ODOT contract 260239 bid tabulation
HAR-US 68/SR 31 Roundabout (INTERSECTION). Let by Ohio DOT on May 7, 2026, HAR. 3 bids received; low bid $3,596,050 by Eagle Bridge Co, -3.5% against the engineer's estimate of $3,725,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 237
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eagle Bridge Co | $3,596,050 | Low | -3.0% |
| 2 | Helms and Sons Excavating | $3,651,725 | +2.0% | -2.0% |
| 3 | Fenson Contracting LLC | $4,934,520 | +37% | +32% |
Engineer's estimate: $3,725,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Bridge Co | 2. Helms and Sons Excavating | 3. Fenson Contracting LLC |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $45,000 | $50,000 |
| 2 | Pavement removed (202E23000) | SY | 7,404 | $11.50 | $11.50 | $16.00 |
| 3 | Walk removed (202E30000) | SF | 10,638 | $2.00 | $3.00 | $2.50 |
| 4 | Curb removed (202E32000) | FT | 1,018 | $6.00 | $7.00 | $10.00 |
| 5 | Curb and gutter removed (202E32500) | FT | 414 | $7.00 | $12.00 | $10.00 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 1,559 | $30.00 | $23.00 | $65.00 |
| 7 | Guardrail removed (202E38000) | FT | 87 | $5.00 | $24.00 | $3.00 |
| 8 | Manhole removed (202E58000) | EACH | 2 | $700.00 | $1,200.00 | $1,800.00 |
| 9 | Catch basin removed (202E58100) | EACH | 15 | $300.00 | $700.00 | $1,200.00 |
| 10 | Regulated underground storage tank removed (202E67000) | EACH | 3 | $16,500 | $1,350.00 | $20,000 |
| 11 | Removal misc.: inspection well (202E98100) | EACH | 2 | $200.00 | $550.00 | $3,500.00 |
| 12 | Removal misc.: conduit (202E98200) | FT | 60 | $5.00 | $34.00 | $30.00 |
| 13 | Removal misc.: removal of modular block wall (202E98200) | FT | 172 | $15.00 | $6.00 | $35.00 |
| 14 | Excavation (203E10000) | CY | 4,558 | $30.00 | $23.00 | $30.00 |
| 15 | Embankment (203E20000) | CY | 1,040 | $25.00 | $21.00 | $12.00 |
| 16 | Embankment, as per plan (203E20001) | CY | 15 | $40.00 | $66.00 | $175.00 |
| 17 | Subgrade compaction (204E10000) | SY | 3,153 | $4.00 | $2.00 | $3.00 |
| 18 | Excavation of subgrade (204E13000) | CY | 403 | $27.00 | $26.00 | $22.00 |
| 19 | Granular material, type B (204E30010) | CY | 403 | $70.00 | $54.00 | $60.00 |
| 20 | Proof rolling (204E45000) | HR | 1 | $175.00 | $150.00 | $200.00 |
| 21 | Geotextile fabric (204E50000) | SY | 688 | $3.00 | $4.00 | $2.25 |
| 22 | Geogrid (204E51000) | SY | 462 | $3.50 | $5.00 | $3.50 |
| 23 | Cement (206E10500) | TON | 169 | $226.00 | $238.00 | $215.00 |
| 24 | Curing coat (206E11000) | SY | 5,623 | $1.30 | $1.50 | $1.50 |
| 25 | Cement stabilized subgrade, 14 inches deep (206E15020) | SY | 5,623 | $8.00 | $5.00 | $18.00 |
| 26 | Test rolling (206E20000) | HR | 3 | $175.00 | $150.00 | $150.00 |
| 27 | Guardrail, type MGS (606E15050) | FT | 43.75 | $60.00 | $62.00 | $70.00 |
| 28 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,760.00 | $1,850.00 | $2,000.00 |
| 29 | Bridge terminal assembly, type 1 (606E35000) | EACH | 1 | $3,100.00 | $3,275.00 | $3,500.00 |
| 30 | 4" concrete walk, as per plan (608E10001) | SF | 7,202 | $6.00 | $6.00 | $9.50 |
| 31 | 8" concrete walk, as per plan (608E15001) | SF | 4,224 | $10.00 | $9.00 | $12.00 |
| 32 | Curb ramp, as per plan (608E52001) | SF | 1,233 | $10.00 | $17.00 | $15.00 |
