025, MRG. 2 bids received; low bid $5,463,646 by Shelly & Sands Inc, +4.6% against the engineer's estimate of $5,222,000.

Owner
Ohio DOT
Letting
14 AUG 2025
Pay items
39
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly & Sands Inc$5,463,646Low+5.0%
2NLS Paving, Inc$5,514,855+1.0%+6.0%
ODOT contract 250382: bids by rank

Engineer's estimate: $5,222,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly & Sands Inc2. NLS Paving, Inc
1Walk removed (202E30000)SF1,113$4.75$8.00
2Curb removed (202E32000)FT76$16.75$35.00
3Excavation (203E10000)CY250$150.00$90.00
4Subgrade compaction (204E10000)SY750$5.50$4.50
5Preparing subgrade for shoulder paving (209E72050)MI25.96$1,500.00$1,400.00
6Curb ramp (608E52000)SF1,138$30.00$31.00
7Catch basin adjusted to grade (611E98630)EACH3$1,100.00$1,850.00
8Manhole adjusted to grade (611E99654)EACH2$1,100.00$1,500.00
9Full depth pavement sawing (252E01500)FT1,620$5.35$1.60
10Pavement repair (253E02000)CY1,480$350.00$400.00
11Pavement planing, asphalt concrete , 1.50" (254E01000)SY7,623$5.00$3.50
12Pavement planing, asphalt concrete, 3.25" (254E01000)SY10,559$6.00$3.75
13Pavement planing, asphalt concrete, bridge (254E01000)SY3,674$6.50$4.00
14Pavement planing, portland cement concrete, variab (254E01010)SY223$5.00$25.00
15Asphalt concrete base, PG64-22, (449) (301E56000)CY98$325.00$320.00
16Aggregate base (304E20000)CY112$175.00$180.00
17Tack coat, 702.13 (407E13900)GAL18$3.50$3.20
18Non-tracking tack coat (407E20000)GAL25,117$3.50$3.20
19Prime coat (408E10000)GAL11,536$5.00$4.50
20Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY8,464$225.00$220.00
21Asphalt concrete intermediate course, type 2, (448) (441E50300)CY9,158$200.00$210.00
22Curb, type 6 (609E26000)FT16$83.50$120.00
23Compacted aggregate (617E10100)CY1,307$100.00$100.00
24Valve box adjusted to grade (638E10800)EACH6$1,100.00$350.00
25RPM (621E00100)EACH1,525$36.00$36.00
26Raised pavement marker removed (621E54000)EACH1,525$19.50$20.00
27Edge line, 6", type 1 (642E00104)MI26.82$795.00$815.00
28Center line, type 1 (642E00300)MI13.41$1,190.00$1,050.00
29Stop line (644E00500)FT536$9.50$13.00
30Crosswalk line, 24" (644E00630)FT168$8.15$14.00
31Parking lot stall marking (644E01200)FT92$3.00$6.00
32Work zone marking sign (614E12460)EACH107$80.00$80.00
33Work zone center line, class I, 642 paint (614E21100)MI27.51$1,245.00$1,255.00
34Work zone center line, class II, 642 paint (614E21500)MI27.51$290.00$450.00
35Polymer modified asphalt expansion joint system (846E00110)CF23$800.00$895.00
36Premium for contract performance bond and for payment bond (103E05000)LS1$28,500$25,000
37Maintaining traffic (614E11000)LS1$336,718$220,000
38Construction layout stakes and surveying, as per plan (623E10001)LS1$6,500.00$10,000
39Mobilization (624E10000)LS1$42,450$150,000
ODOT contract 250382: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy