ODOT contract 260367 bid tabulation
PIK-SR 32-06.60 (BRIDGE REPAIR). Let by Ohio DOT on August 13, 2026, PIK. 6 bids received; low bid $516,978 by Miller Bros Const Inc, -23% against the engineer's estimate of $670,000.
- Owner
- Ohio DOT
- Letting
- 13 AUG 2026
- Pay items
- 19
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Miller Bros Const Inc | $516,978 | Low | -23% |
| 2 | D G M Inc | $642,292 | +24% | -4.0% |
| 3 | Sunesis Construction Co | $722,179 | +40% | +8.0% |
| 4 | Axis Civil Construction LLC | $833,086 | +61% | +24% |
| 5 | Double Z Construction Company | $836,200 | +62% | +25% |
| 6 | Complete General Construction Company | $1,198,723 | +132% | +79% |
Engineer's estimate: $670,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Miller Bros Const Inc | 2. D G M Inc | 3. Sunesis Construction Co | 4. Axis Civil Construction LLC | 5. Double Z Construction Company | 6. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $48,811 | $15,000 | $3,206.00 | $10,000 | $30,000 | $70,000 |
| 2 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $1.00 | $73,000 | $26,814 | $35,000 | $85,000 | $35,000 |
| 3 | Special - pile encasement (507E71200) | FT | 299 | $155.46 | $150.00 | $210.00 | $320.00 | $270.00 | $375.00 |
| 4 | Riprap, with grout (601E12000) | SY | 60 | $244.95 | $250.00 | $414.00 | $365.00 | $235.00 | $1,575.00 |
| 5 | Slope protection, misc.: armortec A-jacks (601E21100) | SY | 624 | $235.83 | $280.00 | $331.00 | $460.00 | $360.00 | $900.00 |
| 6 | Dumped rock fill, type A (601E25000) | CY | 200 | $127.43 | $125.00 | $128.00 | $165.00 | $110.00 | $125.00 |
| 7 | Rock channel protection, type A with geotextile fabric (601E32004) | CY | 489 | $104.01 | $115.00 | $169.00 | $130.00 | $155.00 | $100.00 |
| 8 | Rock channel protection, type A with geotextile fabric, as per plan (601E32005) | CY | 695 | $100.27 | $140.00 | $189.00 | $140.00 | $210.00 | $110.00 |
| 9 | Seeding and mulching (659E10000) | SY | 1,936 | $1.30 | $3.00 | $5.00 | $1.80 | $6.00 | $1.80 |
| 10 | Commercial fertilizer (659E20000) | TON | 0.27 | $850.00 | $1,500.00 | $700.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 11 | Lime (659E31000) | ACRE | 0.40 | $0.10 | $300.00 | $50.00 | $150.00 | $150.00 | $150.00 |
| 12 | Water (659E35000) | MGAL | 11 | $0.10 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 13 | Erosion control (832E30000) | EACH | 7,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 14 | Water (616E10000) | MGAL | 3 | $94.78 | $1.00 | $128.00 | $1.00 | $40.00 | $85.00 |
| 15 | Steel sheet piling left in place (18.1 CU in/FT) (504E11100) | SF | 1,380 | $43.18 | $43.00 | $57.00 | $90.00 | $43.00 | $50.00 |
| 16 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,520.77 | $22,000 | $4,720.00 | $7,500.00 | $6,000.00 | $8,000.00 |
| 17 | Maintaining traffic (614E11000) | LS | 1 | $11,104 | $20,000 | $18,961 | $10,000 | $24,000 | $15,000 |
| 18 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,200.00 | $6,000.00 | $8,600.00 | $8,500.00 | $9,000.00 | $12,000 |
| 19 | Mobilization (624E10000) | LS | 1 | $25,849 | $20,000 | $29,664 | $28,000 | $40,000 | $59,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 13, 2026. Compiled by Mirage Metrics.