| 33 | Curb ramp, as per plan (608E52001) | SF | 653 | $13.00 | $21.00 | $38.00 |
| 34 | Special - concrete parking block (690E50500) | EACH | 4 | $400.00 | $450.00 | $350.00 |
| 35 | Special - bollard (690E50600) | EACH | 10 | $1,140.00 | $1,425.00 | $1,300.00 |
| 36 | Special - work involving petroleum contaminated soil (690E65016) | TON | 613 | $100.00 | $110.00 | $110.00 |
| 37 | Crushed aggregate slope protection, as per plan (601E20011) | CY | 75 | $175.00 | $143.00 | $185.00 |
| 38 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 2.70 | $225.00 | $450.00 | $300.00 |
| 39 | Topsoil (659E00300) | CY | 455 | $50.00 | $33.00 | $55.00 |
| 40 | Seeding and mulching, class 1 (659E00500) | SY | 4,100 | $3.00 | $2.00 | $2.25 |
| 41 | Repair seeding and mulching (659E14000) | SY | 205 | $3.00 | $2.00 | $1.00 |
| 42 | Inter-seeding (659E15000) | SY | 205 | $2.00 | $2.00 | $0.70 |
| 43 | Commercial fertilizer (659E20000) | TON | 0.60 | $2,000.00 | $900.00 | $850.00 |
| 44 | Lime (659E31000) | ACRE | 0.85 | $1.00 | $50.00 | $5.00 |
| 45 | Water (659E35000) | MGAL | 22.10 | $20.00 | $0.95 | $0.50 |
| 46 | Special - - black landscaping rock (690E98300) | SY | 223 | $3.50 | $4.00 | $38.00 |
| 47 | Storm water pollution prevention plan (832E15000) | LS | 1 | $4,000.00 | $1,500.00 | $3,500.00 |
| 48 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $17,500 | $20,000 | $67,000 |
| 49 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $6,500.00 | $5,750.00 | $7,500.00 |
| 50 | Erosion control (832E30000) | EACH | 4,500 | $1.00 | $1.00 | $1.00 |
| 51 | Concrete masonry (602E20000) | CY | 2.90 | $2,250.00 | $4,130.00 | $5,000.00 |
| 52 | 4" unclassified pipe underdrains (605E05200) | FT | 120 | $12.00 | $14.00 | $26.00 |
| 53 | 4" base pipe underdrains (605E06000) | FT | 1,661 | $12.00 | $14.00 | $26.00 |
| 54 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 280 | $22.00 | $47.00 | $65.00 |
| 55 | 6" conduit, type B (611E00900) | FT | 7 | $90.00 | $195.00 | $125.00 |
| 56 | 6" conduit, type C (611E01100) | FT | 25 | $75.00 | $108.00 | $125.00 |
| 57 | 8" conduit, type B (611E01800) | FT | 10 | $90.00 | $157.00 | $250.00 |
| 58 | 8" conduit, type E (611E02500) | FT | 4 | $125.00 | $267.00 | $250.00 |
| 59 | 12" conduit, type B (611E04400) | FT | 602 | $100.00 | $141.00 | $200.00 |
| 60 | 12" conduit, type C (611E04600) | FT | 93 | $85.00 | $107.00 | $150.00 |
| 61 | 15" conduit, type B (611E05900) | FT | 8 | $250.00 | $160.00 | $500.00 |
| 62 | 15" conduit, type C (611E06100) | FT | 5 | $375.00 | $226.00 | $500.00 |
| 63 | 18" conduit, type B (611E07400) | FT | 554 | $160.00 | $154.00 | $220.00 |
| 64 | 18" conduit, type C (611E07600) | FT | 40 | $120.00 | $171.00 | $155.00 |
| 65 | 18" conduit, type D (611E07900) | FT | 141 | $100.00 | $117.00 | $155.00 |
| 66 | 24" conduit, type B (611E10400) | FT | 321 | $225.00 | $200.00 | $220.00 |
| 67 | 24" conduit, type C (611E10600) | FT | 90 | $165.00 | $123.00 | $170.00 |
| 68 | Conduit, misc.: type E for drainage discharge cont (611E97400) | FT | 100 | $25.00 | $140.00 | $30.00 |
| 69 | Catch basin, no. 3 (611E98150) | EACH | 6 | $4,750.00 | $4,900.00 | $6,200.00 |
