ODOT contract 260368 bid tabulation
PIK-SR 32-18.40 (INTERSECTION). Let by Ohio DOT on August 13, 2026, PIK. 9 bids received; low bid $2,836,187 by Allard Excavation LLC, -15% against the engineer's estimate of $3,332,000.
- Owner
- Ohio DOT
- Letting
- 13 AUG 2026
- Pay items
- 138
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Allard Excavation LLC | $2,836,187 | Low | -15% |
| 2 | Shelly & Sands Inc | $2,994,823 | +6.0% | -10% |
| 3 | Shelly Company | $3,104,659 | +9.0% | -7.0% |
| 4 | Axis Civil Construction LLC | $3,128,083 | +10% | -6.0% |
| 5 | D G M Inc | $3,219,136 | +14% | -3.0% |
| 6 | Complete General Construction Company | $3,316,308 | +17% | 0.0% |
| 7 | Sunesis Construction Co | $3,329,693 | +17% | 0.0% |
| 8 | Miller Bros Const Inc | $3,341,073 | +18% | 0.0% |
| 9 | Alan Stone Co Inc | $3,469,353 | +22% | +4.0% |
Engineer's estimate: $3,332,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Allard Excavation LLC | 2. Shelly & Sands Inc | 3. Shelly Company | 4. Axis Civil Construction LLC | 5. D G M Inc | 6. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,183.00 | $22,000 | $26,000 | $2,500.00 | $28,000 | $5,800.00 |
| 2 | Pavement removed (202E23000) | SY | 4,004 | $18.00 | $20.00 | $36.00 | $16.00 | $15.00 | $30.00 |
| 3 | Guardrail removed (202E38000) | FT | 1,172 | $3.00 | $2.80 | $2.80 | $6.00 | $3.00 | $2.25 |
| 4 | Monument assembly removed (202E60010) | EACH | 4 | $71.00 | $225.00 | $310.00 | $400.00 | $200.00 | $345.00 |
| 5 | Fence removed (202E75000) | FT | 106 | $4.00 | $10.00 | $6.34 | $8.50 | $10.00 | $5.00 |
| 6 | Excavation (203E10000) | CY | 4,821 | $24.00 | $14.00 | $46.75 | $32.00 | $19.00 | $22.00 |
| 7 | Embankment (203E20000) | CY | 7,497 | $21.00 | $21.00 | $33.50 | $32.00 | $22.00 | $23.00 |
| 8 | Subgrade compaction (204E10000) | SY | 10,230 | $2.00 | $4.00 | $1.45 | $1.50 | $3.50 | $3.20 |
| 9 | Excavation of subgrade (204E13000) | CY | 1,679 | $26.00 | $37.00 | $29.00 | $32.00 | $19.00 | $35.00 |
| 10 | Granular material, type B (204E30010) | CY | 1,679 | $66.00 | $65.00 | $57.25 | $70.00 | $90.00 | $52.00 |
| 11 | Proof rolling (204E45000) | HR | 6 | $256.00 | $275.00 | $850.00 | $250.00 | $150.00 | $370.00 |
| 12 | Geotextile fabric (204E50000) | SY | 4,031 | $2.00 | $1.50 | $1.45 | $2.00 | $2.00 | $2.40 |
| 13 | Guardrail, type MGS (606E15050) | FT | 1,212.50 | $21.50 | $21.50 | $21.50 | $21.38 | $23.00 | $22.40 |
| 14 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,350.00 | $1,350.00 | $1,350.00 | $1,200.00 | $1,400.00 | $1,380.00 |
| 15 | Fence, type 47 (607E15000) | FT | 100 | $30.00 | $30.00 | $30.00 | $30.00 | $40.00 | $43.40 |
| 16 | Reference monument, type A (623E40500) | EACH | 4 | $1,379.00 | $1,700.00 | $1,025.00 | $600.00 | $500.00 | $1,000.00 |
| 17 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 10 | $90.00 | $210.00 | $350.00 | $170.00 | $250.00 | $145.00 |
| 18 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $135.00 | $50.00 | $150.00 | $100.00 | $150.00 |
| 19 | Topsoil (659E00300) | CY | 1,223 | $29.00 | $16.00 | $40.00 | $50.00 | $25.00 | $35.00 |
| 20 | Seeding and mulching (659E10000) | SY | 11,019 | $1.05 | $1.50 | $1.02 | $1.05 | $1.75 | $1.05 |
| 21 | Repair seeding and mulching (659E14000) | SY | 551 | $1.05 | $0.80 | $1.02 | $1.05 | $0.05 | $1.05 |
| 22 | Commercial fertilizer (659E20000) | TON | 1.49 | $1,250.00 | $940.00 | $850.00 | $1,250.00 | $1,500.00 | $1,250.00 |
| 23 | Lime (659E31000) | ACRE | 2.28 | $150.00 | $160.00 | $0.10 | $150.00 | $300.00 | $150.00 |
| 24 | Water (659E35000) | MGAL | 61 | $1.00 | $1.00 | $0.10 | $1.00 | $1.00 | $1.00 |
| 25 | Ditch erosion protection (670E00700) | SY | 1,123 | $2.00 | $1.70 | $1.80 | $2.00 | $2.50 | $2.00 |
| 26 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,000.00 | $2,800.00 | $2,800.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 27 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $14,700 | $6,800.00 | $1,975.00 | $14,700 | $13,000 | $14,700 |
| 28 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $13,300 | $14,000 | $8,250.00 | $13,500 | $15,000 | $13,300 |
| 29 | Erosion control (832E30000) | EACH | 48,200 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 30 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 217 | $5.00 | $5.61 | $1.80 | $5.00 | $8.00 | $5.00 |
| 31 | 6" shallow pipe underdrains with geotextile fabric (605E11110) | FT | 8,369 | $14.00 | $16.50 | $16.00 | $22.00 | $17.50 | $16.30 |
| 32 | 6" unclassified pipe underdrains with geotextile fabric (605E13410) | FT | 389 | $16.00 | $20.00 | $39.75 | $25.00 | $30.00 | $23.75 |
| 33 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 129 | $21.00 | $20.00 | $51.50 | $26.00 | $20.00 | $22.40 |
| 34 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 83 | $17.00 | $30.00 | $107.50 | $25.00 | $25.00 | $34.00 |
| 35 | 6" conduit, type B (611E00900) | FT | 49 | $20.00 | $30.00 | $92.25 | $22.00 | $30.00 | $42.00 |
| 36 | 6" conduit, type F (611E01500) | FT | 60 | $14.00 | $32.00 | $65.25 | $22.00 | $10.00 | $23.00 |
| 37 | 12" conduit, type B (611E04400) | FT | 673 | $66.00 | $115.00 | $76.75 | $65.00 | $120.00 | $124.00 |
| 38 | 12" conduit, type C (611E04600) | FT | 700 | $69.00 | $90.00 | $53.25 | $65.00 | $90.00 | $100.00 |
| 39 | 15" conduit, type B (611E05900) | FT | 200 | $75.00 | $112.00 | $68.50 | $75.00 | $115.00 | $115.00 |
| 40 | Catch basin, no. 8 (611E98410) | EACH | 2 | $6,415.00 | $7,000.00 | $3,835.00 | $4,500.00 | $6,000.00 | $7,400.00 |
| 41 | Inlet, no. 2-6 (611E98710) | EACH | 3 | $7,754.00 | $7,000.00 | $5,725.00 | $6,500.00 | $4,750.00 | $6,800.00 |
| 42 | Manhole, no. 3 (611E99574) | EACH | 3 | $5,027.00 | $4,000.00 | $3,335.00 | $4,500.00 | $2,700.00 | $5,100.00 |
| 43 | Precast reinforced concrete outlet (611E99710) | EACH | 5 | $370.00 | $450.00 | $305.00 | $1,000.00 | $300.00 | $400.00 |
