John R Jurgensen Company: ODOT bid record

John R Jurgensen Company submitted 345 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 29 OCT 2026, and was the low bidder on 107 of them (31%). When it was not low, its total sat a median +18% above the low bid.

Owner
Ohio DOT
Low bid volume
$834,006,810
Latest bid
29 OCT 2026
Data through
12 NOV 2026
345Bids
107Low bids
31Win rate, percent
+18%Median gap to the low bid when not low, 238 bids

By year

YearBidsLow bidsWin rate
202049816%
2021561425%
2022562138%
2023501632%
2024571933%
2025471940%
2026301033%
John R Jurgensen Company, ODOT: bids and low bids by year of letting

By county

CountyBidsLow bidsWin rate
HAM772532%
MOT481633%
CLE341544%
BUT33927%
WAR20735%
HIG2000%
CLI19842%
BRO19211%
GRE16850%
PRE13215%
CLA12217%
FAY11873%
John R Jurgensen Company, ODOT: bids and low bids by county

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Erosion control832E30000EACH253253 (100%)$1.00$1.00
RPM621E00100EACH240170 (71%)$38.10$52.92
Stop line644E00500FT193157 (81%)$7.00$8.29
Water659E35000MGAL200147 (74%)$1.00$1.00
Work zone stop line, class III, 642 paint614E26610FT149126 (85%)$3.50$3.50
Center line644E00300MI162125 (77%)$5,456.00$7,070.00
Lane arrow644E01300EACH150124 (83%)$115.00$110.00
Work zone center line, class III, 642 paint614E21550MI136109 (80%)$1,537.50$1,186.00
Sealing of concrete surfaces (epoxy-urethane)512E10100SY139104 (75%)$26.50$34.00
Seeding and mulching659E10000SY18599 (54%)$1.75$2.60
Transverse/diagonal line644E00700FT11395 (84%)$6.05$7.00
Edge line, 6"644E00104MI12993 (72%)$4,270.00$5,000.00
John R Jurgensen Company, ODOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

John R Jurgensen Company, ODOT: the firms on the same contracts most often

Latest bids

LetContractCountyProjectRankIts bidAgainst the low bid
29 OCT 2026260474WARWAR-IR 71-00.00 (FOUR LANE RESURFACING)2 of 2$12,830,188+15%
15 OCT 2026260460GREGRE-IR 675-09.41 (SPOT PATCHING / PAVEMENT REPAIR)1 of 2$682,880Low, 34% under the second
15 OCT 2026260462HAMHAM-US 42-09.73/12.29 (FOUR LANE RESURFACING)2 of 2$1,170,712+14%
15 OCT 2026260470MOTMOT-SR 48-00.00/17.05 (TWO LANE RESURFACING)2 of 2$2,141,838+16%
08 OCT 2026260398HAMHAM-IR 75-07.85 (MAJOR WIDENING)1 of 1$199,003,213Low
01 OCT 2026260439WARWAR-SR 73-01.49 S Main St Resurf (TWO LANE RESURFACING)3 of 3$1,211,178+36%
17 SEP 2026260407HIGHIG-US 62-00.00 (TWO LANE RESURFACING)4 of 4$2,752,910+32%
30 JUL 2026260347FAYFAY-US 22-00.00, FAY-US 62-00.00 / VAR (FOUR LANE RESURFACING)1 of 2$7,535,868Low, 16% under the second
30 JUL 2026268015PREPRE-IR 70 WB Truck Parking (PARKING AREAS)6 of 6$16,946,821+42%
16 JUL 2026260306BUTBUT-/WAR-IR 75-07.04/00.00 Long Jts2 of 2$6,846,717+49%
11 JUN 2026260288HAMHAM-/CLE-US 52-35.22/00.00 (SPOT PATCHING / PAVEMENT REPAIR)1 of 2$908,492Low, 12% under the second
21 MAY 2026268010District 8D08-Davids Drive Reconstruction (MINOR RECONSTRUCTION)1 of 5$2,057,042Low, 7.0% under the second
07 MAY 2026260251MOTMOT-/WAR-IR 75-11.56/00.00 (MAJOR RECONSTRUCTION)1 of 2$55,097,195Low, 21% under the second
07 MAY 2026268008HAMHAM-CR 128/CR 161 Roundabout (INTERSECTION)2 of 4$2,400,809+2.0%
09 APR 2026260170CLECLE-SR 32-09.80 Herold Rd (INTERSECTION)1 of 3$762,909Low, 0.0% under the second
09 APR 2026260184WARWAR-SR 123-16.79 (MINOR RECONSTRUCTION)2 of 3$846,720+4.0%
26 MAR 2026260121HAMHAM-CR 158/CR 460-02.04/00.54 (INTERSECTION)4 of 4$2,719,403+13%
26 MAR 2026260124HAMHAM-IR 74-07.05 (FOUR LANE RESURFACING)2 of 2$11,372,870+19%
26 MAR 2026260144CLECLE-US 50-02.25 (BRIDGE REPAIR)5 of 5$1,502,953+129%
26 MAR 2026260145District 8D08-Noise Walls FY2026 (NOISE WALLS)3 of 3$4,510,553+42%
26 MAR 2026260149HAMHAM-CR 196-01.89 Delhi Ave (INTERSECTION)3 of 4$1,594,615+4.0%
12 MAR 2026260122HAMHAM-CR 299-05.78 Loveland Madeira (SIDEWALK)4 of 5$2,312,714+29%
19 FEB 2026260101WARWAR-SR 73-05.88 (TWO LANE RESURFACING)2 of 2$1,043,643+8.0%
29 JAN 2026260043BUTBUT-SR 73-16.05 (TWO LANE RESURFACING)3 of 3$976,410+11%
29 JAN 2026260048CLECLE-SR 125-08.95 (FOUR LANE RESURFACING)1 of 2$2,820,429Low, 8.0% under the second
John R Jurgensen Company: latest ODOT bids in the data

How this record was read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way