| 70 | Catch basin, no. 3A (611E98180) | EACH | 6 | $3,750.00 | $3,500.00 | $5,200.00 |
| 71 | Catch basin, no. 6 (611E98370) | EACH | 7 | $3,150.00 | $3,475.00 | $5,200.00 |
| 72 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $2,500.00 | $2,750.00 | $4,000.00 |
| 73 | Catch basin, misc.: CB-3MH (611E98690) | EACH | 1 | $9,000.00 | $13,750 | $25,000 |
| 74 | Manhole, no. 3 (611E99574) | EACH | 17 | $4,500.00 | $4,750.00 | $7,500.00 |
| 75 | Manhole, no. 3 with 96" base I.D. and 9" weir (611E99584) | EACH | 1 | $10,000 | $17,000 | $20,000 |
| 76 | Inspection well (611E99720) | EACH | 2 | $1,500.00 | $1,250.00 | $1,500.00 |
| 77 | Manufactured water quality structure, type 3 (895E10030) | EACH | 1 | $35,000 | $47,750 | $35,000 |
| 78 | Pavement planing, asphalt concrete (1.5" thick) (254E01000) | SY | 813 | $10.00 | $8.00 | $10.00 |
| 79 | Patching planed surface (254E01600) | SY | 40 | $40.00 | $56.00 | $40.00 |
| 80 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,066 | $205.00 | $219.00 | $235.00 |
| 81 | Aggregate base (304E20000) | CY | 1,796 | $90.00 | $76.00 | $85.00 |
| 82 | Non-tracking tack coat (407E20000) | GAL | 716 | $3.00 | $3.00 | $3.00 |
| 83 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 47 | $510.00 | $415.00 | $610.00 |
| 84 | Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700) | CY | 75 | $390.00 | $320.00 | $465.00 |
| 85 | Asphalt concrete surface course, 12.5 MM, type A (448) (442E20000) | CY | 194 | $365.00 | $295.00 | $435.00 |
| 86 | Asphalt concrete intermediate course, 19 MM, type A (448) (442E20200) | CY | 323 | $250.00 | $245.00 | $300.00 |
| 87 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 44 | $310.00 | $345.00 | $370.00 |
| 88 | Asphalt concrete intermediate course, 19 MM, type A (449) (442E22400) | CY | 15 | $430.00 | $395.00 | $500.00 |
| 89 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 61 | $70.00 | $77.00 | $95.00 |
| 90 | 8" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011) | SY | 413 | $83.00 | $96.00 | $95.00 |
| 91 | 8" non-reinforced concrete pavement, class QC MS, as per plan (452E12051) | SY | 326 | $90.00 | $100.00 | $100.00 |
| 92 | 10" non-reinforced concrete pavement, class QC 1P, as per plan (452E14011) | SY | 585 | $100.00 | $138.00 | $150.00 |
| 93 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 1,113 | $40.00 | $39.00 | $36.00 |
| 94 | Curb, type 6, as per plan (609E26001) | FT | 1,489 | $21.00 | $25.00 | $30.00 |
| 95 | Curb, type 7, as per plan (609E28001) | FT | 205 | $26.00 | $39.00 | $30.00 |
| 96 | Combination curb and gutter, type 9, as per plan (609E31001) | FT | 261 | $32.00 | $37.00 | $48.00 |
| 97 | Combination curb and gutter, type 9, as per plan (609E31001) | FT | 375 | $40.00 | $38.00 | $48.00 |
| 98 | Curb, type 10, as per plan (609E33001) | FT | 142 | $30.00 | $36.00 | $37.00 |
| 99 | Curb, type 10, as per plan (609E33001) | FT | 356 | $30.00 | $34.00 | $37.00 |
| 100 | 6" concrete traffic island, as per plan (609E54001) | SY | 130 | $125.00 | $102.00 | $80.00 |
| 101 | Pipe removed, 24" and under (202E35100) | FT | 85 | $20.00 | $26.00 | $60.00 |
| 102 | Manhole removed (202E58000) | EACH | 1 | $700.00 | $1,650.00 | $1,800.00 |
| 103 | Valve box removed (202E75610) | EACH | 1 | $225.00 | $250.00 | $350.00 |