| 44 | Pavement planing, asphalt concrete, 1.25" (254E01000) | SY | 14,108 | $3.00 | $3.00 | $2.85 | $2.85 | $3.10 | $3.00 |
| 45 | Pavement planing, asphalt concrete, 3.0" (254E01000) | SY | 415 | $5.00 | $5.00 | $39.00 | $15.00 | $5.25 | $5.00 |
| 46 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 2,239 | $192.50 | $192.50 | $190.00 | $190.00 | $200.00 | $192.50 |
| 47 | Aggregate base (304E20000) | CY | 1,744 | $66.00 | $60.00 | $59.00 | $90.00 | $92.50 | $85.00 |
| 48 | Non-tracking tack coat (407E20000) | GAL | 2,882 | $3.50 | $3.50 | $4.30 | $4.30 | $3.50 | $3.50 |
| 49 | Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000) | CY | 835 | $245.00 | $245.00 | $255.75 | $255.75 | $260.00 | $245.00 |
| 50 | Asphalt concrete intermediate course, type 2, (446) (441E10200) | CY | 488 | $240.00 | $240.00 | $256.75 | $256.75 | $250.00 | $240.00 |
| 51 | Concrete median (609E71000) | SF | 4,753 | $13.00 | $15.00 | $12.25 | $22.00 | $15.00 | $15.00 |
| 52 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 5,974 | $1.09 | $1.10 | $1.08 | $1.75 | $1.50 | $2.00 |
| 53 | Connection, fused pull apart (625E00450) | EACH | 8 | $181.00 | $181.00 | $155.00 | $181.00 | $191.00 | $155.00 |
| 54 | Connection, unfused pull apart (625E00460) | EACH | 8 | $163.00 | $163.00 | $160.00 | $163.00 | $173.00 | $160.00 |
| 55 | Connection, unfused permanent (625E00480) | EACH | 9 | $155.00 | $155.00 | $140.00 | $155.00 | $165.00 | $140.00 |
| 56 | Light pole, conventional, AT15B40 (625E10490) | EACH | 8 | $4,929.00 | $4,929.00 | $3,350.00 | $4,929.00 | $5,500.00 | $3,350.00 |
| 57 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 8 | $1,814.50 | $1,814.50 | $3,200.00 | $1,814.50 | $1,900.00 | $3,200.00 |
| 58 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,440 | $1.39 | $1.40 | $3.25 | $1.39 | $1.50 | $3.25 |
| 59 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 2,301 | $16.93 | $17.00 | $17.00 | $16.93 | $18.00 | $17.00 |
| 60 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 407 | $63.42 | $63.50 | $67.00 | $63.42 | $70.00 | $67.00 |
| 61 | Luminaire, conventional, solid state (LED), ies-II (625E26252) | EACH | 8 | $543.00 | $543.00 | $450.00 | $543.00 | $575.00 | $450.00 |
| 62 | Trench, 24" deep (625E29002) | FT | 2,171 | $6.59 | $6.60 | $9.50 | $6.59 | $7.00 | $9.50 |
| 63 | Pull box, 725.08, 18" (625E30700) | EACH | 4 | $1,172.00 | $1,172.00 | $1,500.00 | $1,172.00 | $1,250.00 | $1,500.00 |
| 64 | Pull box removed (625E31510) | EACH | 2 | $244.00 | $244.00 | $253.90 | $244.00 | $275.00 | $254.00 |
| 65 | Ground rod (625E32000) | EACH | 9 | $381.00 | $381.00 | $350.00 | $381.00 | $400.00 | $350.00 |
| 66 | Power service, as per plan (625E34001) | EACH | 1 | $13,596 | $13,596 | $9,000.00 | $13,596 | $15,000 | $9,000.00 |
| 67 | Underground warning marking tape (625E36010) | FT | 2,171 | $0.05 | $0.25 | $1.25 | $0.05 | $0.05 | $1.60 |
