By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2023 | 3 | 1 | 33% |
| 2024 | 4 | 1 | 25% |
| 2025 | 12 | 1 | 8% |
| 2026 | 11 | 1 | 9% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| HAM | 9 | 2 | 22% |
| WAR | 5 | 0 | 0% |
| HIG | 3 | 0 | 0% |
| CLE | 3 | 0 | 0% |
| CLI | 3 | 1 | 33% |
| BUT | 2 | 0 | 0% |
| BRO | 1 | 1 | 100% |
| MOT | 1 | 0 | 0% |
| GRE | 1 | 0 | 0% |
| District 8 | 1 | 0 | 0% |
| ADA | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 30 | 30 (100%) | $1.00 | $1.00 |
| Water | 659E35000 | MGAL | 30 | 17 (57%) | $1.00 | $1.00 |
| Seeding and mulching | 659E10000 | SY | 26 | 11 (42%) | $2.27 | $2.60 |
| Repair seeding and mulching | 659E14000 | SY | 20 | 9 (45%) | $2.02 | $1.25 |
| Lime | 659E31000 | ACRE | 27 | 8 (30%) | $200.00 | $150.00 |
| Sealing of concrete surfaces (epoxy-urethane) | 512E10100 | SY | 15 | 8 (53%) | $40.00 | $34.00 |
| Subgrade compaction | 204E10000 | SY | 19 | 7 (37%) | $3.30 | $3.00 |
| Commercial fertilizer | 659E20000 | TON | 30 | 6 (20%) | $1,500.00 | $850.00 |
| RPM | 621E00100 | EACH | 11 | 6 (55%) | $200.00 | $52.92 |
| Removal of ground mounted sign and disposal | 630E84900 | EACH | 9 | 6 (67%) | $16.56 | $20.00 |
| Embankment | 203E20000 | CY | 25 | 5 (20%) | $27.00 | $25.00 |
| Pavement removed | 202E23000 | SY | 17 | 5 (29%) | $22.50 | $17.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Sunesis Construction Co | 21 | 8 of 21 |
| Complete General Construction Company | 14 | 5 of 14 |
| John R Jurgensen Company | 13 | 2 of 13 |
| Eagle Bridge Co | 9 | 5 of 9 |
| Prus Construction Company | 9 | 4 of 9 |
| Axis Civil Construction LLC | 8 | 5 of 8 |
| Double Z Construction Company | 7 | 6 of 7 |
| Alan Stone Co Inc | 6 | 3 of 6 |
| Fillmore Construction | 5 | 4 of 5 |
| BCC Ohio Inc | 4 | 4 of 4 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260524 | WAR | WAR-IR 71 Rest Areas TP (PARKING AREAS) | 4 of 7 | $15,358,367 | +13% |
| 29 OCT 2026 | 260454 | ADA | ADA-SR 247-14.51/15.56 (BRIDGE REPLACEMENT (2 BRIDGES)) | 4 of 5 | $5,286,695 | +8.0% |
| 01 OCT 2026 | 264025 | CLI | CLI-SR 72-02.18 (CULVERT REPLACEMENT) | 1 of 5 | $296,299 | Low, 13% under the second |
| 27 AUG 2026 | 260379 | BUT | BUT-SR 129-09.09/09.20 (BRIDGE REPAIR) | 4 of 5 | $798,401 | +26% |
| 30 JUL 2026 | 260349 | HAM | HAM-Inverts FY2027 (CULVERT REPLACEMENT) | 3 of 5 | $2,082,813 | +10% |
| 21 MAY 2026 | 268010 | District 8 | D08-Davids Drive Reconstruction (MINOR RECONSTRUCTION) | 4 of 5 | $2,235,528 | +9.0% |
| 07 MAY 2026 | 260238 | HAM | HAM-Columbia Connector (BIKEWAYS) | 2 of 3 | $2,172,181 | +8.0% |
| 23 APR 2026 | 260225 | WAR | WAR-Central Greenway SUP Seg D (BIKEWAYS) | 3 of 5 | $787,976 | +13% |
| 26 MAR 2026 | 260144 | CLE | CLE-US 50-02.25 (BRIDGE REPAIR) | 4 of 5 | $755,619 | +15% |
| 12 MAR 2026 | 260122 | HAM | HAM-CR 299-05.78 Loveland Madeira (SIDEWALK) | 2 of 5 | $1,871,213 | +4.0% |
| 29 JAN 2026 | 260049 | CLE | CLE-SR 132-12.64 (BRIDGE REPAIR) | 5 of 5 | $631,523 | +11% |
| 13 NOV 2025 | 250526 | HIG | HIG-SR 73-00.26 (BRIDGE REPLACEMENT (1 BRIDGE)) | 7 of 8 | $2,336,827 | +34% |
| 11 SEP 2025 | 250412 | HIG | HIG-US 62-17.10 (BRIDGE REPAIR) | 3 of 3 | $323,890 | +46% |
| 28 AUG 2025 | 250376 | CLI | CLI-SR 134-02.25 (BRIDGE REPAIR) | 4 of 4 | $2,077,664 | +30% |
| 17 JUL 2025 | 250342 | CLI | CLI-SR 28-16.91 (BRIDGE REPAIR) | 2 of 4 | $595,954 | +29% |
| 26 JUN 2025 | 250319 | HAM | HAM-IR 74-11.25 (MISCELLANEOUS) | 2 of 4 | $440,069 | +3.0% |
| 22 MAY 2025 | 250277 | HAM | HAM-SR 264-10.42 (RELOCATION) | 1 of 5 | $2,212,186 | Low, 4.0% under the second |
| 10 APR 2025 | 250189 | BUT | BUT-SR 126-02.92 (SLIDE REPAIR) | 2 of 5 | $5,397,265 | +5.0% |
| 10 APR 2025 | 254013 | GRE | GRE-IR 675-09.60, GRE-US 35-18.46 (CULVERT REPLACEMENT) | 3 of 5 | $1,296,330 | +24% |
| 27 MAR 2025 | 250182 | HAM | HAM-IR 71-08.24 Ramp T (MISCELLANEOUS) | 6 of 6 | $841,288 | +66% |
| 27 FEB 2025 | 250136 | WAR | WAR-US 42-20.23 (INTERSECTION) | 2 of 5 | $1,303,469 | +1.0% |
| 13 FEB 2025 | 250097 | MOT | MOT-Sycamore Creek Bridge Replac (BRIDGE REPLACEMENT (1 BRIDGE)) | 4 of 7 | $558,540 | +18% |
| 16 JAN 2025 | 240582 | HAM | HAM-US 52-36.85 (SLIDE REPAIR) | 2 of 9 | $1,956,795 | +1.0% |
| 05 DEC 2024 | 240563 | WAR | WAR-SR 350-08.73 (BRIDGE REPLACEMENT (1 BRIDGE)) | 2 of 7 | $4,122,504 | +2.0% |
| 14 NOV 2024 | 240525 | HAM | HAM-Culverts FY25 (CULVERT REPLACEMENT) | 2 of 5 | $491,597 | +11% |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.