| 104 | 1" copper service branch, as per plan (638E04901) | FT | 170 | $60.00 | $116.00 | $40.00 |
| 105 | Fire hydrant extended and adjusted to grade, as per plan (638E10301) | EACH | 2 | $7,500.00 | $9,500.00 | $12,000 |
| 106 | Valve box adjusted to grade (638E10800) | EACH | 5 | $250.00 | $950.00 | $350.00 |
| 107 | Service box adjusted to grade (638E10900) | EACH | 1 | $800.00 | $850.00 | $600.00 |
| 108 | Water work, misc.: 12" water main reconnected (638E98000) | EACH | 1 | $7,500.00 | $4,650.00 | $3,500.00 |
| 109 | Water work, misc.: 8" water main reconnected (638E98000) | EACH | 1 | $5,000.00 | $3,600.00 | $3,000.00 |
| 110 | Water work, misc.: 12" water main relocated (638E98600) | FT | 50 | $250.00 | $295.00 | $235.00 |
| 111 | Water work, misc.: 8" water main relocated (638E98600) | FT | 50 | $200.00 | $220.00 | $150.00 |
| 112 | Manhole reconstructed to grade (611E99660) | EACH | 2 | $2,650.00 | $5,425.00 | $3,500.00 |
| 113 | 4" conduit, type E (611E00400) | FT | 60 | $5.11 | $5.50 | $28.00 |
| 114 | Connection, fused pull apart, as per plan (625E00451) | EACH | 32 | $179.75 | $190.00 | $190.00 |
| 115 | Connection, unfused pull apart (625E00460) | EACH | 10 | $179.75 | $190.00 | $190.00 |
| 116 | Connection, unfused permanent (625E00480) | EACH | 12 | $179.75 | $190.00 | $205.00 |
| 117 | Light pole, decorative, as per plan (625E10481) | EACH | 10 | $8,211.45 | $8,675.00 | $7,800.00 |
| 118 | Light pole foundation, 24" X 6' deep (625E14000) | EACH | 10 | $1,888.75 | $2,000.00 | $3,500.00 |
| 119 | Bracket arm, 6', as per plan (625E17951) | EACH | 1 | $1,124.10 | $1,200.00 | $2,000.00 |
| 120 | No. 4 AWG 600 volt distribution cable (625E23000) | FT | 4,563 | $5.67 | $6.00 | $5.30 |
| 121 | No. 8 AWG 600 volt distribution cable (625E23304) | FT | 4,926 | $4.75 | $5.00 | $4.60 |
| 122 | No. 10 AWG pole and bracket cable (625E23400) | FT | 2,043 | $2.64 | $3.00 | $2.00 |
| 123 | Conduit, 2", 725.051 (625E25408) | FT | 929 | $6.63 | $7.00 | $11.00 |
| 124 | Conduit, 3", 725.051 (625E25504) | FT | 222 | $8.48 | $9.00 | $16.00 |
| 125 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 110 | $51.70 | $55.00 | $85.00 |
| 126 | Luminaire, teardrop, solid state (LED), as per plan (625E27507) | EACH | 11 | $2,186.70 | $2,310.00 | $2,400.00 |
| 127 | Trench (625E29000) | FT | 1,151 | $14.78 | $16.00 | $12.00 |
| 128 | Pull box, 725.08, 18" (625E30700) | EACH | 2 | $1,048.75 | $1,115.00 | $1,550.00 |
| 129 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,221.25 | $1,290.00 | $1,900.00 |
| 130 | Ground rod (625E32000) | EACH | 11 | $341.25 | $360.00 | $425.00 |
| 131 | Power service, as per plan (625E34001) | EACH | 1 | $9,827.50 | $10,400 | $19,000 |
| 132 | Underground warning marking tape (625E36010) | FT | 1,151 | $2.08 | $2.50 | $4.25 |
| 133 | Arc flash calculations and label, lighting power S (625E76000) | EACH | 1 | $3,015.00 | $3,200.00 | $4,000.00 |
| 134 | Power cable, 3 conductor, no. 2 AWG (632E69320) | FT | 86 | $15.50 | $17.00 | $15.00 |
| 135 | Ground rod (625E32000) | EACH | 1 | $135.00 | $656.00 | $500.00 |
| 136 | Barrier reflector, type 1 (bidirectional) (626E00102) | EACH | 3 | $12.00 | $13.00 | $13.00 |
