ODOT contract 260212 bid tabulation
PRE-SR 726-02.74 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on May 7, 2026, PRE. 5 bids received; low bid $1,215,000 by Brumbaugh Construction Inc, -24% against the engineer's estimate of $1,600,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 74
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Brumbaugh Construction Inc | $1,215,000 | Low | -24% |
| 2 | Eagle Bridge Co | $1,258,050 | +4.0% | -21% |
| 3 | Sunesis Construction Co | $1,627,958 | +34% | +2.0% |
| 4 | Complete General Construction Company | $1,769,324 | +46% | +11% |
| 5 | Beaty Construction Inc | $1,820,789 | +50% | +14% |
Engineer's estimate: $1,600,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Brumbaugh Construction Inc | 2. Eagle Bridge Co | 3. Sunesis Construction Co | 4. Complete General Construction Company | 5. Beaty Construction Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $6,000.00 | $6,500.00 | $2,906.28 | $5,000.00 | $40,000 |
| 2 | Approach slab removed (202E22900) | SY | 93 | $70.00 | $50.00 | $38.52 | $125.00 | $52.00 |
| 3 | Pavement removed (202E23000) | SY | 309 | $12.00 | $20.00 | $15.28 | $19.00 | $35.00 |
| 4 | Guardrail removed (202E38000) | FT | 200 | $8.00 | $4.00 | $12.00 | $2.40 | $14.76 |
| 5 | Anchor assembly removed, type A, as per plan (202E42001) | EACH | 4 | $500.00 | $400.00 | $433.83 | $325.00 | $596.90 |
| 6 | Bridge terminal assembly removed (202E47000) | EACH | 4 | $500.00 | $250.00 | $125.00 | $80.00 | $298.45 |
| 7 | Excavation (203E10000) | CY | 237 | $22.00 | $30.00 | $16.93 | $29.00 | $25.00 |
| 8 | Embankment (203E20000) | CY | 215 | $22.00 | $30.00 | $19.17 | $49.00 | $30.00 |
| 9 | Guardrail, type MGS (606E15050) | FT | 350 | $27.00 | $22.50 | $27.50 | $21.20 | $22.50 |
| 10 | Anchor assembly, MGS type E (MASH 2016 soft stop) (606E26150) | EACH | 3 | $2,800.00 | $2,650.00 | $2,650.00 | $2,580.00 | $2,650.00 |
| 11 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,500.00 | $1,250.00 | $1,350.00 | $1,360.00 | $1,250.00 |
| 12 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $2,800.00 | $2,650.00 | $2,550.00 | $2,520.00 | $2,650.00 |
| 13 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $5,000.00 | $10,000 | $3,259.84 | $12,000 | $6,000.00 |
| 14 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 294 | $90.00 | $100.00 | $126.22 | $95.00 | $250.00 |
| 15 | Seeding and mulching (659E10000) | SY | 806 | $5.00 | $6.00 | $3.07 | $4.40 | $3.90 |
| 16 | Repair seeding and mulching (659E14000) | SY | 40 | $2.00 | $3.00 | $0.28 | $2.00 | $3.90 |
| 17 | Commercial fertilizer (659E20000) | TON | 0.11 | $1,000.00 | $1,500.00 | $345.55 | $800.00 | $1,000.00 |
| 18 | Lime (659E31000) | ACRE | 0.17 | $2.00 | $1.00 | $51.88 | $2.00 | $100.00 |
| 19 | Water (659E35000) | MGAL | 4.40 | $5.00 | $10.00 | $1.39 | $0.50 | $1.00 |
| 20 | Erosion control (832E30000) | EACH | 8,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | Subgrade compaction (204E10000) | SY | 332 | $1.50 | $10.00 | $4.54 | $9.00 | $3.00 |