| 68 | Arc flash calculations and label, lighting control (625E76000) | EACH | 1 | $3,655.00 | $3,655.00 | $3,600.00 | $3,655.00 | $3,750.00 | $3,600.00 |
| 69 | Lighting, misc.: foundation test hole (625E98000) | EACH | 2 | $2,901.00 | $1,901.00 | $2,800.00 | $1,901.00 | $2,000.00 | $2,800.00 |
| 70 | Delineator, post surface mounted, as per plan (620E60001) | EACH | 89 | $115.00 | $115.00 | $115.00 | $115.00 | $120.00 | $95.00 |
| 71 | RPM (621E00100) | EACH | 233 | $47.00 | $47.00 | $47.00 | $52.00 | $50.00 | $58.00 |
| 72 | Raised pavement marker removed (621E54000) | EACH | 120 | $6.92 | $10.00 | $60.00 | $40.00 | $10.00 | $17.00 |
| 73 | Barrier reflector, type 2, (one-way) (626E00110) | EACH | 20 | $12.00 | $12.00 | $12.00 | $13.00 | $15.00 | $13.40 |
| 74 | Ground mounted support, no. 2 post (630E02100) | FT | 277.80 | $13.50 | $13.50 | $13.50 | $13.50 | $16.00 | $15.00 |
| 75 | Ground mounted support, no. 3 post (630E03100) | FT | 534.60 | $14.00 | $14.00 | $14.00 | $14.00 | $16.00 | $16.00 |
| 76 | Ground mounted support, no. 4 post (630E04100) | FT | 58.40 | $20.00 | $20.00 | $20.00 | $20.00 | $22.00 | $18.50 |
| 77 | Ground mounted structural beam support, W6X9 (630E06500) | FT | 108.30 | $22.00 | $22.00 | $22.00 | $22.00 | $23.00 | $40.00 |
| 78 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 43 | $48.00 | $48.00 | $48.00 | $48.00 | $50.00 | $73.00 |
| 79 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 87.50 | $28.00 | $28.00 | $28.00 | $28.00 | $30.00 | $50.00 |
| 80 | Sign post reflector (630E08600) | EACH | 22 | $45.00 | $45.00 | $45.00 | $45.00 | $60.00 | $45.00 |
| 81 | Breakaway structural beam connection (630E09000) | EACH | 10 | $550.00 | $550.00 | $550.00 | $550.00 | $570.00 | $650.00 |
| 82 | Sign, flat sheet (630E80100) | SF | 390.90 | $22.00 | $22.00 | $22.00 | $22.00 | $17.00 | $20.00 |
| 83 | Sign, ground mounted extrusheet (630E80200) | SF | 49 | $30.00 | $30.00 | $30.00 | $30.00 | $32.00 | $30.00 |
| 84 | Sign, ground mounted extrusheet, as per plan (630E80201) | SF | 185 | $31.00 | $31.00 | $31.00 | $31.00 | $33.00 | $29.00 |
| 85 | Ground mounted structural beam support foundation (630E84500) | EACH | 10 | $1,250.00 | $1,250.00 | $1,250.00 | $1,250.00 | $1,300.00 | $1,140.00 |
| 86 | Removal of ground mounted sign and disposal (630E84900) | EACH | 45 | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 | $15.00 |
| 87 | Removal of ground mounted sign and reerection (630E85100) | EACH | 5 | $125.00 | $125.00 | $125.00 | $125.00 | $65.00 | $70.00 |
| 88 | Removal of ground mounted major sign and reerection (630E85600) | EACH | 1 | $650.00 | $650.00 | $650.00 | $650.00 | $700.00 | $385.00 |
| 89 | Removal of ground mounted post support and disposal (630E86002) | EACH | 30 | $20.00 | $20.00 | $20.00 | $20.00 | $45.00 | $20.00 |
| 90 | Removal of ground mounted structural beam support (630E86102) | EACH | 6 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 | $295.00 |