| 137 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 459 | $34.00 | $36.00 | $36.00 |
| 138 | Sign post reflector (630E08600) | EACH | 24 | $45.00 | $48.00 | $48.00 |
| 139 | Combination overhead sign support, type TC-16.22, design 9, as per plan (630E73531) | EACH | 1 | $27,150 | $28,750 | $29,500 |
| 140 | Sign hanger assembly, mast arm, as per plan (630E79101) | EACH | 2 | $680.00 | $720.00 | $760.00 |
| 141 | Sign hanger assembly, mast arm, as per plan (630E79101) | EACH | 15 | $680.00 | $720.00 | $750.00 |
| 142 | Sign support assembly, pole mounted, as per plan (630E79501) | EACH | 20 | $325.00 | $350.00 | $360.00 |
| 143 | Sign, flat sheet (630E80100) | SF | 316.10 | $20.00 | $21.00 | $21.00 |
| 144 | Sign, flat sheet, as per plan (630E80101) | SF | 52.50 | $38.00 | $40.00 | $44.00 |
| 145 | Sign, flat sheet, as per plan (630E80101) | SF | 117 | $36.00 | $38.00 | $40.00 |
| 146 | Sign, double faced, street name (630E80500) | EACH | 2 | $245.00 | $260.00 | $260.00 |
| 147 | Sign, street name, as per plan (630E80511) | EACH | 8 | $595.00 | $630.00 | $640.00 |
| 148 | Rigid overhead sign support foundation (630E84510) | EACH | 1 | $9,460.00 | $9,995.00 | $11,000 |
| 149 | Removal of ground mounted sign and disposal (630E84900) | EACH | 49 | $15.00 | $16.00 | $16.00 |
| 150 | Removal of ground mounted post support and disposal (630E86002) | EACH | 23 | $20.00 | $21.00 | $22.00 |
| 151 | Removal of pole mounted sign and disposal (630E87500) | EACH | 21 | $35.00 | $37.00 | $38.00 |
| 152 | Signing, misc.: ground mounted removable support S (630E97900) | FT | 137 | $65.00 | $70.00 | $70.00 |
| 153 | Removal of pavement marking (642E30000) | FT | 205 | $5.00 | $4.00 | $4.35 |
| 154 | Removal of pavement marking (642E30020) | EACH | 2 | $50.00 | $530.00 | $550.00 |
| 155 | Edge line, 6" (644E00104) | MI | 0.30 | $5,500.00 | $7,925.00 | $8,200.00 |
| 156 | Center line (644E00300) | MI | 0.26 | $7,000.00 | $10,500 | $11,000 |
| 157 | Channelizing line, 8" (644E00400) | FT | 374 | $2.00 | $4.00 | $4.25 |
| 158 | Stop line (644E00500) | FT | 183 | $7.00 | $10.00 | $10.00 |
| 159 | Crosswalk line, 12" (644E00620) | FT | 387 | $7.00 | $5.50 | $5.50 |
| 160 | Transverse/diagonal line (644E00700) | FT | 183 | $9.00 | $8.50 | $8.50 |
| 161 | Chevron marking (644E00720) | FT | 51 | $9.00 | $8.50 | $8.50 |
| 162 | Island marking (644E00900) | SF | 35 | $7.00 | $11.00 | $11.00 |
| 163 | Railroad symbol marking (644E01000) | EACH | 1 | $500.00 | $690.00 | $700.00 |
| 164 | Parking lot stall marking (644E01200) | FT | 42 | $1.00 | $2.00 | $2.20 |
| 165 | Lane arrow (644E01300) | EACH | 5 | $100.00 | $135.00 | $135.00 |
| 166 | Dotted line, 8" (644E01514) | FT | 324 | $0.75 | $2.00 | $2.20 |
| 167 | Dotted line, 12" (644E01520) | FT | 112 | $1.25 | $4.00 | $4.30 |
| 168 | Removal of pavement marking (644E30000) | FT | 467 | $5.00 | $9.00 | $8.50 |
| 169 | Center line (646E10200) | MI | 0.20 | $6,000.00 | $10,500 | $11,000 |
| 170 | Channelizing line, 8" (646E10300) | FT | 175 | $8.00 | $3.00 | $3.25 |
| 171 | Transverse/diagonal line (646E10600) | FT | 134 | $9.00 | $16.00 | $16.00 |
| 172 | Island marking (646E10800) | SF | 65 | $9.00 | $21.00 | $22.00 |
