ODOT contract 268010 bid tabulation
D08-Davids Drive Reconstruction (MINOR RECONSTRUCTION). Let by Ohio DOT on May 21, 2026, District 8. 5 bids received; low bid $2,057,042 by John R Jurgensen Company, -8.3% against the engineer's estimate of $2,243,000.
- Owner
- Ohio DOT
- Letting
- 21 MAY 2026
- Pay items
- 69
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | John R Jurgensen Company | $2,057,042 | Low | -8.0% |
| 2 | Fillmore Construction | $2,196,687 | +7.0% | -2.0% |
| 3 | Sunesis Construction Co | $2,223,046 | +8.0% | -1.0% |
| 4 | KT Holden Construction LLC | $2,235,528 | +9.0% | 0.0% |
| 5 | R B Jergens Contractors Inc | $2,346,410 | +14% | +5.0% |
Engineer's estimate: $2,243,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. John R Jurgensen Company | 2. Fillmore Construction | 3. Sunesis Construction Co | 4. KT Holden Construction LLC | 5. R B Jergens Contractors Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,168.00 | $2,500.00 | $11,932 | $1,444.00 | $7,864.72 |
| 2 | Curb and gutter removed (202E32500) | FT | 6,758 | $4.70 | $10.00 | $2.45 | $5.00 | $5.22 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 539 | $38.01 | $25.00 | $8.28 | $9.00 | $38.79 |
| 4 | Catch basin removed (202E58100) | EACH | 19 | $576.12 | $500.00 | $477.53 | $430.00 | $679.20 |
| 5 | Excavation (203E10000) | CY | 6,510 | $23.33 | $40.00 | $40.61 | $37.20 | $38.04 |
| 6 | Embankment (203E20000) | CY | 203 | $20.28 | $80.00 | $19.33 | $8.75 | $20.94 |
| 7 | Subgrade compaction (204E10000) | SY | 222 | $3.24 | $5.00 | $3.60 | $2.80 | $3.84 |
| 8 | Excavation of subgrade (204E13000) | CY | 86 | $39.22 | $60.00 | $51.68 | $53.10 | $39.10 |
| 9 | Granular material, type B (204E30010) | CY | 86 | $79.31 | $70.00 | $85.70 | $82.15 | $54.25 |
| 10 | Proof rolling (204E45000) | HR | 7 | $233.03 | $150.00 | $248.60 | $372.15 | $313.01 |
| 11 | Geotextile fabric (204E50000) | SY | 222 | $5.74 | $3.00 | $2.03 | $9.25 | $4.24 |
| 12 | Cement (206E10500) | TON | 448 | $256.31 | $224.00 | $221.49 | $224.00 | $241.66 |
| 13 | Curing coat (206E11000) | SY | 14,816 | $1.33 | $1.25 | $1.31 | $1.25 | $1.35 |
| 14 | Cement stabilized subgrade, 14 inches deep (206E15020) | SY | 14,816 | $6.24 | $3.00 | $3.28 | $4.55 | $4.15 |
| 15 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 4 | $280.66 | $250.00 | $248.33 | $240.35 | $131.84 |
| 16 | Soil analysis test (659E00100) | EACH | 2 | $200.00 | $200.00 | $75.00 | $200.00 | $211.21 |
| 17 | Topsoil (659E00300) | CY | 533 | $60.35 | $35.00 | $34.77 | $46.15 | $41.41 |
| 18 | Seeding and mulching (659E10000) | SY | 3,624 | $1.75 | $1.45 | $4.97 | $1.75 | $1.85 |
| 19 | Repair seeding and mulching (659E14000) | SY | 182 | $1.00 | $2.20 | $1.90 | $1.00 | $1.06 |
| 20 | Inter-seeding (659E15000) | SY | 182 | $0.01 | $2.20 | $1.90 | $0.01 | $0.01 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.51 | $1,500.00 | $1,400.00 | $760.00 | $1,500.00 | $1,584.08 |
| 22 | Lime (659E31000) | ACRE | 0.75 | $200.00 | $450.00 | $50.00 | $200.00 | $211.21 |
| 23 | Water (659E35000) | MGAL | 21 | $1.00 | $10.00 | $50.00 | $1.00 | $1.06 |
| 24 | Slope erosion protection (670E00500) | SY | 1,170 | $2.35 | $2.00 | $4.00 | $2.35 | $2.48 |
| 25 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,800.00 | $2,500.00 | $1,250.00 | $2,800.00 | $2,534.51 |
| 26 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,090.00 | $10,000 | $7,500.00 | $1,120.00 | $13,306 |
| 27 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $6,971.68 | $12,500 | $14,972 | $10,000 | $21,121 |
| 28 | Erosion control (832E30000) | EACH | 25,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 29 | 6" unclassified pipe underdrains (605E13300) | FT | 120 | $34.05 | $30.00 | $15.19 | $19.75 | $28.51 |
| 30 | 6" base pipe underdrains (605E14000) | FT | 7,147 | $13.00 | $12.00 | $16.43 | $17.10 | $12.81 |
| 31 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 400 | $49.11 | $30.00 | $32.39 | $41.75 | $26.39 |
| 32 | 12" conduit, type B (611E04400) | FT | 607 | $99.27 | $220.00 | $100.72 | $111.65 | $80.17 |
