BCC Ohio Inc: ODOT bid record
BCC Ohio Inc submitted 172 bids on Ohio DOT contracts in the data, from 13 FEB 2020 to 12 NOV 2026, and was the low bidder on 88 of them (51%). When it was not low, its total sat a median +11% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $56,023,046
- Latest bid
- 12 NOV 2026
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 19 | 8 | 42% |
| 2021 | 35 | 17 | 49% |
| 2022 | 13 | 6 | 46% |
| 2023 | 27 | 16 | 59% |
| 2024 | 30 | 15 | 50% |
| 2025 | 21 | 12 | 57% |
| 2026 | 27 | 14 | 52% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| ASD | 8 | 2 | 25% |
| District 1 | 7 | 5 | 71% |
| District 7 | 6 | 5 | 83% |
| RIC | 6 | 2 | 33% |
| HOL | 6 | 1 | 17% |
| BUT | 6 | 4 | 67% |
| District 3 | 6 | 5 | 83% |
| District 5 | 5 | 3 | 60% |
| HUR | 5 | 1 | 20% |
| CLI | 5 | 3 | 60% |
| CLE | 5 | 2 | 40% |
| HAM | 5 | 3 | 60% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 152 | 152 (100%) | $1.00 | $1.00 |
| Patching concrete structure, as per plan | 519E11101 | SF | 123 | 73 (59%) | $128.62 | $150.00 |
| Sealing concrete bridge decks with HMWM resin, as per plan | 512E10301 | SY | 96 | 54 (56%) | $15.56 | $16.50 |
| Sealing of concrete surfaces (epoxy-urethane) | 512E10100 | SY | 106 | 51 (48%) | $33.99 | $34.00 |
| Removal of existing coatings from concrete surfaces | 512E74000 | SY | 71 | 47 (66%) | $23.66 | $27.00 |
| Treating concrete bridge decks with gravity fed resin | 512E73500 | SY | 182 | 41 (23%) | $9.07 | $11.00 |
| Excavation | 203E10000 | CY | 68 | 37 (54%) | $20.44 | $27.00 |
| Pavement removed | 202E23000 | SY | 59 | 33 (56%) | $12.86 | $17.00 |
| Lime | 659E31000 | ACRE | 82 | 29 (35%) | $52.50 | $150.00 |
| Treating of concrete bridge deck with SRS | 512E10400 | SY | 59 | 27 (46%) | $7.70 | $8.25 |
| Special - pipe cleanout over 48" | 202E70130 | FT | 42 | 26 (62%) | $16.71 | $50.00 |
| Patching concrete structure | 519E11100 | SF | 31 | 26 (84%) | $127.83 | $145.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Complete General Construction Company | 47 | 15 of 47 |
| Axis Civil Construction LLC | 29 | 5 of 29 |
| Eclipse Co LLC | 27 | 2 of 27 |
| Eagle Bridge Co | 25 | 4 of 25 |
| Shelly & Sands Inc | 18 | 12 of 18 |
| Sunesis Construction Co | 18 | 4 of 18 |
| Stanley Miller Construction Company | 17 | 5 of 17 |
| Catts Construction Inc | 17 | 6 of 17 |
| DOT Construction Corp | 16 | 4 of 16 |
| Ohio Concrete Maintenance LLC | 16 | 5 of 16 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260493 | CLI | CLI-US 68-09.42 (CULVERT REPLACEMENT) | 2 of 5 | $244,826 | +2.0% |
| 12 NOV 2026 | 260497 | District 1 | D01-OL FY27 (BRIDGE REPAIR) | 1 of 4 | $1,242,291 | Low, 9.0% under the second |
| 29 OCT 2026 | 264027 | CLI | CLI-/GRE Inverts FY27 (CULVERT REPLACEMENT) | 1 of 3 | $791,078 | Low, 26% under the second |
| 29 OCT 2026 | 264028 | HAN | HAN-SR 103-12.43 (BRIDGE REPAIR) | 1 of 4 | $581,103 | Low, 2.0% under the second |
| 01 OCT 2026 | 260422 | District 3 | D03-BH FY2027 (A) (BRIDGE REPAIR) | 1 of 5 | $715,231 | Low, 6.0% under the second |
| 01 OCT 2026 | 260450 | SHE | SHE-SR 119-03.60 (BRIDGE REPAIR) | 2 of 4 | $533,901 | +4.0% |
| 17 SEP 2026 | 264022 | ASD | ASD-/WAY BH FY2027(B) (BRIDGE REPAIR) | 2 of 3 | $291,561 | +2.0% |
| 27 AUG 2026 | 260379 | BUT | BUT-SR 129-09.09/09.20 (BRIDGE REPAIR) | 1 of 5 | $635,734 | Low, 13% under the second |
| 13 AUG 2026 | 260359 | BEL | BEL-SR 148-03.12 (BRIDGE REPAIR) | 1 of 2 | $166,399 | Low, 34% under the second |
| 30 JUL 2026 | 260346 | District 2 | D02-Bridge Maintenance FY2027 (BRIDGE REPAIR) | 1 of 6 | $1,009,658 | Low, 4.0% under the second |
| 30 JUL 2026 | 260349 | HAM | HAM-Inverts FY2027 (CULVERT REPLACEMENT) | 2 of 5 | $1,923,379 | +2.0% |
| 16 JUL 2026 | 260329 | District 8 | D08-PM Bridge FY27 (BRIDGE REPAIR) | 1 of 7 | $1,950,457 | Low, 15% under the second |
| 16 JUL 2026 | 260337 | District 9 | D09-DS-FY2027 (BRIDGE REPAIR) | 3 of 3 | $1,122,216 | +45% |
| 16 JUL 2026 | 264017 | CRA | CRA-SR 100-18.38 (CULVERT REPLACEMENT) | 2 of 4 | $471,318 | +7.0% |
| 25 JUN 2026 | 260314 | RIC | RIC-US 42-03.22 (Lexington) (CULVERT REPLACEMENT) | 2 of 3 | $228,340 | +7.0% |
| 25 JUN 2026 | 260316 | District 5 | D05-FY2027 Bridge Rehab West (BRIDGE REPAIR) | 2 of 2 | $1,253,688 | +15% |
| 11 JUN 2026 | 260294 | District 5 | D05-FY2027 Bridge Rehab East (BRIDGE REPAIR) | 3 of 5 | $878,204 | +6.0% |
| 21 MAY 2026 | 260272 | POR | POR-US 224/SR 303-08.29/19.51 (CULVERT REPLACEMENT) | 1 of 3 | $707,216 | Low, 13% under the second |
| 07 MAY 2026 | 260249 | SCI | SCI-/ROS-SR 73/US 50-10.63/19.26 (BRIDGE REPAIR) | 1 of 4 | $670,731 | Low, 9.0% under the second |
| 23 APR 2026 | 264009 | MOT | MOT-/CLA BH FY26 (BRIDGE REPAIR) | 1 of 2 | $537,104 | Low, 80% under the second |
| 12 MAR 2026 | 264007 | GUE | GUE-IR 70/IR 77 VAR (BRIDGE REPAIR) | 1 of 1 | $2,277,507 | Low |
| 19 FEB 2026 | 260103 | District 1 | D01-BM FY26 (BRIDGE REPAIR) | 1 of 4 | $815,072 | Low, 7.0% under the second |
| 19 FEB 2026 | 264005 | MRW | MRW-SR 95-(01.92) (03.40) (BRIDGE REPAIR) | 1 of 2 | $686,462 | Low, 31% under the second |
| 29 JAN 2026 | 260049 | CLE | CLE-SR 132-12.64 (BRIDGE REPAIR) | 4 of 5 | $614,325 | +8.0% |
| 29 JAN 2026 | 260069 | ASD | ASD-Mohican State Park FY2026 (BRIDGE REPAIR) | 3 of 3 | $275,293 | +12% |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.