| 1 | Pavement removed (202E23000) | SY | 4,206 | $12.87 | $30.00 |
| 2 | Curb removed (202E32000) | FT | 977 | $17.00 | $30.00 |
| 3 | Guardrail removed (202E38000) | FT | 27,076 | $3.00 | $3.00 |
| 4 | Anchor assembly removed, type E (202E42010) | EACH | 16 | $150.00 | $150.00 |
| 5 | Anchor assembly removed, type T (202E42040) | EACH | 14 | $100.00 | $100.00 |
| 6 | Anchor assembly removed, type B (202E42050) | EACH | 4 | $150.00 | $150.00 |
| 7 | Bridge terminal assembly removed (202E47000) | EACH | 27 | $250.00 | $250.00 |
| 8 | Cable barrier removed for storage (202E48100) | FT | 2,074 | $14.91 | $20.74 |
| 9 | Reshaping under guardrail (209E15000) | STA | 283 | $92.32 | $100.00 |
| 10 | Linear grading (209E60500) | MI | 5.64 | $3,970.55 | $2,000.00 |
| 11 | Borrow (209E70000) | CY | 2,516 | $162.46 | $160.00 |
| 12 | Guardrail, type MGS with long posts (606E15100) | FT | 26,712.50 | $26.75 | $26.75 |
| 13 | Anchor assembly, MGS type B (606E26050) | EACH | 1 | $2,250.00 | $2,250.00 |
| 14 | Anchor assembly, MGS type E (606E26150) | EACH | 18 | $2,400.00 | $2,400.00 |
| 15 | Anchor assembly, MGS type T (606E26550) | EACH | 14 | $1,150.00 | $1,150.00 |
| 16 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 17 | $2,400.00 | $2,400.00 |
| 17 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 11 | $350.00 | $350.00 |
| 18 | Special - mow strip (690E98300) | SY | 1,152 | $68.72 | $100.00 |
| 21 | Special - cable barrier, (brifen) (alternate 2) [alternate group AA2] (606E55000) | FT | 2,024 | $24.50 | $24.50 |
| 22 | Special - cable barrier, anchor assembly (606E55150) | EACH | 2 | $4,600.00 | $4,600.00 |
| 23 | Seeding and mulching (659E10000) | SY | 9,933 | $0.92 | $1.53 |
| 24 | Commercial fertilizer (659E20000) | TON | 1.34 | $1,500.00 | $900.00 |
| 25 | Lime (659E31000) | ACRE | 2.05 | $200.00 | $100.00 |
| 26 | Water (659E35000) | MGAL | 27 | $1.00 | $10.00 |
| 27 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 |
| 28 | Catch basin adjusted to grade (611E98630) | EACH | 3 | $2,004.88 | $3,000.00 |
| 29 | Pavement planing, asphalt concrete, 3.25" (254E01000) | SY | 21,068 | $4.25 | $10.00 |
| 30 | Patching planed surface (254E01600) | SY | 214 | $11.50 | $5.00 |
| 31 | Full depth pavement removal and rigid replacement, type 2, class QC RS (255E19100) | SY | 1,262 | $820.87 | $563.00 |
| 32 | Full depth pavement sawing (255E20000) | FT | 4,914 | $2.52 | $3.50 |
| 33 | Retrofit dowel bar (258E10000) | EACH | 2,652 | $186.45 | $135.50 |
| 34 | Aggregate base (304E20000) | CY | 6.10 | $478.25 | $750.00 |
| 35 | Tack coat, 702.13 (407E13900) | GAL | 13,142 | $5.00 | $5.50 |
| 36 | Non-tracking tack coat (407E20000) | GAL | 9,856 | $5.00 | $4.50 |
| 37 | Anti-segregation equipment (442E00100) | CY | 11,051 | $12.00 | $35.00 |
| 38 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 10,969 | $226.43 | $255.00 |
| 39 | Asphalt concrete intermediate course, 19 MM, type A (449) (442E22400) | CY | 118 | $226.52 | $265.00 |
| 40 | Asphalt concrete surface course, 12.5 MM, type A (447) (442E10300) | CY | 7,068 | $286.35 | $280.00 |
| 41 | Special - pressure relief joint, type A (451E30000) | FT | 702 | $360.85 | $300.00 |
| 42 | Combination curb and gutter, type 3 (609E18000) | FT | 347 | $36.00 | $90.00 |
| 43 | Combination curb and gutter, type 4, as per plan (609E23001) | FT | 36 | $40.00 | $97.00 |
| 44 | Curb, type 6 (609E26000) | FT | 630 | $25.00 | $50.00 |
| 45 | Compacted aggregate (617E10100) | CY | 73 | $350.46 | $650.00 |
