ODOT contract 260286 bid tabulation
FUL-US 20-15.07 Culvert Repl (CULVERT REPLACEMENT). Let by Ohio DOT on June 11, 2026, FUL. 3 bids received; low bid $474,496 by Eclipse Co LLC, -7.0% against the engineer's estimate of $510,000.
- Owner
- Ohio DOT
- Letting
- 11 JUN 2026
- Pay items
- 53
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eclipse Co LLC | $474,496 | Low | -7.0% |
| 2 | Fenson Contracting LLC | $491,900 | +4.0% | -4.0% |
| 3 | Ebony Construction Co | $505,555 | +7.0% | -1.0% |
Engineer's estimate: $510,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eclipse Co LLC | 2. Fenson Contracting LLC | 3. Ebony Construction Co |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $5,000.00 | $3,500.00 | $5,305.02 |
| 2 | Pavement removed (202E23000) | SY | 235 | $38.01 | $28.00 | $18.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 222 | $30.15 | $35.00 | $25.00 |
| 4 | Pipe removed, over 24" diameter (202E35200) | FT | 70 | $26.35 | $80.00 | $83.00 |
| 5 | Guardrail removed (202E38000) | FT | 437.50 | $6.00 | $5.00 | $6.00 |
| 6 | Anchor assembly removed, type E (202E42010) | EACH | 3 | $185.00 | $250.00 | $261.00 |
| 7 | Anchor assembly removed, type T (202E42040) | EACH | 5 | $135.00 | $250.00 | $208.50 |
| 8 | Excavation (203E10000) | CY | 144 | $13.38 | $30.00 | $54.50 |
| 9 | Embankment (203E20000) | CY | 258 | $12.43 | $30.00 | $38.00 |
| 10 | Subgrade compaction (204E10000) | SY | 354 | $1.60 | $4.00 | $2.25 |
| 11 | Linear grading (209E60500) | MI | 0.09 | $1,877.44 | $7,500.00 | $3,977.00 |
| 12 | Monument assembly, type D (623E38550) | EACH | 8 | $806.38 | $1,500.00 | $1,160.00 |
| 13 | Reference monument, type A (623E40500) | EACH | 1 | $700.95 | $1,000.00 | $576.00 |
| 14 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 114 | $99.95 | $175.00 | $120.50 |
| 15 | Topsoil furnished and placed (653E10000) | CY | 142 | $90.58 | $60.00 | $84.00 |
| 16 | Seeding and mulching (659E10000) | SY | 1,279 | $1.28 | $4.25 | $2.70 |
| 17 | Repair seeding and mulching (659E14000) | SY | 64 | $0.80 | $0.80 | $2.70 |
| 18 | Inter-seeding (659E15000) | SY | 64 | $0.50 | $0.50 | $3.00 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.19 | $800.00 | $800.00 | $850.00 |
| 20 | Water (659E35000) | MGAL | 7 | $0.50 | $0.50 | $1.00 |
| 21 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 |
| 22 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $9,868.49 | $8,850.00 | $36,000 |
| 23 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $2,201.34 | $29,250 | $6,565.00 |
| 24 | Epoxy coated steel reinforcement (509E10000) | LB | 3,973 | $2.81 | $3.25 | $2.50 |
| 25 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 20 | $1,210.49 | $1,775.00 | $1,700.00 |
| 26 | Class QC1 concrete, footing (511E46510) | CY | 32 | $856.20 | $525.00 | $1,200.00 |
| 27 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 74 | $10.37 | $35.00 | $20.00 |
| 28 | Porous backfill with geotextile fabric (518E21200) | CY | 26 | $97.15 | $150.00 | $180.00 |
| 29 | Concrete masonry (602E20000) | CY | 30.20 | $1,620.63 | $1,630.00 | $1,500.00 |
| 30 | 6" conduit, type E (611E01400) | FT | 50 | $47.52 | $30.00 | $14.00 |
| 31 | 6" conduit, type F (611E01500) | FT | 50 | $47.52 | $30.00 | $14.00 |
| 32 | 8" conduit, type E (611E02500) | FT | 97 | $52.12 | $37.00 | $17.00 |
| 33 | 8" conduit, type F (611E02600) | FT | 50 | $51.16 | $33.00 | $18.00 |
| 34 | 12" conduit, type C (611E04600) | FT | 192 | $99.36 | $60.00 | $60.00 |
| 35 | 96" conduit, type A, 706.02, 707.85 (611E30000) | FT | 89 | $1,015.36 | $1,200.00 | $1,300.00 |
| 36 | Catch basin, no. 2-2B (611E98470) | EACH | 3 | $3,902.86 | $2,800.00 | $2,200.00 |
| 37 | Inspection well (611E99720) | EACH | 1 | $829.24 | $1,050.00 | $1,800.00 |
| 38 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 61 | $335.00 | $305.00 | $300.00 |
| 39 | Aggregate base (304E20000) | CY | 58 | $42.01 | $95.00 | $119.00 |
| 40 | Tack coat (407E10000) | GAL | 39 | $2.50 | $3.00 | $3.00 |
| 41 | Stabilized crushed aggregate (411E10000) | CY | 11 | $100.11 | $125.00 | $173.00 |
| 42 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 20 | $475.00 | $650.00 | $450.00 |
| 43 | Compacted aggregate (617E10100) | CY | 7 | $116.91 | $125.00 | $148.50 |
| 44 | Longitudinal joint adhesive (875E10000) | LB | 19 | $65.00 | $32.00 | $70.00 |
| 45 | Raised pavement marker removed (621E54000) | EACH | 1 | $1,314.25 | $15.00 | $4.50 |
| 46 | Traffic compacted surface, type A or B (410E12000) | CY | 10 | $400.00 | $125.00 | $250.00 |
| 47 | Asphalt concrete for maintaining traffic (614E13000) | CY | 5 | $800.00 | $675.00 | $2,100.00 |
| 48 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,126.59 | $1,350.00 | $1,200.00 |
| 49 | Water (616E10000) | MGAL | 2 | $0.50 | $50.00 | $1.50 |
| 50 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,832.51 | $6,500.00 | $4,280.00 |
| 51 | Maintaining traffic (614E11000) | LS | 1 | $7,075.32 | $10,750 | $6,690.00 |
| 52 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,263.09 | $10,750 | $14,400 |
| 53 | Mobilization (624E10000) | LS | 1 | $72,722 | $22,000 | $16,800 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 11, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way