ODOT contract 260368 bid tabulation

PIK-SR 32-18.40 (INTERSECTION). Let by Ohio DOT on August 13, 2026, PIK. 9 bids received; low bid $2,836,187 by Allard Excavation LLC, -15% against the engineer's estimate of $3,332,000.

Owner
Ohio DOT
Letting
13 AUG 2026
Pay items
138
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Allard Excavation LLC$2,836,187Low-15%
2Shelly & Sands Inc$2,994,823+6.0%-10%
3Shelly Company$3,104,659+9.0%-7.0%
4Axis Civil Construction LLC$3,128,083+10%-6.0%
5D G M Inc$3,219,136+14%-3.0%
6Complete General Construction Company$3,316,308+17%0.0%
7Sunesis Construction Co$3,329,693+17%0.0%
8Miller Bros Const Inc$3,341,073+18%0.0%
9Alan Stone Co Inc$3,469,353+22%+4.0%
ODOT contract 260368: bids by rank

Engineer's estimate: $3,332,000.

Bid tabulation

LinePay itemUnitQuantity1. Allard Excavation LLC2. Shelly & Sands Inc3. Shelly Company4. Axis Civil Construction LLC5. D G M Inc6. Complete General Construction Company
1Clearing and grubbing (201E11000)LS1$3,183.00$22,000$26,000$2,500.00$28,000$5,800.00
2Pavement removed (202E23000)SY4,004$18.00$20.00$36.00$16.00$15.00$30.00
3Guardrail removed (202E38000)FT1,172$3.00$2.80$2.80$6.00$3.00$2.25
4Monument assembly removed (202E60010)EACH4$71.00$225.00$310.00$400.00$200.00$345.00
5Fence removed (202E75000)FT106$4.00$10.00$6.34$8.50$10.00$5.00
6Excavation (203E10000)CY4,821$24.00$14.00$46.75$32.00$19.00$22.00
7Embankment (203E20000)CY7,497$21.00$21.00$33.50$32.00$22.00$23.00
8Subgrade compaction (204E10000)SY10,230$2.00$4.00$1.45$1.50$3.50$3.20
9Excavation of subgrade (204E13000)CY1,679$26.00$37.00$29.00$32.00$19.00$35.00
10Granular material, type B (204E30010)CY1,679$66.00$65.00$57.25$70.00$90.00$52.00
11Proof rolling (204E45000)HR6$256.00$275.00$850.00$250.00$150.00$370.00
12Geotextile fabric (204E50000)SY4,031$2.00$1.50$1.45$2.00$2.00$2.40
13Guardrail, type MGS (606E15050)FT1,212.50$21.50$21.50$21.50$21.38$23.00$22.40
14Anchor assembly, MGS type T (606E26550)EACH2$1,350.00$1,350.00$1,350.00$1,200.00$1,400.00$1,380.00
15Fence, type 47 (607E15000)FT100$30.00$30.00$30.00$30.00$40.00$43.40
16Reference monument, type A (623E40500)EACH4$1,379.00$1,700.00$1,025.00$600.00$500.00$1,000.00
17Tied concrete block mat with type 1 underlayment (601E21050)SY10$90.00$210.00$350.00$170.00$250.00$145.00
18Soil analysis test (659E00100)EACH2$150.00$135.00$50.00$150.00$100.00$150.00
19Topsoil (659E00300)CY1,223$29.00$16.00$40.00$50.00$25.00$35.00
20Seeding and mulching (659E10000)SY11,019$1.05$1.50$1.02$1.05$1.75$1.05
21Repair seeding and mulching (659E14000)SY551$1.05$0.80$1.02$1.05$0.05$1.05
22Commercial fertilizer (659E20000)TON1.49$1,250.00$940.00$850.00$1,250.00$1,500.00$1,250.00
23Lime (659E31000)ACRE2.28$150.00$160.00$0.10$150.00$300.00$150.00
24Water (659E35000)MGAL61$1.00$1.00$0.10$1.00$1.00$1.00
25Ditch erosion protection (670E00700)SY1,123$2.00$1.70$1.80$2.00$2.50$2.00
26Storm water pollution prevention plan (832E15000)LS1$3,000.00$2,800.00$2,800.00$3,000.00$3,000.00$3,000.00
27Storm water pollution prevention inspections (832E15002)LS1$14,700$6,800.00$1,975.00$14,700$13,000$14,700
28Storm water pollution prevention inspection software (832E15010)LS1$13,300$14,000$8,250.00$13,500$15,000$13,300
29Erosion control (832E30000)EACH48,200$1.00$1.00$1.00$1.00$1.00$1.00
30Seeding and erosion control with turf reinforcing mat, type 1 (836E10000)SY217$5.00$5.61$1.80$5.00$8.00$5.00