| 46 | Shoulder preparation (617E20000) | SY | 1,306 | $5.72 | $1.50 |
| 47 | Water (617E25000) | MGAL | 1 | $7.93 | $25.00 |
| 48 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 12.95 | $1,075.00 | $3,000.00 |
| 49 | RPM (621E00100) | EACH | 783 | $37.00 | $37.00 |
| 50 | Raised pavement marker removed (621E54000) | EACH | 722 | $12.90 | $10.00 |
| 51 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 298 | $10.00 | $10.00 |
| 52 | Barrier reflector, type 6 (626E00118) | EACH | 21 | $20.00 | $5.00 |
| 53 | Stop line (644E00500) | FT | 65 | $10.00 | $10.00 |
| 54 | Transverse/diagonal line (644E00700) | FT | 542 | $11.00 | $11.00 |
| 55 | Chevron marking (644E00720) | FT | 1,072 | $11.00 | $11.00 |
| 56 | Lane arrow (644E01300) | EACH | 7 | $150.00 | $150.00 |
| 57 | Lane reduction arrow (644E01350) | EACH | 5 | $275.00 | $275.00 |
| 58 | Wrong way arrow (644E01360) | EACH | 5 | $175.00 | $175.00 |
| 59 | Edge line, 6", type A4 (645E00118) | MI | 0.58 | $25,000 | $25,000 |
| 60 | Lane line, 6", type A4 (645E00220) | MI | 0.34 | $9,000.00 | $9,000.00 |
| 61 | Dotted line, 6", type A4 (645E01522) | FT | 260 | $2.50 | $2.50 |
| 62 | Transverse/diagonal line (646E10600) | FT | 91 | $10.00 | $10.00 |
| 63 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 12.95 | $4,080.00 | $4,080.00 |
| 64 | Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110) | MI | 6.36 | $1,500.00 | $1,500.00 |
| 65 | Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310) | FT | 5,676 | $2.50 | $2.50 |
| 66 | Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410) | FT | 3,669 | $0.85 | $0.85 |
| 67 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 20 | $1,390.00 | $1,390.00 |
| 68 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 5,676 | $1.30 | $1.30 |
| 69 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 0.97 | $1,800.00 | $1,800.00 |
| 70 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 450 | $138.84 | $100.00 |
| 71 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $889.10 | $889.10 |
| 72 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 6.36 | $660.00 | $660.00 |
| 73 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 6.36 | $660.00 | $660.00 |
| 74 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 12.95 | $890.00 | $890.00 |
| 75 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 12.95 | $890.00 | $890.00 |
| 76 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 5,676 | $0.95 | $0.95 |
| 77 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 5,676 | $0.95 | $0.95 |
| 78 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 3,669 | $0.70 | $0.70 |
| 79 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 3,669 | $0.70 | $0.70 |
| 80 | Work zone transverse/diagonal line, class I, 642 paint (614E25200) | FT | 542 | $4.00 | $4.00 |
| 81 | Work zone transverse/diagonal line, class III, 642 paint (614E25620) | FT | 542 | $4.00 | $4.00 |
| 82 | Work zone stop line, class I, 642 paint (614E26200) | FT | 65 | $8.00 | $8.00 |
| 83 | Work zone stop line, class III, 642 paint (614E26610) | FT | 65 | $8.00 | $8.00 |
| 84 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 36 | $776.89 | $776.89 |
| 85 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $32,740 | $71,044 |
| 86 | Maintaining traffic (614E11000) | LS | 1 | $575,383 | $2,100,000 |
| 87 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $12,369 | $35,000 |
| 88 | Mobilization (624E10000) | LS | 1 | $487,500 | $400,000 |