ODOT contract 260202 bid tabulation
HAN-McComb Ped Improvements (BIKEWAYS). Let by Ohio DOT on April 23, 2026, HAN. 2 bids received; low bid $206,097 by Advanced Excavating & Demolition LLC, +5.7% against the engineer's estimate of $195,000.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 35
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Advanced Excavating & Demolition LLC | $206,097 | Low | +6.0% |
| 2 | Fenson Contracting LLC | $229,009 | +11% | +17% |
Engineer's estimate: $195,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Advanced Excavating & Demolition LLC | 2. Fenson Contracting LLC |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,500.00 | $3,800.00 |
| 2 | Pavement removed (202E23000) | SY | 83 | $30.00 | $80.00 |
| 3 | Walk removed (202E30000) | SF | 992 | $7.00 | $13.25 |
| 4 | Curb and gutter removed (202E32500) | FT | 123 | $30.00 | $15.00 |
| 5 | Excavation (203E10000) | CY | 19 | $70.00 | $65.00 |
| 6 | Removal of existing pavement marking (512E74500) | FT | 181 | $20.00 | $25.00 |
| 7 | 4" concrete walk, as per plan (608E10001) | SF | 1,915 | $19.00 | $16.00 |
| 8 | Curb ramp, as per plan (608E52001) | SF | 391 | $25.00 | $28.00 |
| 9 | Detectable warning (608E53020) | SF | 40 | $50.00 | $28.00 |
| 10 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 181 | $78.00 | $75.00 |
| 11 | Curb, type 6, as per plan (609E26001) | FT | 195 | $65.00 | $65.00 |
| 12 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,500.00 | $1,500.00 |
| 13 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,500.00 | $1,500.00 |
| 14 | Topsoil (659E00300) | CY | 30 | $75.00 | $150.00 |
| 15 | Seeding and mulching (659E10000) | SY | 265 | $7.00 | $12.75 |
| 16 | Repair seeding and mulching (659E14000) | SY | 14 | $1.50 | $5.70 |
| 17 | Water (659E35000) | MGAL | 2 | $0.50 | $1.00 |
| 18 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 |
| 19 | Pavement repair (253E01000) | SY | 6 | $850.00 | $550.00 |
| 20 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 2 | $750.00 | $375.00 |
| 21 | Ground mounted support, no. 3 post (630E03100) | FT | 78 | $14.00 | $16.50 |
| 22 | Sign, flat sheet (630E80100) | SF | 197 | $22.00 | $25.50 |
| 23 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $75.00 | $90.00 |
| 24 | Signing, misc.:solar powered rectangular rapid fla (630E97700) | EACH | 6 | $8,750.00 | $10,150 |
| 25 | Transverse/diagonal line, type 1, as per plan (642E00701) | FT | 480 | $2.00 | $2.30 |
| 26 | Stop line (644E00500) | FT | 38 | $8.00 | $9.20 |
| 27 | Crosswalk line, 24" (644E00630) | FT | 416 | $8.00 | $9.20 |
| 28 | Fence, snow (607E30000) | FT | 115 | $11.00 | $8.00 |
| 29 | Work zone marking sign, as per plan (614E12461) | EACH | 4 | $100.00 | $115.00 |
| 30 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $2,500.00 |
| 31 | Maintaining traffic (614E11000) | LS | 1 | $10,000 | $14,000 |
| 32 | Water (616E10000) | MGAL | 2 | $5.00 | $50.00 |
| 33 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,500.00 | $7,250.00 |
| 34 | Mobilization (624E10000) | LS | 1 | $5,000.00 | $10,000 |
| 35 | Special - preconstruction video (900E17000) | LS | 1 | $2,000.00 | $950.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.