ODOT contract 260226 bid tabulation

ALL-SR 117-10.78 (INTERSECTION). Let by Ohio DOT on May 7, 2026, ALL. 3 bids received; low bid $2,424,191 by Fenson Contracting LLC, -3.8% against the engineer's estimate of $2,521,000.

Owner
Ohio DOT
Letting
07 MAY 2026
Pay items
120
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Fenson Contracting LLC$2,424,191Low-4.0%
2Helms and Sons Excavating$2,534,904+5.0%+1.0%
3Vernon Nagel Inc$2,877,284+19%+14%
ODOT contract 260226: bids by rank

Engineer's estimate: $2,521,000.

Bid tabulation

LinePay itemUnitQuantity1. Fenson Contracting LLC2. Helms and Sons Excavating3. Vernon Nagel Inc
1Clearing and grubbing (201E11000)LS1$9,500.00$85,000$10,000
2Pavement removed (202E23000)SY7,357$14.00$9.00$20.00
3Pipe removed, 24" and under (202E35100)FT492$30.00$50.00$65.00
4Pipe removed, over 24" diameter (202E35200)FT15$50.00$190.00$90.00
5Catch basin removed (202E58100)EACH5$670.00$600.00$500.00
6Monument assembly removed (202E60010)EACH10$350.00$250.00$200.00
7Excavation (203E10000)CY1,694$15.00$12.00$30.00
8Embankment (203E20000)CY2,768$25.00$15.00$30.00
9Subgrade compaction (204E10000)SY9,554$1.50$2.00$1.00
10Excavation of subgrade (204E13000)CY623$11.75$27.00$30.00
11Granular material, type B (204E30010)CY623$50.00$56.00$100.00
12Proof rolling (204E45000)HR5$125.00$150.00$250.00
13Geogrid (204E51000)SY1,867$5.88$4.00$3.50
14Monument assembly, type D (623E38550)EACH6$1,500.00$2,500.00$2,000.00
15Monument assembly adjusted to grade (623E39500)EACH1$1,000.00$550.00$1,000.00
16Right-of-way monument, type B (623E40520)EACH1$400.00$1,250.00$1,000.00
17Preconstruction survey monument verification and report (623E50000)LS1$3,200.00$8,500.00$3,500.00
18Post construction survey monument verification and report (623E51000)LS1$3,200.00$8,500.00$2,500.00
19Special - mailbox support (690E50000)EACH2$300.00$300.00$500.00
20Special - mailbox removed and reset (690E50350)EACH2$300.00$300.00$250.00
21Tied concrete block mat with type 1 underlayment (601E21050)SY3.56$210.00$2,200.00$350.00
22Topsoil (659E00300)CY1,030$40.00$13.00$75.00
23Seeding and mulching (659E10000)SY7,375$2.75$1.50$1.05
24Repair seeding and mulching (659E14000)SY369$1.30$2.00$1.00
25Inter-seeding (659E15000)SY369$1.00$2.00$0.80
26Commercial fertilizer (659E20000)TON1.03$900.00$950.00$800.00
27Lime (659E31000)ACRE1.52$35.00$120.00$1.00
28Water (659E35000)MGAL41$1.00$1.00$1.00
29Slope erosion protection (670E00500)SY1,894$2.00$3.00$1.85
30Storm water pollution prevention plan (832E15000)LS1$2,500.00$2,500.00$3,900.00
31Storm water pollution prevention inspections (832E15002)LS1$17,500$11,000$2,500.00
32Storm water pollution prevention inspection software (832E15010)LS1$17,000$17,000$8,500.00
33Erosion control (832E30000)EACH60,000$1.00$1.00$1.00
34Concrete masonry (602E20000)CY0.30$5,000.00$3,200.00$3,000.00
356" unclassified pipe underdrains with geotextile fabric (605E13410)FT91$16.00$25.00$15.00
366" base pipe underdrains with geotextile fabric (605E14020)FT2,978$16.00$12.00$22.00
376" conduit, type F for underdrain outlets (611E00510)FT260$38.00$44.00$20.00
386" conduit, type B, as per plan (611E00901)FT55$35.00$96.00$22.00
396" conduit, type C (611E01100)FT20$25.00$64.00$30.00
406" conduit, type E (611E01400)FT50$25.00$80.00$20.00
416" conduit, type F (611E01500)FT50$25.00$80.00$20.00
4212" conduit, type B, as per plan (611E04401)FT602$85.00$98.00$170.00
4312" conduit, type C (611E04600)FT437$60.00$84.00$125.00
4415" conduit, type B, as per plan (611E05901)FT135$135.00$133.00$155.00
4515" conduit, type C (611E06100)FT15$140.00$124.00$130.00
4624" conduit, type B, as per plan (611E10401)FT5$250.00$485.00$400.00
4724" conduit, type C (611E10600)FT336$85.00$119.00$140.00
4827" conduit, type B, as per plan (611E11901)FT76$225.00$176.00$350.00
4936" conduit, type B, as per plan (611E16401)FT15$225.00$448.00$500.00
50Catch basin, no. 3 (611E98150)EACH6$5,500.00$5,000.00$6,500.00
51Catch basin, no. 3A (611E98180)EACH7$4,700.00$3,750.00$6,000.00
52Catch basin, no. 6 (611E98370)EACH2$4,900.00$3,600.00$5,200.00
53Catch basin, no. 2-2B (611E98470)EACH3$3,300.00$3,350.00$4,500.00
54Catch basin, no. 2-3 (611E98510)EACH3$3,500.00$3,800.00$5,000.00
55Manhole, no. 3 (611E99574)EACH2$6,800.00$4,750.00$8,500.00
56Manhole, no. 3 (611E99574)EACH2$14,000$6,650.00$9,000.00
57Precast reinforced concrete outlet (611E99710)EACH2$300.00$1,300.00$1,247.41
58Pavement planing, asphalt concrete, 1 1/4" (254E01000)SY818$3.70$7.00$4.00