| 91 | Edge line, 6" (644E00104) | MI | 1.76 | $5,480.00 | $5,480.00 | $3,400.00 | $5,480.00 | $5,650.00 | $5,480.00 |
| 92 | Lane line, 6" (644E00204) | MI | 1.45 | $2,070.00 | $2,070.00 | $2,250.00 | $2,070.00 | $2,200.00 | $2,070.00 |
| 93 | Center line (644E00300) | MI | 0.10 | $9,500.00 | $9,500.00 | $5,200.00 | $9,500.00 | $10,000 | $9,500.00 |
| 94 | Channelizing line, 12" (644E00404) | FT | 4,506 | $2.40 | $2.40 | $2.80 | $2.40 | $2.75 | $2.40 |
| 95 | Stop line (644E00500) | FT | 74 | $8.50 | $8.50 | $7.75 | $8.50 | $8.75 | $8.50 |
| 96 | Transverse/diagonal line (644E00700) | FT | 204 | $8.25 | $8.25 | $7.75 | $8.25 | $8.50 | $8.25 |
| 97 | Chevron marking (644E00720) | FT | 707 | $8.25 | $8.25 | $9.00 | $8.25 | $8.50 | $8.25 |
| 98 | Lane arrow (644E01300) | EACH | 53 | $120.00 | $120.00 | $100.00 | $120.00 | $130.00 | $120.00 |
| 99 | Yield line (644E20800) | FT | 87 | $12.45 | $12.50 | $8.00 | $12.45 | $13.50 | $12.45 |
| 100 | Removal of traffic signal installation (632E90100) | EACH | 1 | $4,500.00 | $3,000.00 | $3,000.00 | $4,500.00 | $5,000.00 | $3,750.00 |
| 101 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $85.00 | $105.00 | $120.00 | $75.00 | $100.00 | $125.00 |
| 102 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 12 | $1,950.00 | $2,302.59 | $2,150.00 | $2,800.00 | $2,350.00 | $2,420.00 |
| 103 | Work zone lighting system (614E12740) | EACH | 1 | $16,056 | $16,100 | $40,000 | $16,056 | $17,000 | $50,000 |
| 104 | Asphalt concrete for maintaining traffic (614E13000) | CY | 6 | $275.00 | $325.00 | $350.00 | $850.00 | $200.00 | $900.00 |
| 105 | Barrier reflector, type 1, (one-way) (614E13310) | EACH | 171 | $9.00 | $8.00 | $9.00 | $25.00 | $10.00 | $10.00 |
| 106 | Object marker, one way (614E13350) | EACH | 171 | $35.00 | $13.00 | $35.00 | $40.00 | $37.00 | $19.00 |
| 107 | Portable changeable message sign, as per plan (614E18601) | SNMT | 16 | $995.00 | $800.00 | $995.00 | $864.00 | $1,000.00 | $900.00 |
| 108 | Work zone lane line, class I, 4" (614E20000) | MI | 1.45 | $620.00 | $620.00 | $830.00 | $620.00 | $700.00 | $1,650.00 |
| 109 | Work zone center line, class I (614E21000) | MI | 0.35 | $2,310.00 | $2,310.00 | $1,290.00 | $2,310.00 | $2,500.00 | $5,075.00 |
| 110 | Work zone edge line, class I, 4" (614E22000) | MI | 2.21 | $1,340.00 | $1,340.00 | $970.00 | $1,340.00 | $1,500.00 | $2,150.00 |
| 111 | Work zone edge line, class I, 6" (614E22010) | MI | 1.95 | $1,825.00 | $1,825.00 | $970.00 | $1,825.00 | $2,000.00 | $2,600.00 |
| 112 | Work zone channelizing line, class I, 8" (614E23000) | FT | 4,529 | $0.80 | $0.80 | $1.00 | $0.80 | $0.85 | $0.65 |
| 113 | Work zone dotted line, class I (614E24000) | FT | 2,497 | $0.45 | $0.45 | $0.65 | $0.45 | $0.50 | $0.70 |
| 114 | Work zone transverse/diagonal line, class I (614E25000) | FT | 201 | $1.20 | $1.20 | $7.00 | $1.20 | $1.25 | $10.00 |
| 115 | Work zone stop line, class I (614E26000) | FT | 274 | $3.25 | $3.25 | $5.00 | $3.25 | $3.50 | $7.00 |
