ODOT letting results, January 15, 2026
39 contracts let by Ohio DOT on January 15, 2026, $88,424,976 in low bids, a median of 3 bidders per contract. On the 38 with an engineer's estimate, the low bid came in under it 21 times; median low bid -4.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 39
- Low bids, total
- $88,424,976
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 260014 | HAM-IR 275-36.66 (FOUR LANE RESURFACING) | HAM | 2 | John R Jurgensen Company | $9,848,241 | $11,682,088 | +19% | +31% | ODOT |
| 260026 | RIC-IR 71-10.76 (FOUR LANE RESURFACING) | RIC | 2 | Shelly & Sands Inc | $7,853,502 | $8,391,646 | +7.0% | -18% | ODOT |
| 260016 | HAM-SR 126-VAR (BRIDGE REPAIR) | HAM | 1 | 360 Construction Company Inc | $6,184,753 | +19% | ODOT | ||
| 260021 | LOG-PAVE-FY26 (TWO LANE RESURFACING) | LOG | 1 | Shelly Company | $5,373,660 | +8.0% | ODOT | ||
| 268000 | TRU-IR 80-11.32 Truck Parking (PARKING AREAS) | TRU | 7 | Shelly & Sands Inc | $4,717,162 | $4,797,256 | +2.0% | -32% | ODOT |
| 260015 | HAM-SR 126-06.86 (FOUR LANE RESURFACING) | HAM | 2 | Barrett Paving Materials Inc | $4,514,528 | $4,798,851 | +6.0% | 0.0% | ODOT |
| 260025 | POR-SR 82/VAR-10.64/VAR (TWO LANE RESURFACING) | POR | 5 | Ronyak Paving Inc | $4,051,587 | $4,175,000 | +3.0% | -12% | ODOT |
| 260038 | D06-PMF-FY2026 (PAVEMENT MARKING) | District 6 | 3 | Alpha Space Control LLC | $3,762,746 | $3,967,000 | +5.0% | -24% | ODOT |
| 260029 | WOO-SR 795-01.76 Resurf & Overlay (BRIDGE REPAIR) | WOO | 2 | Vernon Nagel Inc | $3,157,003 | $3,433,270 | +9.0% | -23% | ODOT |
| 260031 | CUY-SR 176-10.65 (MISCELLANEOUS) | CUY | 2 | Karvo Companies Inc | $2,967,842 | $3,292,365 | +11% | +22% | ODOT |
| 260028 | UNI-SR 31-15.55, UNI-SR 347-03.89 (TWO LANE RESURFACING) | UNI | 1 | Shelly Company | $2,909,674 | +7.0% | ODOT | ||
| 260017 | HAM-SR 128-00.00 (TWO LANE RESURFACING) | HAM | 2 | Barrett Paving Materials Inc | $2,751,661 | $3,414,390 | +24% | +11% | ODOT |
| 260009 | BUT-SR 122-00.00 (TWO LANE RESURFACING) | BUT | 2 | Barrett Paving Materials Inc | $2,589,998 | $2,956,545 | +14% | +20% | ODOT |
| 260013 | D12-PPM FY2026 (SPOT PATCHING / PAVEMENT REPAIR) | District 12 | 4 | Karvo Companies Inc | $2,375,588 | $2,503,549 | +5.0% | +13% | ODOT |
| 260018 | HIG-SR 73-21.04 (BRIDGE REPLACEMENT (1 BRIDGE)) | HIG | 4 | D G M Inc | $2,244,819 | $2,249,311 | 0.0% | -6.0% | ODOT |
| 260035 | D04-PM/RPM FY2026 (East) (PAVEMENT MARKING) | District 4 | 3 | Alpha Space Control LLC | $1,910,904 | $2,144,000 | +12% | -32% | ODOT |
| 260012 | D01-BP FY26 (BRIDGE PAINTING) | District 1 | 7 | Elite Contractors Inc | $1,893,660 | $2,137,152 | +13% | -10% | ODOT |
| 260010 | CUY-IR 480-13.04 Ramps (MINOR RECONSTRUCTION) | CUY | 9 | Tri-Mor Corp | $1,870,651 | $1,991,437 | +6.0% | -15% | ODOT |
