ODOT contract 260228 bid tabulation
CAR-Grant St Bridge Replacement (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on May 7, 2026, CAR. 2 bids received; low bid $1,628,262 by Sunesis Construction Co, +2.4% against the engineer's estimate of $1,590,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 79
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sunesis Construction Co | $1,628,262 | Low | +2.0% |
| 2 | Beaver Excavating Company | $1,823,447 | +12% | +15% |
Engineer's estimate: $1,590,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunesis Construction Co | 2. Beaver Excavating Company |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,451.64 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 259 | $20.59 | $17.00 |
| 3 | Walk removed (202E30000) | SF | 435 | $2.89 | $3.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 47 | $32.76 | $35.00 |
| 5 | Guardrail removed (202E38000) | FT | 71 | $11.21 | $4.00 |
| 6 | Fence removed (202E75000) | FT | 99 | $8.54 | $4.00 |
| 7 | Excavation (203E10000) | CY | 41 | $37.58 | $45.00 |
| 8 | Embankment (203E20000) | CY | 27 | $49.89 | $45.00 |
| 9 | Subgrade compaction (204E10000) | SY | 343 | $6.46 | $6.50 |
| 10 | Rounded end section (606E20050) | EACH | 3 | $80.00 | $85.00 |
| 11 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,500.00 | $1,380.00 |
| 12 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 3 | $2,850.00 | $2,620.00 |
| 13 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 1 | $3,500.00 | $2,980.00 |
| 14 | 4" concrete walk (608E10000) | SF | 295 | $21.68 | $30.00 |
| 15 | Special - misc.: work involving asbestos containin (690E98400) | LS | 1 | $433.77 | $50.00 |
| 16 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 4 | $210.29 | $270.00 |
| 17 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 110 | $226.65 | $110.00 |
| 18 | Soil analysis test (659E00100) | EACH | 2 | $135.00 | $135.00 |
| 19 | Topsoil (659E00300) | CY | 29 | $102.46 | $60.00 |
| 20 | Seeding and mulching (659E10000) | SY | 257 | $26.79 | $25.00 |
| 21 | Repair seeding and mulching (659E14000) | SY | 13 | $23.75 | $24.00 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.03 | $995.33 | $650.00 |
| 23 | Lime (659E31000) | ACRE | 0.05 | $157.80 | $50.00 |
| 24 | Water (659E35000) | MGAL | 2 | $1.00 | $1.00 |
| 25 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 |
| 26 | Concrete masonry (602E20000) | CY | 0.20 | $3,938.90 | $6,000.00 |
| 27 | 12" conduit, type B (611E04400) | FT | 48 | $122.10 | $160.00 |
| 28 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 26 | $360.00 | $360.00 |
| 29 | Aggregate base (304E20000) | CY | 53 | $102.90 | $130.00 |
| 30 | Non-tracking tack coat (407E20000) | GAL | 21 | $6.00 | $6.00 |
| 31 | Stabilized crushed aggregate (411E10000) | CY | 5 | $220.99 | $120.00 |
| 32 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 7 | $790.00 | $790.00 |
| 33 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 9 | $760.00 | $760.00 |
| 34 | Curb, type 6 (609E26000) | FT | 48 | $116.29 | $50.00 |
| 35 | Manhole adjusted to grade (611E99654) | EACH | 1 | $259.42 | $500.00 |
| 36 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 4 | $13.00 | $12.00 |
| 37 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $12.50 | $70.00 |
| 38 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $13.18 | $75.00 |
| 39 | Traffic compacted surface, type A or B (410E12000) | CY | 10 | $241.02 | $101.43 |
| 40 | Detour signing (614E12420) | LS | 1 | $6,379.55 | $10,000 |
| 41 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $377.05 | $250.00 |
| 42 | Water (616E10000) | MGAL | 5 | $32.48 | $70.00 |
| 43 | Structure removed, over 20 foot span (202E11002) | LS | 1 | $73,170 | $185,000 |
| 44 | Wearing course removed (202E23500) | SY | 199 | $11.42 | $15.00 |
| 45 | Unclassified excavation (503E21100) | CY | 182 | $98.12 | $220.00 |
| 46 | Pile driving equipment mobilization (505E11100) | LS | 1 | $5,448.92 | $60,000 |
| 47 | 12" cast-in-place reinforced concrete piles, driven (507E00500) | FT | 1,050 | $50.33 | $45.00 |
| 48 | 12" cast-in-place reinforced concrete piles, driven, as per plan (507E00501) | FT | 960 | $50.29 | $42.00 |
| 49 | 12" cast-in-place reinforced concrete piles, furnished (507E00550) | FT | 2,140 | $38.46 | $45.00 |
| 50 | Prebored holes, as per plan (507E92201) | FT | 222 | $67.14 | $125.00 |
| 51 | Epoxy coated steel reinforcement (509E10000) | LB | 24,631 | $1.68 | $1.80 |
| 52 | Class QC2 concrete with QC/QA, superstructure, as per plan (511E31613) | CY | 108 | $904.36 | $1,000.00 |
| 53 | Class QC1 concrete, abutment including footing (511E43510) | CY | 113 | $907.62 | $775.00 |
| 54 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 84 | $14.50 | $14.50 |
| 55 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 315 | $28.00 | $28.00 |
| 56 | Type 2 waterproofing (512E33000) | SY | 14 | $65.49 | $70.00 |
| 57 | Prestressed concrete composite box beam bridge members, level 1, CB42-48 (515E12110) | EACH | 8 | $76,096 | $72,000 |
| 58 | 1" preformed expansion joint filler (516E13600) | SF | 14 | $4.76 | $8.00 |
| 59 | 2" preformed expansion joint filler (516E13900) | SF | 43 | $4.83 | $12.00 |
| 60 | Semi-integral abutment expansion joint seal (516E14020) | FT | 97 | $50.00 | $38.00 |
| 61 | Elastomeric bearing with internal laminates only (neoprene), as per plan (516E43101) | EACH | 32 | $220.61 | $220.00 |
| 62 | Railing (twin steel tube) (517E70000) | FT | 101 | $238.00 | $240.00 |
| 63 | Railing (concrete parapet with twin steel tube railing) (517E75120) | FT | 133 | $399.89 | $280.00 |
| 64 | Porous backfill with geotextile fabric (518E21200) | CY | 61 | $113.66 | $90.00 |
| 65 | 6" perforated corrugated plastic pipe (518E40000) | FT | 94 | $5.13 | $28.00 |
| 66 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 39 | $24.47 | $25.00 |
| 67 | Dynamic load testing (523E20000) | EACH | 2 | $5,277.94 | $6,000.00 |
| 68 | Reinforced concrete approach slabs with QC/QA (T=1 (526E10010) | SY | 54 | $320.59 | $500.00 |
| 69 | Reinforced concrete approach slabs with QC/QA (T=1 (526E15010) | SY | 72 | $373.45 | $465.00 |
| 70 | Type A installation (526E90010) | FT | 33 | $151.06 | $210.00 |
| 71 | Type A installation, as per plan (526E90011) | FT | 33 | $156.16 | $170.00 |
| 72 | Special - structural survey and monitoring of vibration (530E14000) | LS | 1 | $6,210.00 | $6,000.00 |
| 73 | Structure grounding system (625E33000) | EACH | 1 | $14,000 | $20,000 |
| 74 | Polymer modified asphalt expansion joint system (846E00110) | CF | 22 | $744.59 | $745.00 |
| 75 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $9,286.45 | $19,000 |
| 76 | Maintaining traffic (614E11000) | LS | 1 | $5,829.55 | $7,500.00 |
| 77 | Field office, type B (619E16010) | MNTH | 6 | $2,443.33 | $3,200.00 |
| 78 | Construction layout stakes and surveying (623E10000) | LS | 1 | $16,710 | $20,000 |
| 79 | Mobilization (624E10000) | LS | 1 | $86,196 | $90,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.