ODOT contract 250089 bid tabulation
HUR-SR 4-00.00 (TWO LANE RESURFACING). Let by Ohio DOT on February 13, 2025, HUR. 2 bids received; low bid $4,484,860 by Erie Blacktop Inc, -19% against the engineer's estimate of $5,510,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 64
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Erie Blacktop Inc | $4,484,860 | Low | -19% |
| 2 | Gerken Paving Inc | $5,043,157 | +12% | -8.0% |
Engineer's estimate: $5,510,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Erie Blacktop Inc | 2. Gerken Paving Inc |
|---|---|---|---|---|---|
| 1 | Guardrail removed (202E38000) | FT | 350 | $2.10 | $2.00 |
| 2 | Anchor assembly removed, type E (202E42010) | EACH | 4 | $105.00 | $135.00 |
| 3 | Bridge terminal assembly removed (202E47000) | EACH | 4 | $105.00 | $75.00 |
| 4 | Embankment, as per plan (203E20001) | CY | 10 | $68.25 | $136.00 |
| 5 | Excavation of subgrade (204E13000) | CY | 313 | $33.80 | $40.00 |
| 6 | Granular material, type B (204E30010) | CY | 313 | $70.00 | $70.00 |
| 7 | Proof rolling (204E45000) | HR | 8 | $135.00 | $100.00 |
| 8 | Geotextile fabric (204E50000) | SY | 626 | $2.40 | $3.00 |
| 9 | Reshaping under guardrail, as per plan (209E15001) | STA | 5.50 | $78.75 | $60.00 |
| 10 | Preparing subgrade for shoulder paving, as per plan (209E72051) | MI | 13.28 | $1,850.00 | $2,100.00 |
| 11 | Grading mailbox approaches (209E80000) | EACH | 14 | $220.00 | $600.00 |
| 12 | Guardrail, type 5 (606E13000) | FT | 100 | $23.50 | $21.00 |
| 13 | Guardrail, type MGS (606E15050) | FT | 250 | $23.50 | $21.80 |
| 14 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 4 | $2,575.00 | $2,420.00 |
| 15 | Bridge terminal assembly, type 4 (606E35140) | EACH | 4 | $1,445.00 | $1,040.00 |
| 16 | Seeding and mulching, as per plan (659E10001) | SY | 2,580 | $11.25 | $5.00 |
| 17 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 |
| 18 | Aggregate drains, as per plan (605E31101) | FT | 11,600 | $5.50 | $8.00 |
| 19 | Partial depth pavement repair (asphalt concrete base) (251E01042) | CY | 1,210 | $195.00 | $212.00 |
| 20 | Partial depth pavement repair (asphalt concrete base) (251E01042) | CY | 122 | $350.00 | $390.00 |
| 21 | Pavement repair, as per plan (253E02001) | CY | 6,252 | $148.00 | $222.00 |
| 22 | Pavement repair, as per plan (253E02001) | CY | 400 | $400.00 | $435.00 |
| 23 | Pavement planing, asphalt concrete (1.25 inch) (254E01000) | SY | 469 | $1.85 | $2.41 |
| 24 | Pavement planing, asphalt concrete (3.0 inch) (254E01000) | SY | 109,556 | $1.85 | $2.41 |
| 25 | Pavement planing, asphalt concrete (taper 3.0" to (254E01000) | SY | 302 | $1.85 | $2.41 |
| 26 | Patching planed surface (254E01600) | SY | 552 | $9.75 | $18.00 |
| 27 | Tack coat (407E10000) | GAL | 14,349 | $2.55 | $2.25 |
| 28 | Prime coat, as per plan (408E10001) | GAL | 6,401 | $4.80 | $6.75 |
| 29 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 3,842 | $206.00 | $187.00 |
| 30 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 199 | $206.00 | $190.00 |
| 31 | Asphalt concrete intermediate course, 12.5 MM, type A (448), as per plan (442E20171) | CY | 5,352 | $170.00 | $172.00 |
| 32 | Compacted aggregate (617E10100) | CY | 907 | $59.20 | $80.00 |
| 33 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 6.64 | $1,090.00 | $1,050.00 |
| 34 | Special - pavement overlay fabric composite (690E12060) | SY | 13,239 | $21.75 | $20.70 |
| 35 | Longitudinal joint preparation (874E20000) | FT | 35,069 | $0.75 | $1.90 |
| 36 | RPM (621E00100) | EACH | 450 | $43.60 | $41.50 |
| 37 | Raised pavement marker removed (621E54000) | EACH | 450 | $5.50 | $5.00 |
| 38 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 6 | $11.55 | $12.50 |
| 39 | Edge line, 6", type 1 (642E00104) | MI | 13.32 | $840.00 | $850.00 |
| 40 | Center line, type 1 (642E00300) | MI | 6.66 | $840.00 | $600.00 |
| 41 | Stop line (644E00500) | FT | 217 | $7.35 | $8.00 |
| 42 | Crosswalk line, 12" (644E00620) | FT | 52 | $4.20 | $4.00 |
| 43 | Railroad symbol marking (644E01000) | EACH | 2 | $630.00 | $700.00 |
| 44 | Word on pavement, 96" (644E01410) | EACH | 2 | $265.00 | $200.00 |
| 45 | Bike crossing symbol (644E01620) | EACH | 2 | $157.50 | $500.00 |
| 46 | Speed measurement marking (644E40000) | EACH | 5 | $675.00 | $30.00 |
| 47 | Traffic compacted surface, type A or B (410E12000) | CY | 18 | $255.00 | $225.00 |
| 48 | Traffic compacted surface, type C (410E13000) | CY | 110 | $120.00 | $145.00 |
| 49 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 75 | $89.25 | $110.00 |
| 50 | Detour signing (614E12420) | LS | 1 | $7,875.00 | $12,000 |
| 51 | Work zone marking sign (614E12460) | EACH | 29 | $105.00 | $125.00 |
| 52 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $325.00 | $500.00 |
| 53 | Maintaining traffic, misc.: temporary mailboxes (614E18000) | EACH | 26 | $142.00 | $120.00 |
| 54 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $998.00 | $1,350.00 |
| 55 | Work zone center line, class III, 642 paint (614E21550) | MI | 19.98 | $840.00 | $600.00 |
| 56 | Work zone stop line, class III, 642 paint (614E26610) | FT | 117 | $3.15 | $3.00 |
| 57 | Sawing and sealing asphalt concrete pavement joints (409E30000) | FT | 102 | $27.35 | $26.04 |
| 58 | Deep beam bridge retrofit railing (517E75600) | FT | 100 | $110.00 | $118.00 |
| 59 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $4,500.00 | $5,400.00 |
| 60 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $22,000 | $24,000 |
| 61 | Maintaining traffic (614E11000) | LS | 1 | $120,000 | $160,000 |
| 62 | Field office, type B (619E16010) | MNTH | 8 | $2,700.00 | $4,250.00 |
| 63 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,500 | $9,460.00 |
| 64 | Mobilization (624E10000) | LS | 1 | $220,000 | $135,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.