| 22 | Proof rolling (204E45000) | HR | 0.17 | $1,000.00 | $100.00 | $382.24 | $500.00 | $2,200.00 |
| 23 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 36 | $410.00 | $450.00 | $550.00 | $790.00 | $790.00 |
| 24 | Aggregate base (304E20000) | CY | 54 | $80.00 | $150.00 | $97.65 | $113.50 | $120.00 |
| 25 | Non-tracking tack coat (407E20000) | GAL | 39 | $20.00 | $2.45 | $6.00 | $5.00 | $5.00 |
| 26 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 8 | $450.00 | $750.00 | $1,800.00 | $1,500.00 | $1,500.00 |
| 27 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 11 | $430.00 | $650.00 | $775.00 | $1,150.00 | $1,150.00 |
| 29 | RPM (621E00100) | EACH | 2 | $1,000.00 | $1,505.85 | $883.00 | $883.00 | $883.00 |
| 30 | Raised pavement marker removed (621E54000) | EACH | 2 | $50.00 | $15.00 | $121.08 | $60.00 | $60.00 |
| 31 | Barrier reflector, type 2 (BI-directional) (626E00110) | EACH | 13 | $15.00 | $12.50 | $15.00 | $12.00 | $20.00 |
| 32 | Edge line, 6" (644E00104) | MI | 0.03 | $47,000 | $46,100 | $46,029 | $35,100 | $46,029 |
| 33 | Center line (644E00300) | MI | 0.02 | $94,000 | $92,200 | $92,058 | $30,688 | $92,058 |
| 34 | Edge line, 6" (646E10010) | MI | 0.05 | $29,000 | $40,000 | $28,068 | $22,949 | $28,068 |
| 35 | Center line (646E10200) | MI | 0.07 | $40,000 | $40,000 | $39,300 | $30,155 | $39,300 |
| 36 | Detour signing (614E12420) | LS | 1 | $8,000.00 | $10,000 | $6,960.00 | $7,650.00 | $6,960.00 |
| 37 | Special - asbestos abatement (work involving asbes (690E71000) | LS | 1 | $500.00 | $225.00 | $442.29 | $2,000.00 | $1.00 |
| 38 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $60,000 | $55,000 | $51,506 | $120,000 | $158,000 |
| 39 | Bridge railing removed (202E38500) | FT | 228 | $12.00 | $20.00 | $7.59 | $7.00 | $20.00 |
| 40 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $10,000 | $1.00 | $3,500.00 | $75,000 | $25,000 |
| 41 | Unclassified excavation (503E21300) | LS | 1 | $6,000.00 | $30,000 | $27,889 | $45,000 | $25,000 |
| 42 | Pile driving equipment mobilization (505E11100) | LS | 1 | $15,000 | $45,000 | $3,748.66 | $17,000 | $25,000 |
| 43 | Steel piles HP12X53, furnished, as per plan (507E00201) | FT | 58 | $350.00 | $200.00 | $207.28 | $375.00 | $450.00 |
| 44 | 12" cast-in-place reinforced concrete piles, driven (507E00500) | FT | 540 | $5.00 | $4.00 | $39.88 | $45.00 | $65.00 |
| 45 | 12" cast-in-place reinforced concrete piles, furnished (507E00550) | FT | 630 | $80.00 | $55.00 | $48.83 | $60.00 | $45.00 |
| 46 | 16" cast-in-place reinforced concrete piles, driven (507E00700) | FT | 350 | $6.00 | $5.00 | $46.72 | $75.00 | $125.00 |
| 47 | 16" cast-in-place reinforced concrete piles, furnished, as per plan (507E00751) | FT | 400 | $155.00 | $125.00 | $97.36 | $110.00 | $80.00 |
| 48 | Steel points or shoes (507E93300) | EACH | 28 | $500.00 | $250.00 | $568.16 | $450.00 | $530.00 |
| 49 | Galvanized steel reinforcement (509E26000) | LB | 90,717 | $1.60 | $1.80 | $3.59 | $1.75 | $2.25 |
