Sunesis Construction Co: ODOT bid record
Sunesis Construction Co submitted 311 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 12 NOV 2026, and was the low bidder on 38 of them (12%). When it was not low, its total sat a median +19% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $126,181,715
- Latest bid
- 12 NOV 2026
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 56 | 8 | 14% |
| 2021 | 50 | 3 | 6% |
| 2022 | 37 | 2 | 5% |
| 2023 | 44 | 4 | 9% |
| 2024 | 38 | 6 | 16% |
| 2025 | 41 | 5 | 12% |
| 2026 | 45 | 10 | 22% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| HAM | 59 | 20 | 34% |
| MOT | 26 | 1 | 4% |
| CLE | 24 | 1 | 4% |
| BUT | 23 | 1 | 4% |
| BRO | 23 | 1 | 4% |
| HIG | 15 | 1 | 7% |
| PIK | 15 | 0 | 0% |
| WAR | 13 | 1 | 8% |
| GRE | 12 | 1 | 8% |
| ROS | 12 | 1 | 8% |
| CLI | 11 | 2 | 18% |
| District 8 | 9 | 2 | 22% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 296 | 296 (100%) | $1.00 | $1.00 |
| Water | 659E35000 | MGAL | 279 | 110 (39%) | $1.39 | $1.00 |
| Commercial fertilizer | 659E20000 | TON | 277 | 100 (36%) | $900.00 | $850.00 |
| Water | 616E10000 | MGAL | 166 | 100 (60%) | $14.20 | $20.00 |
| Ground mounted support, no. 3 post | 630E03100 | FT | 141 | 80 (57%) | $15.50 | $15.20 |
| Embankment | 203E20000 | CY | 241 | 77 (32%) | $19.89 | $25.00 |
| 1" preformed expansion joint filler | 516E13600 | SF | 125 | 72 (58%) | $5.02 | $10.00 |
| Sign, flat sheet | 630E80100 | SF | 151 | 70 (46%) | $22.00 | $24.00 |
| Law enforcement officer with patrol car for assistance | 614E11110 | HR | 183 | 69 (38%) | $75.00 | $80.00 |
| Lime | 659E31000 | ACRE | 264 | 68 (26%) | $200.00 | $150.00 |
| Repair seeding and mulching | 659E14000 | SY | 192 | 66 (34%) | $1.56 | $1.25 |
| RPM | 621E00100 | EACH | 145 | 64 (44%) | $229.00 | $52.92 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Complete General Construction Company | 169 | 89 of 169 |
| John R Jurgensen Company | 118 | 52 of 118 |
| Eagle Bridge Co | 84 | 64 of 84 |
| Axis Civil Construction LLC | 67 | 45 of 67 |
| Shelly & Sands Inc | 60 | 47 of 60 |
| Prus Construction Company | 60 | 26 of 60 |
| Alan Stone Co Inc | 53 | 39 of 53 |
| Barrett Paving Materials Inc | 51 | 33 of 51 |
| Eclipse Co LLC | 46 | 22 of 46 |
| D G M Inc | 46 | 35 of 46 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260492 | CLA | CLA-LMT Culvert Replacement (CULVERT REPLACEMENT) | 2 of 3 | $214,872 | +9.0% |
| 12 NOV 2026 | 260493 | CLI | CLI-US 68-09.42 (CULVERT REPLACEMENT) | 1 of 5 | $239,218 | Low, 2.0% under the second |
| 12 NOV 2026 | 260521 | GUE | GUE-IR 70 EB Rest Area TP (PARKING AREAS) | 3 of 8 | $7,599,321 | +3.0% |
| 12 NOV 2026 | 260524 | WAR | WAR-IR 71 Rest Areas TP (PARKING AREAS) | 5 of 7 | $15,485,841 | +14% |
| 29 OCT 2026 | 260461 | HAM | HAM-IR 275-11.40 (SLIDE REPAIR) | 1 of 5 | $2,766,883 | Low, 5.0% under the second |
| 29 OCT 2026 | 260469 | MOT | MOT-Johnson Station Rd Bridge (BRIDGE REPLACEMENT (1 BRIDGE)) | 4 of 6 | $1,612,906 | +23% |
| 29 OCT 2026 | 260471 | MOT | MOT-SR 835-02.57 (BRIDGE REPLACEMENT (1 BRIDGE)) | 5 of 5 | $6,647,696 | +19% |
| 01 OCT 2026 | 260418 | ADA | ADA-SR 41-31.36 (SLIDE REPAIR) | 3 of 5 | $677,788 | +21% |
| 01 OCT 2026 | 260425 | HAM | HAM-IR 71-02.26/02.94/03.44 (BRIDGE REPAIR) | 1 of 5 | $5,667,659 | Low, 0.0% under the second |
| 01 OCT 2026 | 260430 | MOT | MOT-GMR Trail IMP CR22B (BIKEWAYS) | 8 of 8 | $1,950,697 | +19% |
| 01 OCT 2026 | 260438 | VIN | VIN-SR 278-02.79 (CULVERT REPLACEMENT) | 3 of 7 | $665,710 | +3.0% |
| 17 SEP 2026 | 260408 | JAC | JAC-SR 327-14.98 (SLIDE REPAIR) | 5 of 7 | $916,023 | +36% |
| 27 AUG 2026 | 260381 | CLE | CLE-SR 125-14.08 (SIDEWALK) | 3 of 5 | $1,073,410 | +10% |
| 13 AUG 2026 | 260362 | HAS | HAS-SR 646-01.94 (SLIDE REPAIR) | 5 of 6 | $1,314,067 | +68% |
| 13 AUG 2026 | 260363 | HAS | HAS-Bridge St Bridge Replacement (BRIDGE REPLACEMENT (1 BRIDGE)) | 4 of 5 | $2,394,393 | +15% |
| 13 AUG 2026 | 260367 | PIK | PIK-SR 32-06.60 (BRIDGE REPAIR) | 3 of 6 | $722,179 | +40% |
| 13 AUG 2026 | 260368 | PIK | PIK-SR 32-18.40 (INTERSECTION) | 7 of 9 | $3,329,693 | +17% |
| 30 JUL 2026 | 260349 | HAM | HAM-Inverts FY2027 (CULVERT REPLACEMENT) | 4 of 5 | $2,825,074 | +50% |
| 28 MAY 2026 | 260271 | MAD | MAD-US 42-12.35 (MAJOR WIDENING) | 3 of 4 | $12,834,677 | +4.0% |
| 21 MAY 2026 | 268010 | District 8 | D08-Davids Drive Reconstruction (MINOR RECONSTRUCTION) | 3 of 5 | $2,223,046 | +8.0% |
| 07 MAY 2026 | 260212 | PRE | PRE-SR 726-02.74 (BRIDGE REPLACEMENT (1 BRIDGE)) | 3 of 5 | $1,627,958 | +34% |
| 07 MAY 2026 | 260228 | CAR | CAR-Grant St Bridge Replacement (BRIDGE REPLACEMENT (1 BRIDGE)) | 1 of 2 | $1,628,262 | Low, 12% under the second |
| 07 MAY 2026 | 260238 | HAM | HAM-Columbia Connector (BIKEWAYS) | 1 of 3 | $2,009,547 | Low, 8.0% under the second |
| 07 MAY 2026 | 260243 | MIA | MIA-CR 15-05.57 BH (BRIDGE REPAIR) | 4 of 4 | $3,779,973 | +48% |
| 07 MAY 2026 | 260247 | ROS | ROS-SR 207-08.31 (CULVERT REPLACEMENT) | 4 of 4 | $456,806 | +33% |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.