Axis Civil Construction LLC: ODOT bid record
Axis Civil Construction LLC submitted 349 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 12 NOV 2026, and was the low bidder on 85 of them (24%). When it was not low, its total sat a median +17% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $60,082,019
- Latest bid
- 12 NOV 2026
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 50 | 8 | 16% |
| 2021 | 46 | 14 | 30% |
| 2022 | 41 | 11 | 27% |
| 2023 | 45 | 10 | 22% |
| 2024 | 60 | 19 | 32% |
| 2025 | 57 | 13 | 23% |
| 2026 | 50 | 10 | 20% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| LAW | 22 | 6 | 27% |
| SCI | 18 | 4 | 22% |
| ATH | 18 | 6 | 33% |
| MEG | 17 | 3 | 18% |
| CLE | 16 | 5 | 31% |
| JAC | 16 | 4 | 25% |
| PIK | 15 | 1 | 7% |
| CLI | 15 | 5 | 33% |
| GAL | 14 | 5 | 36% |
| ROS | 14 | 3 | 21% |
| BRO | 13 | 4 | 31% |
| HIG | 13 | 2 | 15% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 337 | 337 (100%) | $1.00 | $1.00 |
| Water | 659E35000 | MGAL | 320 | 277 (87%) | $1.00 | $1.00 |
| Lime | 659E31000 | ACRE | 314 | 174 (55%) | $150.00 | $150.00 |
| Commercial fertilizer | 659E20000 | TON | 315 | 98 (31%) | $1,250.00 | $850.00 |
| Seeding and mulching | 659E10000 | SY | 260 | 95 (37%) | $2.48 | $2.60 |
| Center line, type 1 | 642E00300 | MI | 153 | 78 (51%) | $11,250 | $5,500.00 |
| Edge line, 6", type 1 | 642E00104 | MI | 135 | 75 (56%) | $7,550.00 | $3,200.00 |
| Subgrade compaction | 204E10000 | SY | 249 | 68 (27%) | $3.00 | $3.00 |
| Guardrail, type MGS | 606E15050 | FT | 109 | 59 (54%) | $25.00 | $22.73 |
| Law enforcement officer with patrol car for assistance | 614E11110 | HR | 138 | 57 (41%) | $75.00 | $80.00 |
| Embankment | 203E20000 | CY | 263 | 56 (21%) | $30.00 | $25.00 |
| Ground mounted support, no. 3 post | 630E03100 | FT | 98 | 51 (52%) | $15.50 | $15.20 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Alan Stone Co Inc | 123 | 51 of 123 |
| D G M Inc | 95 | 54 of 95 |
| Eclipse Co LLC | 95 | 19 of 95 |
| R C Construction Company and Son Inc | 93 | 34 of 93 |
| Complete General Construction Company | 93 | 22 of 93 |
| Shelly & Sands Inc | 91 | 50 of 91 |
| Sunesis Construction Co | 67 | 22 of 67 |
| Allard Excavation LLC | 54 | 33 of 54 |
| Parker Corporation | 49 | 33 of 49 |
| Fillmore Construction | 45 | 27 of 45 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260493 | CLI | CLI-US 68-09.42 (CULVERT REPLACEMENT) | 4 of 5 | $291,283 | +22% |
| 12 NOV 2026 | 260509 | SCI | SCI-US 52-13.33 (CULVERT REPLACEMENT) | 1 of 5 | $723,107 | Low, 11% under the second |
| 29 OCT 2026 | 264027 | CLI | CLI-/GRE Inverts FY27 (CULVERT REPLACEMENT) | 3 of 3 | $1,013,487 | +28% |
| 15 OCT 2026 | 260481 | District 9 | D09-BH-FY2027 (BRIDGE REPAIR) | 1 of 1 | $439,985 | Low |
| 01 OCT 2026 | 260427 | LAW | LAW-SR 93-11.21 Flooding (MINOR RECONSTRUCTION) | 3 of 4 | $3,028,712 | +11% |
| 01 OCT 2026 | 260438 | VIN | VIN-SR 278-02.79 (CULVERT REPLACEMENT) | 5 of 7 | $740,490 | +15% |
| 01 OCT 2026 | 264025 | CLI | CLI-SR 72-02.18 (CULVERT REPLACEMENT) | 3 of 5 | $356,974 | +20% |
| 27 AUG 2026 | 260381 | CLE | CLE-SR 125-14.08 (SIDEWALK) | 1 of 5 | $972,510 | Low, 1.0% under the second |
| 27 AUG 2026 | 260386 | LAW | LAW-VAR South Point-Sidewalk (SIDEWALK) | 1 of 3 | $1,158,611 | Low, 2.0% under the second |
| 27 AUG 2026 | 260390 | SCI | SCI-SR 348-17.51 (BRIDGE REPAIR) | 2 of 3 | $653,852 | -23% |
| 27 AUG 2026 | 264021 | FRA | FRA-US 62-04.90 (CULVERT REPLACEMENT) | 1 of 2 | $541,249 | Low, 8.0% under the second |
| 13 AUG 2026 | 260361 | GAL | GAL-SR 218-04.81/08.56 (CULVERT REPLACEMENT) | 1 of 4 | $894,456 | Low, 2.0% under the second |
| 13 AUG 2026 | 260367 | PIK | PIK-SR 32-06.60 (BRIDGE REPAIR) | 4 of 6 | $833,086 | +61% |
| 13 AUG 2026 | 260368 | PIK | PIK-SR 32-18.40 (INTERSECTION) | 4 of 9 | $3,128,083 | +10% |
| 16 JUL 2026 | 264018 | MRG | MRG-SR 669-02.09 (CULVERT REPLACEMENT) | 4 of 4 | $436,618 | +18% |
| 25 JUN 2026 | 260324 | PER | PER-SR 345-06.48 (BRIDGE REPAIR) | 4 of 6 | $945,964 | +9.0% |
| 11 JUN 2026 | 260291 | SCI | SCI-SR 335-01.72 (CULVERT REPLACEMENT) | 2 of 2 | $1,365,189 | +2.0% |
| 21 MAY 2026 | 260268 | JAC | JAC-US 35-18.16 (Safety) (PART 1 AND PART 2) (INTERSECTION) | 2 of 4 | $2,481,157 | +9.0% |
| 21 MAY 2026 | 260270 | LAW | LAW-SR 650-07.16 (BRIDGE REPLACEMENT (1 BRIDGE)) | 2 of 3 | $2,994,768 | +4.0% |
| 21 MAY 2026 | 260280 | FRA | FRA-US 33-08.75 Culvert Repl. (CULVERT REPLACEMENT) | 2 of 2 | $2,472,520 | +11% |
| 21 MAY 2026 | 264013 | District 5 | D05-CUL FY2026 (A) (CULVERT REPLACEMENT) | 2 of 2 | $1,877,320 | +12% |
| 21 MAY 2026 | 264014 | WAS | WAS-SR 60-15.43 (CULVERT REPLACEMENT) | 2 of 4 | $585,358 | +1.0% |
| 07 MAY 2026 | 260236 | FRA | FRA-SR 317/Williams Rd (INTERSECTION) | 2 of 3 | $353,191 | +4.0% |
| 07 MAY 2026 | 260244 | MUS | MUS-SR 555-02.09 (SLIDE REPAIR) | 4 of 7 | $265,159 | +19% |
| 07 MAY 2026 | 260247 | ROS | ROS-SR 207-08.31 (CULVERT REPLACEMENT) | 1 of 4 | $343,332 | Low, 21% under the second |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.