| 250607 | MRW-/MRW-IR 71/SR 288-17.013 R/0.073 | MRW | 2 | Vimas Painting Company Inc | $1,837,660 | $2,154,853 | +17% | ODOT | |
| 260024 | PAU-SR 49/SR 500/SR 613-Varies (TWO LANE RESURFACING) | PAU | 2 | Shelly Company | $1,598,848 | $2,096,697 | +31% | -4.0% | ODOT |
| 260020 | LAW-SR 378-04.84 (BRIDGE REPLACEMENT (1 BRIDGE)) | LAW | 4 | R C Construction Company and Son Inc | $1,568,946 | $1,631,449 | +4.0% | +8.0% | ODOT |
| 260022 | LUC-US 20A-09.77 Roundabout (INTERSECTION) | LUC | 4 | Vernon Nagel Inc | $1,529,372 | $1,576,377 | +3.0% | -17% | ODOT |
| 260019 | JEF-SR 213-04.51 (SLIDE REPAIR) | JEF | 8 | Marucci & Gaffney Excavating Co | $1,423,293 | $1,518,470 | +7.0% | -23% | ODOT |
| 260039 | LAW-SR 775/SR 790-18.51/00.00 (TWO LANE RESURFACING) | LAW | 1 | Shelly Company | $1,339,401 | +15% | ODOT | ||
| 260023 | MOT-/MIA-NW-FY26 (NOISE WALLS) | MOT | 3 | Eagle Bridge Co | $1,151,203 | $1,381,988 | +20% | +17% | ODOT |
| 260006 | ATH-SR 13-13.71 (SLIDE REPAIR) | ATH | 7 | Allard Excavation LLC | $984,857 | $886,436 | -10% | -4.0% | ODOT |
| 260007 | ATH-SR 682-04.70 (SIDEWALK) | ATH | 5 | Shelly & Sands Inc | $951,988 | $966,583 | +2.0% | -9.0% | ODOT |
| 264001 | CUY-SR 82-00.93 (CULVERT REPLACEMENT) | CUY | 5 | Shook Company LLC | $678,678 | $649,539 | -4.0% | +19% | ODOT |
| 264000 | COL-SR 644-07.96 (MISCELLANEOUS) | COL | 4 | S.T.A.R.T., LLC | $665,351 | $660,049 | -1.0% | +4.0% | ODOT |
| 260008 | BEL-SR 149-15.10 (SLIDE REPAIR) | BEL | 4 | Shelly & Sands Inc | $558,225 | $570,000 | +2.0% | +4.0% | ODOT |
| 260005 | JAC-SR 327/SR 32-13.58/17.51 (CULVERT REPLACEMENT) | JAC | 5 | D G M Inc | $536,376 | $588,633 | +10% | +13% | ODOT |
| 260040 | UNI-US 42-SP-FY2026 (GENERAL) (SPOT PATCHING / PAVEMENT REPAIR) | UNI | 3 | Shelly & Sands Inc | $528,029 | $549,798 | +4.0% | -33% | ODOT |
| 260034 | D03-SYSSIGN FY2026 (SIGNING) | District 3 | 2 | Cleveland Barricading Systems LLC | $525,537 | $576,480 | +10% | -5.0% | ODOT |
| 260036 | D05-PM FY2026 (C) R-WR (PAVEMENT MARKING) | District 5 | 3 | Oglesby Construction Inc | $413,058 | $424,882 | +3.0% | -39% | ODOT |
| 264002 | HOL-SR 39-00.25 (CULVERT REPLACEMENT) | HOL | 7 | V O Menuez & Son Inc | $355,966 | $445,087 | +25% | -27% | ODOT |
| 260030 | WYA-US 23-09.28 (SIGNING) | WYA | 3 | Cleveland Barricading Systems LLC | $252,068 | $318,425 | +26% | -25% | ODOT |
| 260037 | D05-RPM FY2026 (RAISED PAVEMENT MARKERS) | District 5 | 3 | Alpha Space Control LLC | $219,968 | $225,646 | +3.0% | -18% | ODOT |
| 260032 | D03-MOW FY2026 (A) (MOWING) | District 3 | 4 | Linkel Company | $176,584 | $184,840 | +5.0% | -1.0% | ODOT |
| 260033 | D03-MOW FY2026 (B) (MOWING) | District 3 | 3 | Linkel Company | $151,590 | $155,640 | +3.0% | +4.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.