| 173 | Railroad symbol marking (646E20000) | EACH | 1 | $500.00 | $1,100.00 | $1,100.00 |
| 174 | Lane arrow (646E20300) | EACH | 2 | $120.00 | $265.00 | $265.00 |
| 175 | Bracket arm, 18', as per plan (625E18301) | EACH | 4 | $1,483.45 | $1,575.00 | $2,000.00 |
| 176 | Conduit, 2", 725.051 (625E25408) | FT | 217 | $6.63 | $7.00 | $17.00 |
| 177 | Conduit, 3", 725.051 (625E25504) | FT | 112 | $8.48 | $9.00 | $20.00 |
| 178 | Luminaire, teardrop, solid state (LED), as per plan (625E27507) | EACH | 4 | $2,129.20 | $2,250.00 | $2,300.00 |
| 179 | Trench (625E29000) | FT | 217 | $14.78 | $16.00 | $40.00 |
| 180 | Ground rod (625E32000) | EACH | 18 | $341.25 | $360.00 | $350.00 |
| 181 | Underground warning marking tape (625E36010) | FT | 217 | $2.08 | $2.50 | $3.50 |
| 182 | Arc flash calculations and label, signal power ser (625E76000) | EACH | 2 | $3,015.00 | $3,200.00 | $2,000.00 |
| 183 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007) | EACH | 16 | $1,306.35 | $1,380.00 | $1,375.00 |
| 184 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 16 | $743.30 | $790.00 | $750.00 |
| 185 | Accessible pedestrian pushbutton, as per plan (632E20751) | EACH | 16 | $1,044.75 | $1,100.00 | $1,180.00 |
| 186 | Covering of vehicular signal head (632E25000) | EACH | 16 | $38.25 | $40.00 | $46.00 |
| 187 | Covering of pedestrian signal head (632E25010) | EACH | 16 | $25.50 | $28.00 | $40.00 |
| 188 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 3,026 | $5.40 | $6.00 | $3.15 |
| 189 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 1,539 | $5.80 | $6.00 | $4.00 |
| 190 | Interconnect, misc.: spread spectrum radio unit (632E62820) | EACH | 2 | $4,756.25 | $5,025.00 | $4,600.00 |
| 191 | Signal support foundation, as per plan (632E64011) | EACH | 8 | $4,237.50 | $4,475.00 | $11,750 |
| 192 | Pedestal foundation (632E64020) | EACH | 8 | $1,213.75 | $1,285.00 | $3,400.00 |
| 193 | Loop detector lead-in cable, 2 conductor, no. 14 AWG (632E65300) | FT | 2,182 | $4.59 | $5.00 | $2.20 |
| 194 | Power service, as per plan (632E70001) | EACH | 2 | $3,677.50 | $3,885.00 | $2,400.00 |
| 195 | Signal support, type TC-81.22, design 4, as per plan (632E72111) | EACH | 2 | $13,243 | $13,985 | $17,000 |
| 196 | Signal support, type TC-81.22, design 12, as per plan (632E72131) | EACH | 1 | $17,787 | $18,785 | $22,000 |
| 197 | Signal support, type TC-81.22, design 13, as per plan (632E72141) | EACH | 1 | $21,094 | $22,300 | $25,000 |
| 198 | Combination signal support, type TC-81.22, design 4, as per plan (632E79111) | EACH | 3 | $16,427 | $17,350 | $20,000 |
| 199 | Combination signal support, type TC-81.22, design 12, as per plan (632E79131) | EACH | 1 | $19,392 | $20,500 | $24,000 |
| 200 | Pedestal, 10.7' tall, transformer base, as per plan (632E89921) | EACH | 8 | $1,926.80 | $2,035.00 | $2,800.00 |
| 201 | Removal of traffic signal installation for storage, as per plan (632E90103) | EACH | 2 | $5,062.50 | $5,350.00 | $5,500.00 |
| 202 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 2 | $18,793 | $19,850 | $22,000 |
| 203 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 2 | $8,819.25 | $9,325.00 | $11,900 |
| 206 | Stop line radar detection, as per plan (809E69101) | EACH | 8 | $9,551.75 | $10,100 | $10,750 |
