Fenson Contracting LLC: ODOT bid record
Fenson Contracting LLC submitted 23 bids on Ohio DOT contracts in the data, from 13 APR 2023 to 01 OCT 2026, and was the low bidder on 6 of them (26%). When it was not low, its total sat a median +28% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $7,653,587
- Latest bid
- 01 OCT 2026
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2023 | 1 | 1 | 100% |
| 2024 | 6 | 1 | 17% |
| 2025 | 5 | 0 | 0% |
| 2026 | 11 | 4 | 36% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| ALL | 6 | 3 | 50% |
| PUT | 3 | 2 | 67% |
| WYA | 2 | 0 | 0% |
| AUG | 2 | 0 | 0% |
| PAU | 2 | 0 | 0% |
| District 7 | 1 | 1 | 100% |
| MIA | 1 | 0 | 0% |
| WOO | 1 | 0 | 0% |
| WIL | 1 | 0 | 0% |
| HAN | 1 | 0 | 0% |
| VAN | 1 | 0 | 0% |
| HAR | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 24 | 24 (100%) | $1.00 | $1.00 |
| Water | 659E35000 | MGAL | 23 | 17 (74%) | $1.00 | $1.00 |
| Repair seeding and mulching | 659E14000 | SY | 17 | 10 (59%) | $1.20 | $1.25 |
| Non-tracking tack coat | 407E20000 | GAL | 21 | 8 (38%) | $3.00 | $3.25 |
| Commercial fertilizer | 659E20000 | TON | 20 | 8 (40%) | $850.00 | $850.00 |
| Lime | 659E31000 | ACRE | 13 | 8 (62%) | $35.00 | $150.00 |
| Ground mounted support, no. 3 post | 630E03100 | FT | 13 | 8 (62%) | $16.50 | $15.20 |
| Proof rolling | 204E45000 | HR | 10 | 8 (80%) | $150.00 | $219.05 |
| Embankment | 203E20000 | CY | 21 | 7 (33%) | $21.55 | $25.00 |
| Asphalt concrete base, PG64-22, (449) | 301E56000 | CY | 17 | 7 (41%) | $235.00 | $300.00 |
| Inter-seeding | 659E15000 | SY | 10 | 7 (70%) | $1.00 | $1.00 |
| Pavement removed | 202E23000 | SY | 21 | 5 (24%) | $14.00 | $17.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Vernon Nagel Inc | 8 | 4 of 8 |
| Advanced Excavating & Demolition LLC | 7 | 4 of 7 |
| Sand Ridge Excavating | 4 | 2 of 4 |
| Miller Contracting Group Inc | 4 | 2 of 4 |
| Helms and Sons Excavating | 4 | 1 of 4 |
| BCC Ohio Inc | 3 | 2 of 3 |
| Crawford Construction Company Inc | 3 | 0 of 3 |
| D L Smith Concrete LLC | 3 | 2 of 3 |
| Eclipse Co LLC | 3 | 1 of 3 |
| Madex Construction Co | 3 | 0 of 3 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 01 OCT 2026 | 260433 | PUT | PUT-SR 115-05.23 AND VARIOUS (CULVERT REPLACEMENT) | 1 of 6 | $2,035,569 | Low, 6.0% under the second |
| 30 JUL 2026 | 260341 | ALL | ALL-Delphos S. Main St. Trail (SIDEWALK) | 1 of 5 | $466,218 | Low, 0.0% under the second |
| 11 JUN 2026 | 260286 | FUL | FUL-US 20-15.07 Culvert Repl (CULVERT REPLACEMENT) | 2 of 3 | $491,900 | +4.0% |
| 07 MAY 2026 | 260226 | ALL | ALL-SR 117-10.78 (INTERSECTION) | 1 of 3 | $2,424,191 | Low, 5.0% under the second |
| 07 MAY 2026 | 260239 | HAR | HAR-US 68/SR 31 Roundabout (INTERSECTION) | 3 of 3 | $4,934,520 | +37% |
| 23 APR 2026 | 260202 | HAN | HAN-McComb Ped Improvements (BIKEWAYS) | 2 of 2 | $229,009 | +11% |
| 23 APR 2026 | 260216 | VAN | VAN-US 224-10.88 (PART 1, PART 2 AND PART 3) (INTERSECTION) | 2 of 2 | $7,206,817 | +12% |
| 09 APR 2026 | 260187 | WYA | WYA-Carey SRTS Phase 2 (SIDEWALK) | 4 of 6 | $344,718 | +32% |
| 09 APR 2026 | 264008 | PUT | PUT-SR 190-05.71 (CULVERT REPLACEMENT) | 1 of 3 | $598,999 | Low, 40% under the second |
| 26 MAR 2026 | 260143 | AUG | AUG-SR 501/SR 198-02.32/02.36 (INTERSECTION) | 2 of 2 | $2,166,924 | +28% |
| 26 MAR 2026 | 260166 | ALL | ALL-Lafayette Improvements (TWO LANE RESURFACING) | 2 of 2 | $1,581,469 | +33% |
| 26 JUN 2025 | 250324 | PUT | PUT-Ottawa Ped. Improvements (SPOT SAFETY) | 2 of 4 | $281,751 | +52% |
| 08 MAY 2025 | 250258 | PAU | PAU-SR 637-12.27 (SLIDE REPAIR) | 3 of 6 | $827,612 | +12% |
| 08 MAY 2025 | 254016 | PAU | PAU-SR 111-01.65 (CULVERT REPLACEMENT) | 3 of 3 | $349,564 | +10% |
| 24 APR 2025 | 250209 | ALL | ALL-Harrod Improvements (MINOR RECONSTRUCTION) | 2 of 6 | $2,027,885 | +32% |
| 13 FEB 2025 | 254006 | ALL | ALL-SR 117-03.47/04.64 (CULVERT REPLACEMENT) | 3 of 4 | $918,215 | +5.0% |
| 19 DEC 2024 | 240591 | AUG | AUG-SR 274-04.31 (CULVERT REPLACEMENT) | 4 of 6 | $273,268 | +57% |
| 14 NOV 2024 | 244025 | WIL | WIL-US 6-11.07 Bridge Repl. (CULVERT REPLACEMENT) | 2 of 5 | $687,764 | 0.0% |
| 25 JUL 2024 | 240382 | WYA | WYA-US 23-06.63 (INTERSECTION) | 5 of 6 | $384,988 | +37% |
| 18 APR 2024 | 244009 | District 7 | D07-CR-FY24 (CULVERT REPLACEMENT) | 1 of 1 | $1,707,790 | Low |
| 18 APR 2024 | 244010 | MIA | MIA-/MER-IR 75/SR 119-16.91/13.74 (CULVERT REPLACEMENT) | 3 of 3 | $722,461 | +57% |
| 18 APR 2024 | 244011 | WOO | WOO-SR 582-16.35 Bridge Repl. (CULVERT REPLACEMENT) | 3 of 4 | $348,532 | +7.0% |
| 13 APR 2023 | 238000 | ALL | ALL-SRTS Delphos (SIDEWALK) | 1 of 2 | $420,820 | Low, 17% under the second |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.