| 33 | 12" conduit, type B (611E04400) | FT | 8 | $232.34 | $300.00 | $291.08 | $241.50 | $198.13 |
| 34 | 12" conduit, type C (611E04600) | FT | 238 | $100.18 | $120.00 | $88.13 | $109.80 | $108.26 |
| 35 | 18" conduit, type B (611E07400) | FT | 74 | $179.69 | $240.00 | $172.65 | $176.15 | $118.38 |
| 36 | 18" conduit, type C (611E07600) | FT | 32 | $299.12 | $220.00 | $138.94 | $194.10 | $163.68 |
| 37 | 24" conduit, type B (611E10400) | FT | 8 | $554.21 | $300.00 | $279.90 | $263.45 | $302.24 |
| 38 | 24" conduit, type C (611E10600) | FT | 8 | $435.24 | $320.00 | $395.05 | $222.40 | $262.55 |
| 39 | Catch basin, no. 3, as per plan (611E98151) | EACH | 7 | $2,841.16 | $3,000.00 | $3,163.09 | $3,770.00 | $3,348.27 |
| 40 | Catch basin, no. 3A (611E98180) | EACH | 7 | $2,681.49 | $4,000.00 | $3,889.38 | $3,700.00 | $2,669.60 |
| 41 | Catch basin, no. 3A, as per plan (611E98181) | EACH | 12 | $2,095.28 | $2,200.00 | $2,461.06 | $3,400.00 | $3,003.15 |
| 42 | Catch basin adjusted to grade (611E98630) | EACH | 7 | $1,414.12 | $1,500.00 | $549.54 | $1,705.00 | $859.43 |
| 43 | Manhole adjusted to grade (611E99654) | EACH | 4 | $1,414.11 | $1,500.00 | $549.54 | $1,705.00 | $738.30 |
| 44 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $671.30 | $500.00 | $474.76 | $762.00 | $840.69 |
| 45 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 2,162 | $190.50 | $184.00 | $190.50 | $190.50 | $274.57 |
| 46 | Aggregate base (304E20000) | CY | 2,470 | $53.26 | $64.00 | $84.73 | $86.75 | $57.61 |
| 47 | Non-tracking tack coat (407E20000) | GAL | 1,556 | $5.00 | $3.00 | $5.00 | $5.00 | $1.06 |
| 48 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 451 | $270.00 | $208.00 | $270.00 | $270.00 | $322.09 |
| 49 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 631 | $220.00 | $204.00 | $220.00 | $220.00 | $300.97 |
| 50 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 6,684 | $38.65 | $38.00 | $40.23 | $39.55 | $29.32 |
| 51 | Combination curb and gutter, type 3, as per plan (609E18001) | FT | 60 | $80.26 | $38.00 | $39.79 | $39.00 | $39.69 |
| 52 | Ground mounted support, no. 3 post (630E03100) | FT | 39.50 | $15.50 | $15.50 | $15.50 | $29.65 | $16.37 |
| 53 | Sign, flat sheet (630E80100) | SF | 18 | $16.00 | $16.00 | $16.00 | $36.90 | $16.90 |
| 54 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $20.00 | $20.00 | $20.00 | $17.05 | $21.12 |
| 55 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $25.00 | $25.00 | $25.00 | $22.70 | $26.40 |
| 56 | Center line (644E00300) | MI | 1.22 | $5,305.00 | $6,971.00 | $5,305.00 | $7,610.00 | $5,602.33 |
| 57 | Channelizing line, 12" (644E00404) | FT | 410 | $2.30 | $3.00 | $2.30 | $1.90 | $2.43 |
| 58 | Stop line (644E00500) | FT | 44 | $6.65 | $11.00 | $6.65 | $5.90 | $7.02 |
| 59 | Crosswalk line, 12" (644E00620) | FT | 203 | $3.30 | $5.50 | $3.30 | $5.45 | $3.48 |
| 60 | Lane arrow (644E01300) | EACH | 12 | $107.00 | $150.00 | $107.00 | $135.00 | $113.00 |
| 61 | Detour signing (614E12420) | LS | 1 | $3,995.00 | $3,995.00 | $3,995.00 | $4,059.00 | $4,286.13 |
| 62 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $925.00 | $925.00 | $925.00 | $951.30 | $1,004.58 |
| 63 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.05 | $13,925 | $18,900 | $13,925 | $13,840 | $14,705 |
| 64 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 0.10 | $13,585 | $9,450.00 | $13,585 | $8,870.00 | $14,346 |
| 65 | Water (616E10000) | MGAL | 1 | $140.21 | $10.00 | $14.64 | $1,600.00 | $2,765.75 |
| 66 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,026.00 | $8,500.00 | $12,284 | $29,500 | $11,089 |
| 67 | Maintaining traffic (614E11000) | LS | 1 | $8,289.39 | $25,000 | $3,706.20 | $8,100.00 | $20,821 |
| 68 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,392.16 | $8,000.00 | $29,150 | $10,500 | $30,784 |
| 69 | Mobilization (624E10000) | LS | 1 | $80,000 | $75,000 | $84,066 | $54,210 | $70,865 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 21, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.