ODOT contract 250105 bid tabulation
WAY-SR 94/US 30A-06.70/00.00 (TWO LANE RESURFACING). Let by Ohio DOT on February 13, 2025, WAY. 3 bids received; low bid $1,453,493 by Kokosing Construction Company Inc, -4.6% against the engineer's estimate of $1,524,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 54
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kokosing Construction Company Inc | $1,453,493 | Low | -5.0% |
| 2 | Karvo Companies Inc | $1,453,518 | 0.0% | -5.0% |
| 3 | Barbicas Construction Company Inc | $1,454,541 | 0.0% | -5.0% |
Engineer's estimate: $1,524,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kokosing Construction Company Inc | 2. Karvo Companies Inc | 3. Barbicas Construction Company Inc |
|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 39 | $27.00 | $67.00 | $100.00 |
| 2 | Walk removed (202E30000) | SF | 3,709 | $3.00 | $1.00 | $3.00 |
| 3 | Curb removed (202E32000) | FT | 360 | $8.00 | $14.25 | $20.00 |
| 4 | Curb and gutter removed (202E32500) | FT | 72 | $10.00 | $32.00 | $24.00 |
| 5 | Mailbox removed (202E53100) | EACH | 6 | $50.00 | $75.00 | $35.00 |
| 6 | Linear grading (209E60200) | STA | 5.41 | $62.00 | $1,100.00 | $300.00 |
| 7 | Grading mailbox approaches (209E80000) | EACH | 52 | $20.00 | $70.00 | $70.00 |
| 8 | 4" concrete walk (608E10000) | SF | 1,603 | $7.38 | $5.25 | $11.00 |
| 9 | Curb ramp (608E52000) | SF | 2,750 | $18.44 | $13.45 | $16.00 |
| 10 | Combination curb and gutter, type 2 (609E12000) | FT | 31 | $31.00 | $82.00 | $70.00 |
| 11 | Curb, type 6 (609E26000) | FT | 252 | $24.00 | $26.00 | $38.00 |
| 12 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 1 | $2,000.00 | $1,200.00 | $615.00 |
| 13 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,500.00 | $1,040.00 | $1,440.00 |
| 14 | Special - mailbox support system, double (690E50200) | EACH | 3 | $400.00 | $300.00 | $300.00 |
| 15 | Topsoil, as per plan (659E00301) | CY | 6 | $160.83 | $250.00 | $200.00 |
| 16 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 |
| 17 | Catch basin adjusted to grade (611E98630) | EACH | 43 | $750.00 | $1,300.00 | $700.00 |
| 18 | Manhole adjusted to grade (611E99654) | EACH | 19 | $600.00 | $1,075.00 | $550.00 |
| 19 | Partial depth pavement repair (asphalt concrete base) (251E01042) | CY | 120 | $500.00 | $470.00 | $350.00 |
| 20 | Pavement repair (253E02000) | CY | 13 | $700.00 | $470.00 | $400.00 |
| 21 | Pavement planing, asphalt concrete (1.5") (254E01000) | SY | 37,183 | $2.00 | $2.10 | $3.00 |
| 22 | Pavement planing, asphalt concrete (3.0") (254E01000) | SY | 18,922 | $2.55 | $3.25 | $4.00 |
| 23 | Patching planed surface (254E01600) | SY | 2,805 | $1.25 | $0.75 | $2.31 |
| 24 | Aggregate base, as per plan (304E20001) | CY | 1 | $70.00 | $155.00 | $200.00 |
| 25 | Non-tracking tack coat (407E20000) | GAL | 5,455 | $2.75 | $2.75 | $3.20 |
| 26 | Prime coat, as per plan (408E10001) | GAL | 2,424 | $4.75 | $5.45 | $5.20 |
| 27 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 671 | $235.00 | $240.00 | $185.00 |
| 28 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 1,566 | $235.00 | $233.00 | $185.00 |
| 29 | Asphalt concrete intermediate course, 12.5 MM, type A (448), as per plan (442E20171) | CY | 940 | $200.00 | $221.00 | $235.00 |
| 30 | Compacted aggregate (617E10100) | CY | 389 | $30.00 | $72.00 | $80.00 |
| 31 | Shoulder preparation (617E20000) | SY | 6,060 | $0.25 | $1.15 | $0.50 |
| 32 | Valve box adjusted to grade (638E10800) | EACH | 39 | $400.00 | $500.00 | $400.00 |
| 33 | RPM (621E00100) | EACH | 90 | $43.00 | $43.00 | $65.00 |
| 34 | Raised pavement marker removed (621E54000) | EACH | 56 | $15.00 | $10.00 | $5.00 |
| 35 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $60.00 | $60.00 | $60.00 |
| 36 | Removal of ground mounted post support and reerection (630E86010) | EACH | 4 | $60.00 | $60.00 | $60.00 |
| 37 | Edge line, 6", type 1 (642E00104) | MI | 4.85 | $700.00 | $700.00 | $700.00 |
| 38 | Center line, type 1 (642E00300) | MI | 3.50 | $975.00 | $975.00 | $975.00 |
| 39 | Stop line, type 1 (642E00500) | FT | 533 | $3.50 | $3.50 | $3.50 |
| 40 | Crosswalk line, 12", type 1 (642E00620) | FT | 1,440 | $3.00 | $3.00 | $3.00 |
| 41 | School symbol marking, 96", type 1 (642E01110) | EACH | 2 | $350.00 | $350.00 | $350.00 |
| 42 | Parking lot stall marking, type 1 (642E01200) | FT | 1,135 | $1.30 | $1.30 | $2.00 |
| 43 | Stop line (644E00500) | FT | 88 | $12.00 | $12.00 | $12.00 |
| 44 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $125.00 | $90.00 | $80.00 |
| 45 | Work zone marking sign (614E12460) | EACH | 64 | $60.00 | $55.00 | $55.00 |
| 46 | Asphalt concrete for maintaining traffic (614E13000) | CY | 25 | $100.00 | $300.00 | $300.00 |
| 47 | Work zone center line, class III, 642 paint (614E21550) | MI | 8.28 | $950.00 | $950.00 | $950.00 |
| 48 | Work zone stop line, class III, 642 paint (614E26610) | FT | 588 | $1.00 | $3.50 | $3.50 |
| 49 | Work zone crosswalk line, class III, 12", 642 paint (614E27250) | FT | 1,376 | $1.00 | $2.75 | $2.75 |
| 50 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,000.00 | $6,500.00 | $15,000 |
| 51 | Maintaining traffic (614E11000) | LS | 1 | $203,030 | $85,000 | $222,000 |
| 52 | Field office, type B (619E16010) | MNTH | 6 | $2,295.00 | $1,750.00 | $800.00 |
| 53 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,000.00 | $1,700.00 | $200.00 |
| 54 | Mobilization (624E10000) | LS | 1 | $72,000 | $112,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.