ODOT contract 260493 bid tabulation
CLI-US 68-09.42 (CULVERT REPLACEMENT). Let by Ohio DOT on November 12, 2026, CLI. 5 bids received; low bid $239,218 by Sunesis Construction Co, -20% against the engineer's estimate of $300,000.
- Owner
- Ohio DOT
- Letting
- 12 NOV 2026
- Pay items
- 18
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sunesis Construction Co | $239,218 | Low | -20% |
| 2 | BCC Ohio Inc | $244,826 | +2.0% | -18% |
| 3 | Madex Construction Co | $278,575 | +16% | -7.0% |
| 4 | Axis Civil Construction LLC | $291,283 | +22% | -3.0% |
| 5 | Hydratech Engineered Products LLC | $360,305 | +51% | +20% |
Engineer's estimate: $300,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunesis Construction Co | 2. BCC Ohio Inc | 3. Madex Construction Co | 4. Axis Civil Construction LLC | 5. Hydratech Engineered Products LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $28,315 | $15,087 | $28,327 | $30,000 | $52,460 |
| 2 | Removal misc.: existing concrete field paving (202E98200) | FT | 119 | $89.50 | $221.47 | $75.79 | $120.00 | $170.00 |
| 3 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $16,800 | $20,975 | $16,277 | $25,000 | $3,900.00 |
| 4 | Rock channel protection, type A with filter (601E32000) | CY | 98 | $160.00 | $196.19 | $295.59 | $195.00 | $300.00 |
| 5 | Topsoil (659E00300) | CY | 160 | $23.50 | $18.45 | $14.74 | $20.00 | $28.00 |
| 6 | Seeding and mulching (659E10000) | SY | 1,500 | $3.00 | $2.45 | $0.55 | $3.00 | $5.00 |
| 7 | Commercial fertilizer (659E20000) | TON | 0.19 | $1,400.00 | $1,022.37 | $36.84 | $450.00 | $590.00 |
| 8 | Lime (659E31000) | ACRE | 0.30 | $450.00 | $224.00 | $7.70 | $250.00 | $110.00 |
| 9 | Water (659E35000) | MGAL | 7.60 | $1.50 | $2.16 | $1.00 | $1.00 | $5.00 |
| 10 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 11 | Field painting structural steel, intermediate coat, as per plan (514E00061) | SF | 50 | $125.00 | $277.20 | $21.58 | $75.00 | $15.00 |
| 12 | Field paving of existing pipe, 135" CMP (611E96550) | FT | 119 | $375.00 | $354.57 | $627.02 | $425.00 | $1,234.00 |
| 13 | Conduit, misc.: CMP repair method A (611E97700) | SF | 500 | $106.50 | $49.62 | $86.84 | $110.00 | $35.00 |
| 14 | Conduit, misc.: CMP repair method B (611E97700) | SF | 40 | $380.50 | $321.44 | $231.58 | $580.00 | $60.00 |
| 15 | Special - fill joint with expansive polyurethane (690E99400) | LB | 10 | $886.00 | $253.20 | $78.95 | $900.00 | $1,000.00 |
| 16 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $1,720.00 | $3,022.48 | $13,105 | $3,500.00 | $30,856 |
| 17 | Maintaining traffic (614E11000) | LS | 1 | $7,450.00 | $24,974 | $19,331 | $25,000 | $15,000 |
| 18 | Mobilization (624E10000) | LS | 1 | $16,725 | $27,027 | $26,181 | $20,000 | $13,800 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way