316" shallow pipe underdrains with geotextile fabric (605E11110)FT8,369$14.00$16.50$16.00$22.00$17.50$16.30
326" unclassified pipe underdrains with geotextile fabric (605E13410)FT389$16.00$20.00$39.75$25.00$30.00$23.75
336" base pipe underdrains with geotextile fabric (605E14020)FT129$21.00$20.00$51.50$26.00$20.00$22.40
346" conduit, type F for underdrain outlets (611E00510)FT83$17.00$30.00$107.50$25.00$25.00$34.00
356" conduit, type B (611E00900)FT49$20.00$30.00$92.25$22.00$30.00$42.00
366" conduit, type F (611E01500)FT60$14.00$32.00$65.25$22.00$10.00$23.00
3712" conduit, type B (611E04400)FT673$66.00$115.00$76.75$65.00$120.00$124.00
3812" conduit, type C (611E04600)FT700$69.00$90.00$53.25$65.00$90.00$100.00
3915" conduit, type B (611E05900)FT200$75.00$112.00$68.50$75.00$115.00$115.00
40Catch basin, no. 8 (611E98410)EACH2$6,415.00$7,000.00$3,835.00$4,500.00$6,000.00$7,400.00
41Inlet, no. 2-6 (611E98710)EACH3$7,754.00$7,000.00$5,725.00$6,500.00$4,750.00$6,800.00
42Manhole, no. 3 (611E99574)EACH3$5,027.00$4,000.00$3,335.00$4,500.00$2,700.00$5,100.00
43Precast reinforced concrete outlet (611E99710)EACH5$370.00$450.00$305.00$1,000.00$300.00$400.00
44Pavement planing, asphalt concrete, 1.25" (254E01000)SY14,108$3.00$3.00$2.85$2.85$3.10$3.00
45Pavement planing, asphalt concrete, 3.0" (254E01000)SY415$5.00$5.00$39.00$15.00$5.25$5.00
46Asphalt concrete base, PG64-22, (449) (301E56000)CY2,239$192.50$192.50$190.00$190.00$200.00$192.50
47Aggregate base (304E20000)CY1,744$66.00$60.00$59.00$90.00$92.50$85.00
48Non-tracking tack coat (407E20000)GAL2,882$3.50$3.50$4.30$4.30$3.50$3.50
49Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000)CY835$245.00$245.00$255.75$255.75$260.00$245.00
50Asphalt concrete intermediate course, type 2, (446) (441E10200)CY488$240.00$240.00$256.75$256.75$250.00$240.00
51Concrete median (609E71000)SF4,753$13.00$15.00$12.25$22.00$15.00$15.00
52Rumble strips, shoulder (asphalt concrete) (618E40100)FT5,974$1.09$1.10$1.08$1.75$1.50$2.00
53Connection, fused pull apart (625E00450)EACH8$181.00$181.00$155.00$181.00$191.00$155.00
54Connection, unfused pull apart (625E00460)EACH8$163.00$163.00$160.00$163.00$173.00$160.00
55Connection, unfused permanent (625E00480)EACH9$155.00$155.00$140.00$155.00$165.00$140.00
56Light pole, conventional, AT15B40 (625E10490)EACH8$4,929.00$4,929.00$3,350.00$4,929.00$5,500.00$3,350.00
57Light pole foundation, 24" X 8' deep (625E14100)EACH8$1,814.50$1,814.50$3,200.00$1,814.50$1,900.00$3,200.00
58No. 10 AWG pole and bracket cable (625E23400)FT1,440$1.39$1.40$3.25$1.39$1.50$3.25
591-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT2,301$16.93$17.00$17.00$16.93$18.00$17.00
60Conduit, jacked or drilled, 725.04, 3" (625E25902)FT407$63.42$63.50$67.00$63.42$70.00$67.00
61Luminaire, conventional, solid state (LED), ies-II (625E26252)EACH8$543.00$543.00$450.00$543.00$575.00$450.00
62Trench, 24" deep (625E29002)FT2,171$6.59$6.60$9.50$6.59$7.00$9.50
63Pull box, 725.08, 18" (625E30700)EACH4$1,172.00$1,172.00$1,500.00$1,172.00$1,250.00$1,500.00
64Pull box removed (625E31510)EACH2$244.00$244.00$253.90$244.00$275.00$254.00
65Ground rod (625E32000)EACH9$381.00$381.00$350.00$381.00$400.00$350.00
66Power service, as per plan (625E34001)EACH1$13,596$13,596$9,000.00$13,596$15,000$9,000.00
67Underground warning marking tape (625E36010)FT2,171$0.05$0.25$1.25$0.05$0.05$1.60
68Arc flash calculations and label, lighting control (625E76000)EACH1$3,655.00$3,655.00$3,600.00$3,655.00$3,750.00$3,600.00
