ODOT contract 264025 bid tabulation
CLI-SR 72-02.18 (CULVERT REPLACEMENT). Let by Ohio DOT on October 1, 2026, CLI. 5 bids received; low bid $296,299 by KT Holden Construction LLC, -10% against the engineer's estimate of $330,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 35
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | KT Holden Construction LLC | $296,299 | Low | -10% |
| 2 | Rack & Ballauer Excavating Co Inc | $333,725 | +13% | +1.0% |
| 3 | Axis Civil Construction LLC | $356,974 | +20% | +8.0% |
| 4 | Madex Construction Co | $399,772 | +35% | +21% |
| 5 | Alan Stone Co Inc | $457,583 | +54% | +39% |
Engineer's estimate: $330,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. KT Holden Construction LLC | 2. Rack & Ballauer Excavating Co Inc | 3. Axis Civil Construction LLC | 4. Madex Construction Co | 5. Alan Stone Co Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 79 | $24.77 | $37.00 | $22.00 | $56.07 | $20.00 |
| 2 | Pipe removed, over 24" diameter (202E35200) | FT | 100 | $71.94 | $60.00 | $49.00 | $69.77 | $40.00 |
| 3 | Excavation (203E10000) | CY | 339 | $30.58 | $32.00 | $35.00 | $30.62 | $25.00 |
| 4 | Embankment (203E20000) | CY | 763 | $26.70 | $32.00 | $40.00 | $37.05 | $35.00 |
| 5 | Subgrade compaction (204E10000) | SY | 87 | $6.02 | $7.00 | $3.50 | $2.32 | $35.00 |
| 6 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $4,378.87 | $500.00 | $3,500.00 | $11,000 | $100.00 |
| 7 | Guardrail, type MGS (606E15050) | FT | 525 | $22.00 | $22.00 | $22.00 | $30.11 | $30.00 |
| 8 | Anchor assembly, MGS type E (606E26150) | EACH | 4 | $2,550.00 | $2,550.00 | $2,550.00 | $3,473.68 | $2,900.00 |
| 9 | Right-of-way monument, type B (623E40520) | EACH | 4 | $500.00 | $250.00 | $400.00 | $1,157.89 | $320.00 |
| 10 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $5,910.00 | $3,500.00 | $4,400.00 | $5,789.47 | $12,000 |
| 11 | Rock channel protection, type B with filter (601E32100) | CY | 14.90 | $251.82 | $225.00 | $150.00 | $289.47 | $360.00 |
| 12 | Topsoil (659E00300) | CY | 462 | $55.56 | $70.00 | $55.00 | $35.42 | $25.00 |
| 13 | Seeding and mulching (659E10000) | SY | 4,162 | $1.45 | $2.00 | $2.00 | $4.63 | $2.00 |
| 14 | Commercial fertilizer (659E20000) | TON | 0.56 | $1,500.00 | $1,100.00 | $820.00 | $315.79 | $1,900.00 |
| 15 | Lime (659E31000) | ACRE | 0.86 | $200.00 | $50.00 | $50.00 | $157.90 | $250.00 |
| 16 | Water (659E35000) | MGAL | 22.50 | $1.00 | $50.00 | $50.00 | $1.00 | $1.00 |
| 17 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | Concrete masonry (602E20000) | CY | 3.94 | $2,814.13 | $3,400.00 | $3,500.00 | $2,723.01 | $3,100.00 |
| 19 | 12" conduit, type B (611E04400) | FT | 200 | $8.96 | $144.00 | $45.00 | $7.79 | $30.00 |
| 20 | 15" conduit, type B (611E05900) | FT | 200 | $11.53 | $150.00 | $45.00 | $8.95 | $35.00 |
| 21 | 58" X 91" conduit, type A, 706.04 (611E53400) | FT | 68 | $1,059.55 | $1,090.00 | $1,850.00 | $1,287.17 | $2,900.00 |
| 23 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 29 | $960.00 | $455.00 | $500.00 | $1,123.16 | $680.00 |
| 24 | Aggregate base (304E20000) | CY | 15 | $145.10 | $175.00 | $220.00 | $115.79 | $180.00 |
| 25 | Tack coat (407E10000) | GAL | 23 | $5.00 | $4.50 | $7.00 | $5.79 | $8.00 |
| 27 | RPM (621E00100) | EACH | 2 | $470.94 | $702.00 | $702.00 | $1,736.84 | $870.00 |
| 28 | Raised pavement marker removed (621E54000) | EACH | 2 | $17.88 | $20.00 | $75.00 | $70.53 | $280.00 |
| 29 | Barrier reflector, type 2 BI-directional (626E00110) | EACH | 14 | $12.50 | $12.50 | $12.50 | $17.37 | $20.00 |
| 30 | Edge line, 6", type 1 (642E00104) | MI | 0.02 | $57,800 | $57,800 | $57,800 | $53,263 | $72,000 |
| 31 | Center line, type 1 (642E00300) | MI | 0.01 | $86,400 | $86,400 | $86,400 | $53,263 | $107,000 |
| 32 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $80.00 | $100.00 | $75.00 | $49.79 | $150.00 |
| 33 | Detour signing (614E12420) | LS | 1 | $8,663.30 | $8,000.00 | $12,000 | $14,579 | $9,400.00 |
| 34 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,925.97 | $3,000.00 | $4,500.00 | $19,307 | $5,000.00 |
| 35 | Maintaining traffic (614E11000) | LS | 1 | $1,500.00 | $3,000.00 | $7,500.00 | $15,789 | $3,200.00 |
| 36 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,375.00 | $6,000.00 | $7,500.00 | $16,737 | $2,800.00 |
| 37 | Mobilization (624E10000) | LS | 1 | $36,153 | $21,500 | $20,000 | $43,203 | $65,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.