ODOT contract 268010 bid tabulation

D08-Davids Drive Reconstruction (MINOR RECONSTRUCTION). Let by Ohio DOT on May 21, 2026, District 8. 5 bids received; low bid $2,057,042 by John R Jurgensen Company, -8.3% against the engineer's estimate of $2,243,000.

Owner
Ohio DOT
Letting
21 MAY 2026
Pay items
69
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1John R Jurgensen Company$2,057,042Low-8.0%
2Fillmore Construction$2,196,687+7.0%-2.0%
3Sunesis Construction Co$2,223,046+8.0%-1.0%
4KT Holden Construction LLC$2,235,528+9.0%0.0%
5R B Jergens Contractors Inc$2,346,410+14%+5.0%
ODOT contract 268010: bids by rank

Engineer's estimate: $2,243,000.

Bid tabulation

LinePay itemUnitQuantity1. John R Jurgensen Company2. Fillmore Construction3. Sunesis Construction Co4. KT Holden Construction LLC5. R B Jergens Contractors Inc
1Clearing and grubbing (201E11000)LS1$2,168.00$2,500.00$11,932$1,444.00$7,864.72
2Curb and gutter removed (202E32500)FT6,758$4.70$10.00$2.45$5.00$5.22
3Pipe removed, 24" and under (202E35100)FT539$38.01$25.00$8.28$9.00$38.79
4Catch basin removed (202E58100)EACH19$576.12$500.00$477.53$430.00$679.20
5Excavation (203E10000)CY6,510$23.33$40.00$40.61$37.20$38.04
6Embankment (203E20000)CY203$20.28$80.00$19.33$8.75$20.94
7Subgrade compaction (204E10000)SY222$3.24$5.00$3.60$2.80$3.84
8Excavation of subgrade (204E13000)CY86$39.22$60.00$51.68$53.10$39.10
9Granular material, type B (204E30010)CY86$79.31$70.00$85.70$82.15$54.25
10Proof rolling (204E45000)HR7$233.03$150.00$248.60$372.15$313.01
11Geotextile fabric (204E50000)SY222$5.74$3.00$2.03$9.25$4.24
12Cement (206E10500)TON448$256.31$224.00$221.49$224.00$241.66
13Curing coat (206E11000)SY14,816$1.33$1.25$1.31$1.25$1.35
14Cement stabilized subgrade, 14 inches deep (206E15020)SY14,816$6.24$3.00$3.28$4.55$4.15
15Tied concrete block mat with type 1 underlayment (601E21050)SY4$280.66$250.00$248.33$240.35$131.84
16Soil analysis test (659E00100)EACH2$200.00$200.00$75.00$200.00$211.21
17Topsoil (659E00300)CY533$60.35$35.00$34.77$46.15$41.41
18Seeding and mulching (659E10000)SY3,624$1.75$1.45$4.97$1.75$1.85
19Repair seeding and mulching (659E14000)SY182$1.00$2.20$1.90$1.00$1.06
20Inter-seeding (659E15000)SY182$0.01$2.20$1.90$0.01$0.01
21Commercial fertilizer (659E20000)TON0.51$1,500.00$1,400.00$760.00$1,500.00$1,584.08
22Lime (659E31000)ACRE0.75$200.00$450.00$50.00$200.00$211.21
23Water (659E35000)MGAL21$1.00$10.00$50.00$1.00$1.06
24Slope erosion protection (670E00500)SY1,170$2.35$2.00$4.00$2.35$2.48
25Storm water pollution prevention plan (832E15000)LS1$2,800.00$2,500.00$1,250.00$2,800.00$2,534.51
26Storm water pollution prevention inspections (832E15002)LS1$6,090.00$10,000$7,500.00$1,120.00$13,306
27Storm water pollution prevention inspection software (832E15010)LS1$6,971.68$12,500$14,972$10,000$21,121
28Erosion control (832E30000)EACH25,000$1.00$1.00$1.00$1.00$1.00
296" unclassified pipe underdrains (605E13300)FT120$34.05$30.00$15.19$19.75$28.51
306" base pipe underdrains (605E14000)FT7,147$13.00$12.00$16.43$17.10$12.81
316" conduit, type F for underdrain outlets (611E00510)FT400$49.11$30.00$32.39$41.75$26.39
3212" conduit, type B (611E04400)FT607$99.27$220.00$100.72$111.65$80.17