| 207 | Atc controller, as per plan (809E69123) | EACH | 2 | $5,671.75 | $5,990.00 | $6,000.00 |
| 208 | Pavement removed (202E23000) | SY | 225 | $25.00 | $23.00 | $25.00 |
| 209 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 50 | $300.00 | $270.00 | $300.00 |
| 210 | Aggregate base (304E20000) | CY | 40 | $100.00 | $130.00 | $106.00 |
| 211 | Non-tracking tack coat (407E20000) | GAL | 14 | $3.00 | $5.00 | $3.00 |
| 212 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 10 | $650.00 | $325.00 | $650.00 |
| 213 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 32 | $120.00 | $80.00 | $120.00 |
| 214 | Detour signing, as per plan (614E12421) | LS | 1 | $30,000 | $26,500 | $35,000 |
| 215 | Work zone center line, class I (614E21000) | MI | 0.20 | $4,000.00 | $5,300.00 | $5,400.00 |
| 216 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.20 | $4,000.00 | $5,300.00 | $5,400.00 |
| 217 | Work zone edge line, class I, 4" (614E22000) | MI | 0.60 | $2,000.00 | $2,150.00 | $2,200.00 |
| 218 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 0.30 | $2,000.00 | $2,150.00 | $2,200.00 |
| 219 | Work zone channelizing line, class II, 8", 642 paint (614E23660) | FT | 374 | $3.00 | $2.00 | $2.10 |
| 220 | Work zone dotted line, class III, 8", 642 paint (614E24614) | FT | 436 | $1.50 | $1.00 | $1.05 |
| 221 | Work zone transverse/diagonal line, class I (614E25000) | FT | 143 | $8.00 | $4.00 | $4.30 |
| 222 | Work zone stop line, class I (614E26000) | FT | 15 | $8.00 | $4.00 | $4.30 |
| 223 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 110 | $7.37 | $21.00 | $21.00 |
| 224 | Work zone stop line, class III, 642 paint (614E26610) | FT | 126 | $7.00 | $5.00 | $5.30 |
| 225 | Work zone crosswalk line, class III, 12", 642 paint (614E27250) | FT | 387 | $7.00 | $5.00 | $5.30 |
| 226 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 7 | $60.00 | $53.00 | $55.00 |
| 227 | Work zone railroad symbol marking, class III, 642 paint (614E32210) | EACH | 2 | $200.00 | $265.00 | $260.00 |
| 228 | Work zone island marking, class I (614E32700) | SF | 7 | $8.00 | $9.00 | $8.50 |
| 229 | Water (616E10000) | MGAL | 19.30 | $20.00 | $3.00 | $50.00 |
| 230 | Approach slab removed, as per plan (202E22901) | SY | 16 | $200.00 | $370.00 | $350.00 |
| 231 | Reinforced concrete approach slabs (T=12"), as per plan (526E10001) | SY | 17 | $1,000.00 | $750.00 | $650.00 |
| 232 | Monument assembly, type C (623E38500) | EACH | 6 | $2,000.00 | $2,050.00 | $3,500.00 |
| 233 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $4,000.00 | $7,950.00 | $5,000.00 |
| 234 | Post construction survey monument verification and report (623E51000) | LS | 1 | $4,000.00 | $7,950.00 | $5,000.00 |
| 235 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $50,000 | $35,000 | $45,000 |
| 236 | Maintaining traffic (614E11000) | LS | 1 | $50,000 | $71,000 | $350,000 |
| 237 | Field office, type B (619E16010) | MNTH | 14 | $3,000.00 | $500.00 | $4,200.00 |
| 238 | Construction layout stakes and surveying (623E10000) | LS | 1 | $40,000 | $47,000 | $110,000 |
| 239 | Mobilization (624E10000) | LS | 1 | $170,000 | $145,000 | $200,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.