ODOT contract 260035 bid tabulation

D04-PM/RPM FY2026 (East) (PAVEMENT MARKING). Let by Ohio DOT on January 15, 2026, District 4. 3 bids received; low bid $1,910,904 by Alpha Space Control LLC, -32% against the engineer's estimate of $2,814,000.

Owner
Ohio DOT
Letting
15 JAN 2026
Pay items
65
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Alpha Space Control LLC$1,910,904Low-32%
2The Aero-Mark Company LLC$2,144,000+12%-24%
3Oglesby Construction Inc$2,475,293+30%-12%
ODOT contract 260035: bids by rank

Engineer's estimate: $2,814,000.

Bid tabulation

LinePay itemUnitQuantity1. Alpha Space Control LLC2. The Aero-Mark Company LLC3. Oglesby Construction Inc
1RPM reflector (621E00300)EACH16,207$4.44$9.25$9.25
2Edge line, 6", type 1 (642E00104)MI1,434.65$587.25$625.00$715.00
3Edge line, 6", type 1 (642E00104)MI50$625.65$625.00$700.00
4Lane line, 6", type 1 (642E00204)MI245.58$298.55$354.00$365.00
5Lane line, 6", type 1 (642E00204)MI10$305.25$354.00$340.00
6Center line, type 1 (642E00300)MI516.23$385.15$584.00$680.00
7Center line, type 1 (642E00300)MI30$433.45$584.00$655.00
8Channelizing line, 8", type 1 (642E00400)FT33,482$0.40$0.50$0.55
9Channelizing line, 8", type 1 (642E00400)FT3,750$0.40$0.50$0.55
10Channelizing line, 12", type 1 (642E00404)FT160,671$0.51$0.50$0.60
11Channelizing line, 12", type 1 (642E00404)FT175$0.56$0.50$0.60
12Stop line, type 1 (642E00500)FT12,994$2.95$2.75$5.00
13Stop line, type 1 (642E00500)FT650$4.65$2.75$5.00
14Crosswalk line, 12", type 1 (642E00620)FT13,229$1.93$2.25$3.10
15Crosswalk line, 12", type 1 (642E00620)FT175$1.95$2.25$3.10
16Crosswalk line, 24", type 1 (642E00630)FT54$3.50$2.25$4.95
17Transverse/diagonal line, type 1 (642E00700)FT11,637$2.20$2.25$4.00
18Transverse/diagonal line, type 1 (642E00700)FT1,250$2.65$2.25$4.00
19Chevron marking, type 1 (642E00720)FT2,918$3.65$2.25$12.00
20Island marking, type 1 (642E00900)SF4,190$2.25$1.50$3.30
21Island marking, type 1 (642E00900)SF163$2.25$1.50$3.30
22Railroad symbol marking, type 1 (642E01000)EACH48$315.00$300.00$400.00
23Railroad symbol marking, type 1 (642E01000)EACH3$330.00$300.00$400.00
24School symbol marking, 96", type 1 (642E01110)EACH58$245.00$300.00$300.00
25School symbol marking, 96", type 1 (642E01110)EACH10$250.00$300.00$300.00
26Parking lot stall marking, type 1 (642E01200)FT1,495$1.45$3.00$1.20
27Parking lot stall marking, type 1 (642E01200)FT500$1.45$3.00$1.20
28Parking lot stall marking, type 1A (642E01210)FT75$1.45$3.00$1.20
29Lane arrow, type 1 (642E01300)EACH1,398$54.25$58.00$50.00
30Lane arrow, type 1 (642E01300)EACH38$54.25$58.00$50.00
31Lane reduction arrow, type 1 (642E01312)EACH6$275.00$250.00$160.00
32Lane reduction arrow, type 1 (642E01312)EACH5$275.00$250.00$160.00
33Wrong way arrow, type 1 (642E01322)EACH122$205.00$190.00$115.00
34Word on pavement, 96", type 1 (642E01410)EACH2$65.00$500.00$115.00
35Dotted line, 6", type 1 (642E01510)FT99,519$0.44$0.50$0.65
36Dotted line, 6", type 1 (642E01510)FT1,290$0.50$0.50$0.60
37Handicap symbol marking, type 1 (642E01702)EACH6$47.45$75.00$50.00
38Handicap symbol marking, type 1 (642E01702)EACH3$47.45$75.00$50.00
39Removal of pavement marking (642E30000)FT1,250$2.85$5.00$1.00
40Removal of pavement marking, work order (642E30010)SF250$3.00$5.00$1.00
41Removal of pavement marking (642E30020)EACH12$125.00$150.00$250.00
42Speed measurement marking (642E40000)EACH25$285.00$900.00$325.00
43Pavement marking, misc.:, work order (642E50010)EACH8$67.95$1,000.00$2,000.00
44Removal of pavement marking (644E30000)FT500$2.85$5.00$1.00
45Removal of pavement marking (644E30010)SF100$3.00$5.00$1.00
46Removal of pavement marking (644E30020)EACH25$125.00$150.00$250.00
47Edge line, 6" (646E10010)MI10$2,150.00$3,900.00$2,450.00
48Lane line, 6" (646E10110)MI10$1,145.30$2,200.00$1,100.00
49Center line (646E10200)MI5$2,675.00$4,000.00$3,500.00
50Channelizing line, 12" (646E10310)FT1,000$1.15$2.00$0.75
51Stop line (646E10400)FT100$6.50$15.00$5.00
52Transverse/diagonal line (646E10600)FT150$6.50$10.00$5.00
53Lane arrow (646E20300)EACH10$87.50$200.00$55.00
54Wrong way arrow (646E20320)EACH10$215.00$300.00$1.00
55Dotted line (646E20500)FT500$1.45$3.00$0.75
56Law enforcement officer with patrol car for assistance (614E11110)HR80$55.00$65.00$100.00
57Maintenance of traffic, one lane closure on A two lane highway (614E13600)EACH13$750.00$500.00$500.00
58Maintenance of traffic, one lane closure on A four lane undivided highway (614E13700)EACH13$750.00$500.00$500.00
59Maintenance of traffic, one lane closure on A 4 lane or greater divided highway (614E13800)EACH13$750.00$500.00$500.00
60Portable changeable message sign, as per plan (614E18601)SNMT2$85.00$750.00$1,000.00
61Premium for contract performance bond and for payment bond (103E05000)LS1$30,000$9,565.61$12,500
62Maintaining traffic (614E11000)LS1$1,500.00$4,250.00$60,000
63Construction layout stakes and surveying (623E10000)LS1$1.00$1.00$1.00
64Mobilization (624E10000)LS1$15,000$4,250.00$70,000
65Mobilization, as per plan (624E15001)EACH25$5,000.00$2,450.00$500.00
ODOT contract 260035: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.