69Lighting, misc.: foundation test hole (625E98000)EACH2$2,901.00$1,901.00$2,800.00$1,901.00$2,000.00$2,800.00
70Delineator, post surface mounted, as per plan (620E60001)EACH89$115.00$115.00$115.00$115.00$120.00$95.00
71RPM (621E00100)EACH233$47.00$47.00$47.00$52.00$50.00$58.00
72Raised pavement marker removed (621E54000)EACH120$6.92$10.00$60.00$40.00$10.00$17.00
73Barrier reflector, type 2, (one-way) (626E00110)EACH20$12.00$12.00$12.00$13.00$15.00$13.40
74Ground mounted support, no. 2 post (630E02100)FT277.80$13.50$13.50$13.50$13.50$16.00$15.00
75Ground mounted support, no. 3 post (630E03100)FT534.60$14.00$14.00$14.00$14.00$16.00$16.00
76Ground mounted support, no. 4 post (630E04100)FT58.40$20.00$20.00$20.00$20.00$22.00$18.50
77Ground mounted structural beam support, W6X9 (630E06500)FT108.30$22.00$22.00$22.00$22.00$23.00$40.00
78Ground mounted structural beam support, W10X22 (630E07500)FT43$48.00$48.00$48.00$48.00$50.00$73.00
79Ground mounted structural beam support, W10X12 (630E07600)FT87.50$28.00$28.00$28.00$28.00$30.00$50.00
80Sign post reflector (630E08600)EACH22$45.00$45.00$45.00$45.00$60.00$45.00
81Breakaway structural beam connection (630E09000)EACH10$550.00$550.00$550.00$550.00$570.00$650.00
82Sign, flat sheet (630E80100)SF390.90$22.00$22.00$22.00$22.00$17.00$20.00
83Sign, ground mounted extrusheet (630E80200)SF49$30.00$30.00$30.00$30.00$32.00$30.00
84Sign, ground mounted extrusheet, as per plan (630E80201)SF185$31.00$31.00$31.00$31.00$33.00$29.00
85Ground mounted structural beam support foundation (630E84500)EACH10$1,250.00$1,250.00$1,250.00$1,250.00$1,300.00$1,140.00
86Removal of ground mounted sign and disposal (630E84900)EACH45$20.00$20.00$20.00$20.00$20.00$15.00
87Removal of ground mounted sign and reerection (630E85100)EACH5$125.00$125.00$125.00$125.00$65.00$70.00
88Removal of ground mounted major sign and reerection (630E85600)EACH1$650.00$650.00$650.00$650.00$700.00$385.00
89Removal of ground mounted post support and disposal (630E86002)EACH30$20.00$20.00$20.00$20.00$45.00$20.00
90Removal of ground mounted structural beam support (630E86102)EACH6$250.00$250.00$250.00$250.00$250.00$295.00
91Edge line, 6" (644E00104)MI1.76$5,480.00$5,480.00$3,400.00$5,480.00$5,650.00$5,480.00
92Lane line, 6" (644E00204)MI1.45$2,070.00$2,070.00$2,250.00$2,070.00$2,200.00$2,070.00
93Center line (644E00300)MI0.10$9,500.00$9,500.00$5,200.00$9,500.00$10,000$9,500.00
94Channelizing line, 12" (644E00404)FT4,506$2.40$2.40$2.80$2.40$2.75$2.40
95Stop line (644E00500)FT74$8.50$8.50$7.75$8.50$8.75$8.50
96Transverse/diagonal line (644E00700)FT204$8.25$8.25$7.75$8.25$8.50$8.25
97Chevron marking (644E00720)FT707$8.25$8.25$9.00$8.25$8.50$8.25
98Lane arrow (644E01300)EACH53$120.00$120.00$100.00$120.00$130.00$120.00
99Yield line (644E20800)FT87$12.45$12.50$8.00$12.45$13.50$12.45
100Removal of traffic signal installation (632E90100)EACH1$4,500.00$3,000.00$3,000.00$4,500.00$5,000.00$3,750.00
101Law enforcement officer with patrol car for assistance (614E11110)HR40$85.00$105.00$120.00$75.00$100.00$125.00
102Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH12$1,950.00$2,302.59$2,150.00$2,800.00$2,350.00$2,420.00
103Work zone lighting system (614E12740)EACH1$16,056$16,100$40,000$16,056$17,000$50,000
104Asphalt concrete for maintaining traffic (614E13000)CY6$275.00$325.00$350.00$850.00$200.00$900.00
105Barrier reflector, type 1, (one-way) (614E13310)EACH171$9.00$8.00$9.00$25.00$10.00$10.00
