ODOT letting results, June 11, 2026
21 contracts let by Ohio DOT on June 11, 2026, $27,842,854 in low bids, a median of 2 bidders per contract. On the 21 with an engineer's estimate, the low bid came in under it 10 times; median low bid 0.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 21
- Low bids, total
- $27,842,854
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 260282 | ATB-/TRU-SR 7/VAR-18.62/VAR (PART 1, 2, 3) (BRIDGE REPAIR) | ATB | 4 | A P O'Horo Company | $3,814,000 | $3,899,665 | +2.0% | -14% | ODOT |
| 260287 | FUL-US 20-19.75 Roundabout (INTERSECTION) | FUL | 3 | Miller Bros Const Inc | $3,332,719 | $3,682,638 | +10% | -12% | ODOT |
| 260285 | CUY-SR 237-06.35 (FOUR LANE RESURFACING) | CUY | 3 | Karvo Companies Inc | $3,245,457 | $4,061,100 | +25% | +15% | ODOT |
| 260299 | D11-PM-FY2027(B) (PAVEMENT MARKING) | District 11 | 3 | The Aero-Mark Company LLC | $2,060,000 | $2,435,585 | +18% | -7.0% | ODOT |
| 260298 | D08-GR FY2027 (GUARDRAIL REBUILDING) | District 8 | 1 | Lake Erie Construction Company | $1,925,725 | +4.0% | ODOT | ||
| 260300 | FRA-GR-FY2027 (GUARDRAIL REBUILDING) | FRA | 2 | M P Dory Co | $1,858,557 | $2,305,625 | +24% | -6.0% | ODOT |
| 260297 | D07-TSG & Lighting MAINT FY27 (SIGNALIZATION) | District 7 | 1 | Capital Electric Line Builders Inc | $1,809,897 | +20% | ODOT | ||
| 260291 | SCI-SR 335-01.72 (CULVERT REPLACEMENT) | SCI | 2 | Turn-Key Tunneling Inc | $1,341,422 | $1,365,189 | +2.0% | +18% | ODOT |
| 260296 | D07-GR Maint FY27 (GUARDRAIL REBUILDING) | District 7 | 1 | Lake Erie Construction Company | $1,068,595 | +3.0% | ODOT | ||
| 260283 | COL-SR 45/SR 164-15.47/VAR (TWO LANE RESURFACING) | COL | 2 | Shelly & Sands Inc | $1,052,395 | $1,402,791 | +33% | 0.0% | ODOT |
| 260293 | CUY-DMS & QWS FY2026 (SIGNALIZATION) | CUY | 3 | Ruhlin Company | $998,118 | $1,233,133 | +24% | 0.0% | ODOT |
| 260288 | HAM-/CLE-US 52-35.22/00.00 (SPOT PATCHING / PAVEMENT REPAIR) | HAM | 2 | John R Jurgensen Company | $908,492 | $1,014,655 | +12% | +26% | ODOT |
| 260295 | D06-GR-FY2027 (GUARDRAIL REBUILDING) | District 6 | 2 | Lake Erie Construction Company | $836,420 | $899,476 | +8.0% | 0.0% | ODOT |
| 260294 | D05-FY2027 Bridge Rehab East (BRIDGE REPAIR) | District 5 | 5 | Twin Rivers Construction Co | $824,858 | $874,700 | +6.0% | -28% | ODOT |
| 260284 | COL-SR 9/SR 14-14.23/03.65 (TWO LANE RESURFACING) | COL | 4 | Shelly & Sands Inc | $737,081 | $825,455 | +12% | -8.0% | ODOT |
| 260301 | LUC-/OTT-SR 65/SR 163 FY2027 Operations (MISCELLANEOUS) | LUC | 1 | Dependable Tree and Maintenance Services LLC | $698,680 | -1.0% | ODOT | ||
| 260286 | FUL-US 20-15.07 Culvert Repl (CULVERT REPLACEMENT) | FUL | 3 | Eclipse Co LLC | $474,496 | $491,900 | +4.0% | -7.0% | ODOT |
| 260302 | MER-/LOG-SR 49/SR 559-23.45/03.53 (MINOR RECONSTRUCTION) | MER | 2 | Shelly Company | $422,905 | $427,465 | +1.0% | +45% | ODOT |
| 260289 | PER-CR VAR GR FY2027 (GUARDRAIL REBUILDING) | PER | 3 | PDK Construction Inc | $249,367 | $249,745 | 0.0% | +18% | ODOT |
| 268011 | HEN-US 24-13.83 Collision Repair (BRIDGE REPAIR) | HEN | 2 | Eius Company | $93,682 | $134,661 | +44% | -1.0% | ODOT |
| 260290 | PER-CR VAR PM FY2027 (PAVEMENT MARKING) | PER | 3 | Griffin Pavement Striping LLC | $89,988 | $94,305 | +5.0% | -23% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.