| 116 | Work zone arrow, class I (614E30000) | EACH | 53 | $135.00 | $135.00 | $45.00 | $135.00 | $150.00 | $175.00 |
| 117 | Work zone pavement marking, misc.: chevron marking (614E98100) | FT | 430 | $3.25 | $3.25 | $7.00 | $3.25 | $3.50 | $10.00 |
| 118 | Work zone pavement marking, misc.: yield line, cla (614E98100) | FT | 269 | $3.25 | $3.25 | $3.00 | $3.25 | $3.50 | $18.00 |
| 119 | Pavement for maintaining traffic, class B, as per plan (615E25001) | SY | 28 | $310.00 | $365.00 | $250.00 | $250.00 | $250.00 | $400.00 |
| 120 | Water (616E10000) | MGAL | 36 | $1.00 | $85.00 | $1.00 | $1.00 | $1.00 | $100.00 |
| 121 | Portable barrier, unanchored (622E41100) | FT | 8,030 | $20.00 | $24.00 | $17.50 | $20.00 | $19.00 | $28.00 |
| 122 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 8 | $1,250.00 | $800.00 | $1,250.00 | $864.00 | $1,400.00 | $950.00 |
| 123 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $24,000 | $18,300 | $13,750 | $16,000 | $102,000 | $21,000 |
| 124 | Maintaining traffic (614E11000) | LS | 1 | $69,049 | $73,575 | $71,750 | $70,000 | $158,300 | $130,000 |
| 125 | Field office, type B (619E16010) | MNTH | 6 | $1,900.00 | $5,450.00 | $2,500.00 | $2,000.00 | $1,250.00 | $2,650.00 |
| 126 | Construction layout stakes and surveying (623E10000) | LS | 1 | $51,000 | $40,000 | $17,500 | $27,000 | $20,000 | $40,000 |
| 127 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,788.00 | $1,800.00 | $5,000.00 | $1,600.00 | $5,000.00 | $1,400.00 |
| 128 | Mobilization (624E10000) | LS | 1 | $100,000 | $145,000 | $75,000 | $90,000 | $110,000 | $165,000 |
| 200 | Riprap, type D (601E11000) | SY | 9 | $396.00 | $600.00 | $635.00 | $360.00 | $300.00 | $525.00 |
| 201 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 1.45 | $530.00 | $530.00 | $830.00 | $530.00 | $550.00 | $1,095.00 |
| 202 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.10 | $1,535.00 | $1,535.00 | $1,290.00 | $1,535.00 | $1,600.00 | $10,500 |
| 203 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 1.76 | $995.00 | $995.00 | $970.00 | $995.00 | $1,100.00 | $1,600.00 |
| 204 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 4,506 | $0.65 | $0.65 | $1.00 | $0.65 | $0.70 | $0.75 |
| 205 | Work zone transverse/diagonal line, class III, 642 paint (614E25620) | FT | 204 | $0.90 | $0.90 | $7.00 | $0.90 | $1.00 | $11.25 |
| 206 | Work zone stop line, class III, 642 paint (614E26610) | FT | 74 | $2.95 | $2.95 | $5.00 | $2.95 | $3.25 | $11.00 |
| 207 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 53 | $130.00 | $130.00 | $45.00 | $130.00 | $145.00 | $150.00 |
| 208 | Work zone pavement marking, misc.: chevron marking (614E98100) | FT | 707 | $3.25 | $3.25 | $7.00 | $3.25 | $3.50 | $6.00 |
| 209 | Work zone pavement marking, misc.: yield line, cla (614E98100) | FT | 87 | $3.25 | $3.25 | $3.00 | $3.25 | $3.50 | $16.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 13, 2026. Compiled by Mirage Metrics.