3312" conduit, type B (611E04400)FT8$232.34$300.00$291.08$241.50$198.13
3412" conduit, type C (611E04600)FT238$100.18$120.00$88.13$109.80$108.26
3518" conduit, type B (611E07400)FT74$179.69$240.00$172.65$176.15$118.38
3618" conduit, type C (611E07600)FT32$299.12$220.00$138.94$194.10$163.68
3724" conduit, type B (611E10400)FT8$554.21$300.00$279.90$263.45$302.24
3824" conduit, type C (611E10600)FT8$435.24$320.00$395.05$222.40$262.55
39Catch basin, no. 3, as per plan (611E98151)EACH7$2,841.16$3,000.00$3,163.09$3,770.00$3,348.27
40Catch basin, no. 3A (611E98180)EACH7$2,681.49$4,000.00$3,889.38$3,700.00$2,669.60
41Catch basin, no. 3A, as per plan (611E98181)EACH12$2,095.28$2,200.00$2,461.06$3,400.00$3,003.15
42Catch basin adjusted to grade (611E98630)EACH7$1,414.12$1,500.00$549.54$1,705.00$859.43
43Manhole adjusted to grade (611E99654)EACH4$1,414.11$1,500.00$549.54$1,705.00$738.30
44Precast reinforced concrete outlet (611E99710)EACH2$671.30$500.00$474.76$762.00$840.69
45Asphalt concrete base, PG64-22, (449) (301E56000)CY2,162$190.50$184.00$190.50$190.50$274.57
46Aggregate base (304E20000)CY2,470$53.26$64.00$84.73$86.75$57.61
47Non-tracking tack coat (407E20000)GAL1,556$5.00$3.00$5.00$5.00$1.06
48Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY451$270.00$208.00$270.00$270.00$322.09
49Asphalt concrete intermediate course, type 2, (449) (441E70300)CY631$220.00$204.00$220.00$220.00$300.97
50Combination curb and gutter, type 2, as per plan (609E12001)FT6,684$38.65$38.00$40.23$39.55$29.32
51Combination curb and gutter, type 3, as per plan (609E18001)FT60$80.26$38.00$39.79$39.00$39.69
52Ground mounted support, no. 3 post (630E03100)FT39.50$15.50$15.50$15.50$29.65$16.37
53Sign, flat sheet (630E80100)SF18$16.00$16.00$16.00$36.90$16.90
54Removal of ground mounted sign and disposal (630E84900)EACH2$20.00$20.00$20.00$17.05$21.12
55Removal of ground mounted post support and disposal (630E86002)EACH2$25.00$25.00$25.00$22.70$26.40
56Center line (644E00300)MI1.22$5,305.00$6,971.00$5,305.00$7,610.00$5,602.33
57Channelizing line, 12" (644E00404)FT410$2.30$3.00$2.30$1.90$2.43
58Stop line (644E00500)FT44$6.65$11.00$6.65$5.90$7.02
59Crosswalk line, 12" (644E00620)FT203$3.30$5.50$3.30$5.45$3.48
60Lane arrow (644E01300)EACH12$107.00$150.00$107.00$135.00$113.00
61Detour signing (614E12420)LS1$3,995.00$3,995.00$3,995.00$4,059.00$4,286.13
62Portable changeable message sign, as per plan (614E18601)SNMT6$925.00$925.00$925.00$951.30$1,004.58
63Work zone center line, class I, 642 paint (614E21100)MI0.05$13,925$18,900$13,925$13,840$14,705
64Work zone edge line, class I, 4", 642 paint (614E22100)MI0.10$13,585$9,450.00$13,585$8,870.00$14,346
65Water (616E10000)MGAL1$140.21$10.00$14.64$1,600.00$2,765.75
66Premium for contract performance bond and for payment bond (103E05000)LS1$5,026.00$8,500.00$12,284$29,500$11,089
67Maintaining traffic (614E11000)LS1$8,289.39$25,000$3,706.20$8,100.00$20,821
68Construction layout stakes and surveying (623E10000)LS1$5,392.16$8,000.00$29,150$10,500$30,784
69Mobilization (624E10000)LS1$80,000$75,000$84,066$54,210$70,865
ODOT contract 268010: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of May 21, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy