ODOT contract 260497 bid tabulation
D01-OL FY27 (BRIDGE REPAIR). Let by Ohio DOT on November 12, 2026, District 1. 4 bids received; low bid $1,242,291 by BCC Ohio Inc, -17% against the engineer's estimate of $1,500,000.
- Owner
- Ohio DOT
- Letting
- 12 NOV 2026
- Pay items
- 59
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BCC Ohio Inc | $1,242,291 | Low | -17% |
| 2 | Ohio Concrete Maintenance LLC | $1,353,009 | +9.0% | -10% |
| 3 | Eagle Bridge Co | $1,375,503 | +11% | -8.0% |
| 4 | Complete General Construction Company | $1,456,712 | +17% | -3.0% |
Engineer's estimate: $1,500,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BCC Ohio Inc | 2. Ohio Concrete Maintenance LLC | 3. Eagle Bridge Co | 4. Complete General Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $858.00 | $5,000.00 | $500.00 | $1,500.00 |
| 2 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 3 | Partial depth pavement repair (441) (251E01000) | SY | 3,411 | $47.25 | $50.00 | $49.00 | $45.00 |
| 4 | Pavement repair (253E02000) | CY | 57 | $493.50 | $525.00 | $437.00 | $470.00 |
| 5 | Pavement repair (253E02000) | CY | 60 | $493.50 | $525.00 | $437.00 | $470.00 |
| 6 | Pavement planing, asphalt concrete, 1 1/2" (254E01000) | SY | 2,859 | $6.93 | $7.35 | $4.50 | $6.60 |
| 7 | Tack coat (407E10000) | GAL | 60 | $1.05 | $1.25 | $5.00 | $1.00 |
| 8 | Non-tracking tack coat (407E20000) | GAL | 243 | $1.05 | $1.25 | $5.00 | $1.00 |
| 9 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 119 | $472.50 | $500.00 | $349.00 | $450.00 |
| 10 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 30 | $472.50 | $500.00 | $626.00 | $450.00 |
| 11 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 56 | $89.25 | $120.00 | $115.00 | $90.00 |
| 12 | Increased barrier delineation (614E11630) | FT | 400 | $5.06 | $2.25 | $2.00 | $1.80 |
| 13 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 4 | $1,948.50 | $2,300.00 | $2,100.00 | $2,100.00 |
| 14 | Work zone speed limit sign (614E12470) | EACH | 4 | $194.52 | $150.00 | $130.00 | $127.50 |
| 15 | Barrier reflector, type 1 (one way) (614E13310) | EACH | 41 | $13.95 | $13.00 | $12.00 | $10.75 |
| 16 | Object marker, one way (614E13350) | EACH | 41 | $24.42 | $25.00 | $18.00 | $21.00 |
| 17 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $891.00 | $1,200.00 | $900.00 | $1,000.00 |
| 18 | Work zone center line, class II (614E21400) | MI | 0.81 | $2,336.25 | $2,500.00 | $2,225.00 | $2,225.00 |
| 19 | Work zone edge line, class I, 6", 873 (614E22326) | MI | 3.56 | $12,962 | $14,000 | $12,350 | $12,350 |
| 20 | Work zone dotted line, class I, 6", 873 (614E24122) | FT | 5,833 | $1.88 | $2.10 | $1.80 | $1.80 |
| 21 | Water (616E10000) | MGAL | 2 | $25.80 | $10.00 | $1.00 | $100.00 |
| 22 | Compacted aggregate (617E10100) | CY | 150 | $120.03 | $120.00 | $150.00 | $125.00 |
| 23 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 8,578 | $1.22 | $1.50 | $1.75 | $0.79 |
| 24 | Portable barrier, unanchored (622E41100) | FT | 1,960 | $23.38 | $25.00 | $25.00 | $22.50 |
| 25 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 4 | $872.25 | $850.00 | $700.00 | $700.00 |
| 26 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 985 | $10.45 | $12.00 | $15.25 | $15.25 |
| 27 | Special - patching concrete bridge deck (519E12510) | SY | 12 | $747.25 | $600.00 | $925.00 | $925.00 |
| 28 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 985 | $10.45 | $12.00 | $15.25 | $15.25 |
| 29 | Special - patching concrete bridge deck (519E12510) | SY | 12 | $747.25 | $600.00 | $925.00 | $925.00 |
| 30 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 200 | $11.88 | $18.00 | $15.25 | $15.25 |
| 31 | 2" deep joint sealer (516E31010) | FT | 96 | $28.44 | $28.00 | $20.00 | $25.50 |
| 32 | Deep beam bridge retrofit railing (517E75600) | FT | 211 | $144.38 | $155.00 | $137.50 | $137.50 |
| 33 | Special - steel drip strip (518E22300) | FT | 262 | $18.56 | $29.00 | $18.00 | $15.50 |
| 34 | Patching concrete structure (519E11100) | SF | 58 | $187.36 | $150.00 | $225.00 | $225.00 |
| 35 | Latex modified concrete overlay using hydrodemolition (848E10100) | SY | 563 | $182.24 | $180.00 | $225.00 | $190.00 |
| 36 | Surface preparation using hydrodemolition (848E20000) | SY | 563 | $72.61 | $80.00 | $110.00 | $185.00 |
| 37 | Latex modified concrete overlay (variable thickness), material only (848E30100) | CY | 11 | $1,177.50 | $1,100.00 | $875.00 | $785.00 |
| 38 | Hand chipping (848E50000) | SY | 20 | $255.75 | $145.00 | $100.00 | $110.00 |
| 39 | Test slab (848E50100) | LS | 1 | $7,323.00 | $5,500.00 | $500.00 | $500.00 |
| 40 | Existing concrete overlay removed (T = 1.75") (848E50320) | SY | 563 | $14.16 | $18.00 | $22.00 | $20.00 |
| 41 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 364 | $10.43 | $18.00 | $15.25 | $15.25 |
| 42 | 2" deep joint sealer (516E31010) | FT | 131 | $28.44 | $27.00 | $20.00 | $25.50 |
| 43 | Deep beam bridge retrofit railing (517E75600) | FT | 211 | $144.38 | $155.00 | $137.50 | $137.50 |
| 44 | Special - steel drip strip (518E22300) | FT | 262 | $18.56 | $29.00 | $18.00 | $15.50 |
| 45 | Latex modified concrete overlay using hydrodemolition (848E10100) | SY | 768 | $169.57 | $175.00 | $200.00 | $190.00 |
| 46 | Surface preparation using hydrodemolition (848E20000) | SY | 768 | $55.70 | $67.00 | $95.00 | $185.00 |
| 47 | Latex modified concrete overlay (variable thickness), material only (848E30100) | CY | 15 | $1,177.50 | $1,100.00 | $875.00 | $785.00 |
| 48 | Hand chipping (848E50000) | SY | 27 | $245.19 | $145.00 | $100.00 | $110.00 |
| 49 | Test slab (848E50100) | LS | 1 | $7,323.00 | $5,500.00 | $500.00 | $500.00 |
| 50 | Existing concrete overlay removed (T = 1.75") (848E50320) | SY | 768 | $12.69 | $18.00 | $22.00 | $20.00 |
| 51 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 1,840 | $10.42 | $12.00 | $15.25 | $15.25 |
| 52 | Patching concrete structure, as per plan (519E11101) | SF | 77 | $187.36 | $150.00 | $225.00 | $225.00 |
| 53 | Special - patching concrete bridge deck (519E12510) | SY | 100 | $573.45 | $485.00 | $600.00 | $750.00 |
| 54 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $5,000.00 | $8,500.00 | $7,500.00 | $4,000.00 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,276 | $22,000 | $27,500 | $10,000 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $50,120 | $70,000 | $82,500 | $60,000 |
| 57 | Mobilization (624E10000) | LS | 1 | $59,948 | $95,000 | $65,000 | $72,500 |
| 100 | Latex modified concrete overlay (variable thickness), material only, as per plan (848E30101) | CY | 12 | $1,177.50 | $1,000.00 | $325.00 | $1,900.00 |
| 101 | Latex modified concrete overlay (variable thickness), material only, as per plan (848E30101) | CY | 12 | $1,177.50 | $1,000.00 | $325.00 | $1,900.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 12, 2026. Compiled by Mirage Metrics.