59Pavement planing, asphalt concrete, 3" (254E01000)SY804$3.70$7.00$4.00
60Pavement planing, asphalt concrete, varies 0" to 3 (254E01000)SY1,442$3.70$5.00$4.73
61Asphalt concrete base, PG64-22, (449) (301E56000)CY1,481$208.00$225.00$205.00
62Aggregate base (304E20000)CY1,771$60.00$55.00$100.00
63Non-tracking tack coat (407E20000)GAL1,359$3.00$3.00$3.00
64Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100)CY311$253.00$265.00$265.00
65Asphalt concrete intermediate course, type 2, (448) (441E50300)CY395$222.00$245.00$230.00
666" non-reinforced concrete pavement, class QC MS (452E10050)SY42$105.00$115.00$135.00
67Non-reinforced concrete pavement, misc.:9? concret (452E19200)SY1,518$150.00$148.00$135.00
68Combination curb and gutter, type 2 (609E12000)FT1,446$34.00$44.00$33.00
69Combination curb and gutter, type 2, as per plan (609E12001)FT244$33.00$44.00$36.00
70Curb, type 6 (609E26000)FT523$25.00$30.00$24.00
71Combination curb and gutter, type 9 (609E31000)FT2,821$28.00$38.00$27.00
72Combination curb and gutter, type 9, as per plan (609E31001)FT552$39.00$45.00$34.00
73Curb, misc.: combination curb and gutter, type 2, (609E98000)FT264$35.00$44.00$33.00
74Compacted aggregate (617E10100)CY17$75.00$80.00$150.00
75Rumble stripes, edge line (asphalt concrete) (618E40800)FT1,466$12.00$5.00$4.50
76Connection, fused pull apart (625E00450)EACH28$200.00$204.00$175.00
77Connection, unfused permanent (625E00480)EACH39$185.00$197.00$175.00
78Light pole (installation only), as per plan (625E10503)EACH14$1,250.00$1,450.00$2,450.00
79Light pole foundation, 24" X 8' deep (625E14100)EACH14$2,500.00$2,750.00$4,200.00
80No. 4 AWG 2400 volt distribution cable (625E23200)FT2,025$7.50$8.00$8.00
81No. 10 AWG pole and bracket cable (625E23400)FT2,226$2.80$3.00$5.00
821-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT1,699$18.00$20.00$25.00
83Conduit, 3", 725.04 (625E25500)FT448$35.00$38.00$45.00
84Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH14$620.00$625.00$950.00
85Trench, 24" deep (625E29002)FT1,880$14.00$15.00$26.00
86Pull box, 725.08, 18" (625E30700)EACH2$1,400.00$1,500.00$2,500.00
87Pull box, 725.08, 24" (625E30706)EACH6$1,600.00$1,750.00$2,800.00
88Pull box removed (625E31510)EACH3$650.00$750.00$650.00
89Ground rod (625E32000)EACH14$300.00$320.00$450.00
90Power service, as per plan (625E34001)EACH1$2,200.00$2,300.00$8,500.00
91Control center cabinet, complete (625E34450)EACH1$7,800.00$8,000.00$25,000
92Underground warning marking tape (625E36010)FT1,880$2.15$2.50$4.00
93Light pole removed (625E75400)EACH2$950.00$1,050.00$1,200.00
94Light pole foundation removed (625E75500)EACH2$1,250.00$1,450.00$1,800.00
95Removal of delineator (620E31200)EACH4$28.00$75.00$10.00
96RPM (621E00100)EACH156$52.00$70.00$39.85
97Ground mounted support, no. 3 post (630E03100)FT643.50$18.00$14.00$12.00
98Sign post reflector (630E08600)EACH18$65.00$50.00$45.00
99Sign, flat sheet (630E80100)SF325.20$23.00$28.00$25.00
100Removal of ground mounted sign and disposal (630E84900)EACH43$20.00$28.00$25.00
101Removal of ground mounted post support and disposal (630E86002)EACH34$25.00$28.00$25.00
102Signing, misc.: ground mounted support, with 12 in (630E97700)EACH12$115.00$120.00$22.50
103Edge line, 6" (644E00104)MI1.41$5,150.00$9,000.00$6,000.00
104Center line (644E00300)MI0.35$6,000.00$11,000$8,000.00
105Transverse/diagonal line (644E00700)FT542$10.00$10.00$7.00
106Dotted line, 12" (644E01520)FT157$1.35$4.00$3.00
107Yield line (644E20800)FT63$7.85$28.00$15.00
108Planting, misc.:10" gray washed river stone mulch (661E99930)SY597$40.00$50.00$34.00
109Pavement repair (253E02000)CY40$400.00$850.00$450.00
110Non-tracking tack coat (407E20000)GAL40$5.00$5.00$3.00
111Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY20$400.00$375.00$550.00
112Detour signing (614E12420)LS1$18,000$20,000$15,000
113Water (616E10000)MGAL40$40.00$2.00$1.00
114Compacted aggregate (617E10100)CY100$70.00$150.00$125.00
115Premium for contract performance bond and for payment bond (103E05000)LS1$25,000$38,000$30,000
116Maintaining traffic (614E11000)LS1$40,000$25,000$25,000
117Field office, type B (619E16010)MNTH9$3,500.00$500.00$2,000.00
118Construction layout stakes and surveying (623E10000)LS1$45,000$35,000$40,000
119Mobilization (624E10000)LS1$100,000$95,000$135,000
200Glare shield (625E28000)EACH2$200.00$250.00$450.00
ODOT contract 260226: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy