ODOT letting results, February 13, 2025
33 contracts let by Ohio DOT on February 13, 2025, $77,387,356 in low bids, a median of 3 bidders per contract. On the 33 with an engineer's estimate, the low bid came in under it 22 times; median low bid -7.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 33
- Low bids, total
- $77,387,356
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 250077 | ROS-SR 159-00.41 (MAJOR RECONSTRUCTION) | ROS | 3 | Complete General Construction Company | $19,286,684 | $20,048,215 | +4.0% | +1.0% | ODOT |
| 250003 | MUS-SR 208-00.00 (PART 1 AND PART 2) (MAJOR RECONSTRUCTION) | MUS | 2 | Shelly Company | $9,639,526 | $10,598,000 | +10% | -4.0% | ODOT |
| 250083 | CLA-US 68-04.43 (FOUR LANE RESURFACING) | CLA | 3 | Shelly Company | $7,086,327 | $7,316,379 | +3.0% | -14% | ODOT |
| 250089 | HUR-SR 4-00.00 (TWO LANE RESURFACING) | HUR | 2 | Erie Blacktop Inc | $4,484,860 | $5,043,157 | +12% | -19% | ODOT |
| 250109 | D07-FDPM FY25 (PAVEMENT MARKING) | District 7 | 2 | Oglesby Construction Inc | $3,178,669 | $3,413,000 | +7.0% | -20% | ODOT |
| 250102 | SHE-PAVE-FY25 (TWO LANE RESURFACING) | SHE | 2 | Barrett Paving Materials Inc | $2,880,600 | $2,975,996 | +3.0% | +6.0% | ODOT |
| 250084 | CUY-IR 90-19.77/VAR Ramps (MINOR RECONSTRUCTION) | CUY | 6 | Anthony Allega Cement Contractor Inc | $2,587,098 | $2,762,220 | +7.0% | -20% | ODOT |
| 250080 | ATB-US 322/VAR-22.48/VAR (TWO LANE RESURFACING) | ATB | 2 | Karvo Companies Inc | $2,575,000 | $2,768,000 | +7.0% | -10% | ODOT |
| 250095 | MAH-US 422/SR 616-07.58/03.81 (FOUR LANE RESURFACING) | MAH | 3 | Shelly & Sands Inc | $2,069,999 | $2,448,277 | +18% | -12% | ODOT |
| 250099 | PIC-SR 762-11.18 (SPOT PATCHING / PAVEMENT REPAIR) | PIC | 5 | Shelly Company | $1,967,344 | $2,162,760 | +10% | -34% | ODOT |
| 250090 | JEF-SR 43-02.00 (TWO LANE RESURFACING) | JEF | 3 | NLS Paving, Inc | $1,718,137 | $1,745,551 | +2.0% | +7.0% | ODOT |
| 250088 | HOC-SR 56-05.69/HOC-SR 180-02.33 (BRIDGE REPLACEMENT (2 BRIDGES)) | HOC | 6 | D G M Inc | $1,686,284 | $1,729,437 | +3.0% | -3.0% | ODOT |
| 250096 | MOE-SR 537-00.32 (SLIDE REPAIR) | MOE | 3 | Alan Stone Co Inc | $1,651,908 | $1,669,419 | +1.0% | 0.0% | ODOT |
| 250105 | WAY-SR 94/US 30A-06.70/00.00 (TWO LANE RESURFACING) | WAY | 3 | Kokosing Construction Company Inc | $1,453,493 | $1,453,518 | 0.0% | -5.0% | ODOT |
| 250073 | GEA-US 322/SR 44-08.63/14.93 (CULVERT REPLACEMENT) | GEA | 5 | Matt Winters Excavation LLC | $1,425,622 | $1,648,594 | +16% | +2.0% | ODOT |
| 250111 | D11-GR FY2025 (GUARDRAIL REBUILDING) | District 11 | 2 | Lake Erie Construction Company | $1,410,325 | $1,466,738 | +4.0% | -7.0% | ODOT |
| 250101 | PUT-SR 108-02.65 (SLIDE REPAIR) | PUT | 3 | Advanced Excavating & Demolition LLC | $1,355,230 | $1,399,778 | +3.0% | +5.0% | ODOT |
| 250091 | LAK-Metroparks Lakefront Phase 2 (SIDEWALK) | LAK | 2 | Marucci & Gaffney Excavating Co | $1,197,820 | $1,524,715 | +27% | +12% | ODOT |
| 250082 | CHP-PAVE-FY25 (TWO LANE RESURFACING) | CHP | 2 | Shelly Company | $1,059,968 | $1,097,251 | +4.0% | -6.0% | ODOT |
| 250107 | D04-CS FY2025 (CRACK SEALING) | District 4 | 3 | Annseal Inc | $998,828 | $1,027,936 | +3.0% | -16% | ODOT |
| 250094 | LIC-CR 327-00.00 (BIKEWAYS) | LIC | 8 | Law General Contracting Inc | $938,829 | $961,702 | +2.0% | -23% | ODOT |
| 254006 | ALL-SR 117-03.47/04.64 (CULVERT REPLACEMENT) | ALL | 4 | Advanced Excavating & Demolition LLC | $876,165 | $917,863 | +5.0% | -17% | ODOT |
| 250110 | D10-Extrusheet Sign FY2025 (SIGNING) | District 10 | 2 | M P Dory Co | $813,279 | $1,014,550 | +25% | -18% | ODOT |
| 250104 | VIN-CR 25-00.20 (BRIDGE REPLACEMENT (1 BRIDGE)) | VIN | 6 | Alan Stone Co Inc | $725,868 | $726,298 | 0.0% | -17% | ODOT |
| 250112 | WOO-IR 75-08.58 Weigh Station (PARKING AREAS) | WOO | 4 | Geddis Paving & Excavating Inc | $693,840 | $694,981 | 0.0% | -28% | ODOT |
| 254008 | GEA-US 422-01.46/VAR Drainage (MISCELLANEOUS) | GEA | 2 | Madex Construction Co | $639,976 | $906,541 | +42% | +34% | ODOT |
| 250098 | NOB-CR 56-South Access (INTERSECTION) | NOB | 3 | Shelly & Sands Inc | $556,886 | $649,832 | +17% | -9.0% | ODOT |
| 250100 | PIK-SR 220-05.50SR (CULVERT REPLACEMENT) | PIK | 6 | D G M Inc | $554,331 | $662,411 | +19% | -8.0% | ODOT |
| 254007 | ERI-/HUR-SR 113/SR 13-20.18/04.13 (CULVERT REPLACEMENT) | ERI | 2 | Great Lakes Demolition Company | $528,983 | $583,898 | +10% | +1.0% | ODOT |
| 250097 | MOT-Sycamore Creek Bridge Replac (BRIDGE REPLACEMENT (1 BRIDGE)) | MOT | 7 | R B Jergens Contractors Inc | $473,959 | $487,831 | +3.0% | 0.0% | ODOT |
| 250108 | D06-RPM FY25 (RAISED PAVEMENT MARKERS) | District 6 | 2 | W L Markers Inc | $367,397 | $482,570 | +31% | -6.0% | ODOT |
| 250106 | D03-SYSSIGN FY2025 (SIGNING) | District 3 | 2 | Cleveland Barricading Systems LLC | $336,162 | $395,475 | +18% | -24% | ODOT |
| 258001 | MRW-SR 529-02.46 (BRIDGE REPAIR) | MRW | 5 | E S Wagner Company | $167,959 | $169,306 | +1.0% | +51% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.