| 50 | Class QC2 concrete with QC/QA, superstructure, as per plan (511E32213) | CY | 221 | $1,200.00 | $1,000.00 | $1,745.36 | $1,350.00 | $1,550.00 |
| 51 | Class QC1 concrete with QC/QA, pier above footings (511E41012) | CY | 16 | $1,800.00 | $1,500.00 | $2,920.79 | $3,000.00 | $3,200.00 |
| 52 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 75 | $850.00 | $750.00 | $1,042.30 | $1,350.00 | $1,200.00 |
| 53 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 146 | $25.00 | $36.25 | $36.25 | $36.25 | $36.50 |
| 54 | Type 2 waterproofing (512E33000) | SY | 15 | $100.00 | $30.00 | $38.57 | $155.00 | $28.00 |
| 55 | Type E waterproofing (512E44450) | SY | 14 | $100.00 | $20.00 | $81.34 | $125.00 | $40.00 |
| 56 | Preformed elastomeric compression joint seal (516E10000) | FT | 65 | $45.00 | $24.00 | $29.29 | $125.00 | $65.00 |
| 57 | 1/2" preformed expansion joint filler (516E13200) | SF | 43 | $4.00 | $7.00 | $7.97 | $25.00 | $5.50 |
| 58 | 1" preformed expansion joint filler (516E13600) | SF | 85 | $6.00 | $8.00 | $5.69 | $15.00 | $5.00 |
| 59 | Integral abutment expansion joint seal (516E14014) | FT | 93 | $40.00 | $40.00 | $48.00 | $80.00 | $35.00 |
| 60 | Railing (three steel tube bridge railing) (517E70100) | FT | 246 | $520.00 | $470.00 | $525.00 | $500.00 | $470.00 |
| 61 | Porous backfill with geotextile fabric (518E21200) | CY | 50 | $70.00 | $125.00 | $111.73 | $125.00 | $380.00 |
| 62 | Special - steel drip strip (518E22300) | FT | 288 | $13.00 | $15.00 | $16.00 | $16.00 | $20.00 |
| 63 | 6" perforated corrugated plastic pipe (518E40000) | FT | 122 | $11.00 | $14.00 | $4.23 | $14.00 | $5.00 |
| 64 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 80 | $11.00 | $18.00 | $23.58 | $19.00 | $15.00 |
| 65 | Dynamic load testing (523E20000) | EACH | 4 | $3,000.00 | $2,250.00 | $3,750.22 | $5,500.00 | $10,000 |
| 66 | Reinforced concrete approach slabs with QC/QA (T=1 (526E10010) | SY | 108 | $325.00 | $275.00 | $490.39 | $395.00 | $525.00 |
| 67 | Type A installation, as per plan (526E90011) | FT | 65 | $240.00 | $250.00 | $205.03 | $350.00 | $235.00 |
| 68 | Special - structures, misc.: temporary constructio (530E00200) | LS | 1 | $10,000 | $55,000 | $17,124 | $110,000 | $25,000 |
| 69 | Structure grounding system (625E33000) | EACH | 1 | $11,000 | $9,000.00 | $13,025 | $15,000 | $19,500 |
| 70 | Polymer modified asphalt expansion joint system (846E00110) | CF | 27 | $550.00 | $740.00 | $738.47 | $750.00 | $738.47 |
| 71 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $20,000 | $9,284.16 | $12,000 | $8,558.00 |
| 72 | Maintaining traffic (614E11000) | LS | 1 | $1,500.00 | $1,500.00 | $4,101.52 | $4,764.00 | $15,000 |
| 73 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $10,000 | $10,000 | $20,250 | $20,000 | $22,750 |
| 74 | Mobilization (624E10000) | LS | 1 | $26,869 | $60,000 | $66,919 | $88,500 | $40,000 |
| 100 | Restrike (523E20500) | EACH | 4 | $1,400.00 | $750.00 | $2,298.80 | $4,000.00 | $6,300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.