106Object marker, one way (614E13350)EACH171$35.00$13.00$35.00$40.00$37.00$19.00
107Portable changeable message sign, as per plan (614E18601)SNMT16$995.00$800.00$995.00$864.00$1,000.00$900.00
108Work zone lane line, class I, 4" (614E20000)MI1.45$620.00$620.00$830.00$620.00$700.00$1,650.00
109Work zone center line, class I (614E21000)MI0.35$2,310.00$2,310.00$1,290.00$2,310.00$2,500.00$5,075.00
110Work zone edge line, class I, 4" (614E22000)MI2.21$1,340.00$1,340.00$970.00$1,340.00$1,500.00$2,150.00
111Work zone edge line, class I, 6" (614E22010)MI1.95$1,825.00$1,825.00$970.00$1,825.00$2,000.00$2,600.00
112Work zone channelizing line, class I, 8" (614E23000)FT4,529$0.80$0.80$1.00$0.80$0.85$0.65
113Work zone dotted line, class I (614E24000)FT2,497$0.45$0.45$0.65$0.45$0.50$0.70
114Work zone transverse/diagonal line, class I (614E25000)FT201$1.20$1.20$7.00$1.20$1.25$10.00
115Work zone stop line, class I (614E26000)FT274$3.25$3.25$5.00$3.25$3.50$7.00
116Work zone arrow, class I (614E30000)EACH53$135.00$135.00$45.00$135.00$150.00$175.00
117Work zone pavement marking, misc.: chevron marking (614E98100)FT430$3.25$3.25$7.00$3.25$3.50$10.00
118Work zone pavement marking, misc.: yield line, cla (614E98100)FT269$3.25$3.25$3.00$3.25$3.50$18.00
119Pavement for maintaining traffic, class B, as per plan (615E25001)SY28$310.00$365.00$250.00$250.00$250.00$400.00
120Water (616E10000)MGAL36$1.00$85.00$1.00$1.00$1.00$100.00
121Portable barrier, unanchored (622E41100)FT8,030$20.00$24.00$17.50$20.00$19.00$28.00
122Digital speed limit (DSL) sign assembly (808E18700)SNMT8$1,250.00$800.00$1,250.00$864.00$1,400.00$950.00
123Premium for contract performance bond and for payment bond (103E05000)LS1$24,000$18,300$13,750$16,000$102,000$21,000
124Maintaining traffic (614E11000)LS1$69,049$73,575$71,750$70,000$158,300$130,000
125Field office, type B (619E16010)MNTH6$1,900.00$5,450.00$2,500.00$2,000.00$1,250.00$2,650.00
126Construction layout stakes and surveying (623E10000)LS1$51,000$40,000$17,500$27,000$20,000$40,000
127Preconstruction survey monument verification and report (623E50000)LS1$1,788.00$1,800.00$5,000.00$1,600.00$5,000.00$1,400.00
128Mobilization (624E10000)LS1$100,000$145,000$75,000$90,000$110,000$165,000
200Riprap, type D (601E11000)SY9$396.00$600.00$635.00$360.00$300.00$525.00
201Work zone lane line, class III, 6", 642 paint (614E20560)MI1.45$530.00$530.00$830.00$530.00$550.00$1,095.00
202Work zone center line, class III, 642 paint (614E21550)MI0.10$1,535.00$1,535.00$1,290.00$1,535.00$1,600.00$10,500
203Work zone edge line, class III, 6", 642 paint (614E22360)MI1.76$995.00$995.00$970.00$995.00$1,100.00$1,600.00
204Work zone channelizing line, class III, 12", 642 paint (614E23690)FT4,506$0.65$0.65$1.00$0.65$0.70$0.75
205Work zone transverse/diagonal line, class III, 642 paint (614E25620)FT204$0.90$0.90$7.00$0.90$1.00$11.25
206Work zone stop line, class III, 642 paint (614E26610)FT74$2.95$2.95$5.00$2.95$3.25$11.00
207Work zone arrow, class III, 642 paint (614E30650)EACH53$130.00$130.00$45.00$130.00$145.00$150.00
208Work zone pavement marking, misc.: chevron marking (614E98100)FT707$3.25$3.25$7.00$3.25$3.50$6.00
209Work zone pavement marking, misc.: yield line, cla (614E98100)FT87$3.25$3.25$3.00$3.25$3.50$16.50
ODOT contract 260368: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 13, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy