ODOT contract 250104 bid tabulation
VIN-CR 25-00.20 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on February 13, 2025, VIN. 6 bids received; low bid $725,868 by Alan Stone Co Inc, -17% against the engineer's estimate of $870,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 54
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Alan Stone Co Inc | $725,868 | Low | -17% |
| 2 | D G M Inc | $726,298 | 0.0% | -17% |
| 3 | Axis Civil Construction LLC | $754,349 | +4.0% | -13% |
| 4 | Double Z Construction Company | $869,995 | +20% | 0.0% |
| 5 | Shelly & Sands Inc | $883,259 | +22% | +2.0% |
| 6 | Complete General Construction Company | $941,820 | +30% | +8.0% |
Engineer's estimate: $870,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alan Stone Co Inc | 2. D G M Inc | 3. Axis Civil Construction LLC | 4. Double Z Construction Company | 5. Shelly & Sands Inc | 6. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,900.00 | $12,000 | $6,000.00 | $11,000 | $1,500.00 | $14,000 |
| 2 | Pavement removed (202E23000) | SY | 167 | $20.00 | $8.00 | $12.00 | $22.00 | $11.00 | $16.00 |
| 3 | Guardrail removed (202E38000) | FT | 232 | $8.50 | $1.00 | $6.00 | $8.00 | $2.50 | $5.00 |
| 4 | Excavation (203E10000) | CY | 112 | $35.00 | $35.00 | $34.00 | $50.00 | $52.00 | $40.00 |
| 5 | Subgrade compaction (204E10000) | SY | 238 | $5.50 | $10.00 | $3.00 | $25.00 | $7.00 | $4.25 |
| 6 | Excavation of subgrade (204E13000) | CY | 119 | $35.00 | $30.00 | $32.00 | $50.00 | $49.00 | $50.00 |
| 7 | Granular embankment (204E21000) | CY | 119 | $15.00 | $30.00 | $100.00 | $70.00 | $110.00 | $125.00 |
| 8 | Proof rolling (204E45000) | HR | 1 | $280.00 | $70.00 | $200.00 | $180.00 | $215.00 | $125.00 |
| 9 | Geotextile fabric (204E50000) | SY | 238 | $1.00 | $2.50 | $8.00 | $1.25 | $1.50 | $5.50 |
| 10 | Guardrail, type MGS (606E15050) | FT | 213 | $25.00 | $24.00 | $22.00 | $22.00 | $21.00 | $27.82 |
| 11 | Anchor assembly, MGS type A (606E25550) | EACH | 4 | $2,100.00 | $1,800.00 | $1,750.00 | $1,750.00 | $1,650.00 | $1,430.00 |
| 12 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $3,100.00 | $2,700.00 | $2,650.00 | $2,650.00 | $2,300.00 | $1,990.00 |
| 13 | Barrier reflector, type 3 (bidirectional) (626E00112) | EACH | 27 | $15.00 | $13.00 | $11.00 | $11.00 | $15.00 | $9.50 |
| 14 | Topsoil (659E00300) | CY | 36 | $35.00 | $20.00 | $55.00 | $70.00 | $92.00 | $50.00 |
| 15 | Seeding and mulching (659E10000) | SY | 322 | $4.50 | $10.00 | $3.00 | $16.00 | $10.00 | $10.00 |
| 16 | Repair seeding and mulching (659E14000) | SY | 16 | $20.00 | $0.05 | $3.00 | $40.00 | $2.50 | $2.50 |
| 17 | Commercial fertilizer (659E20000) | TON | 0.04 | $2,000.00 | $1,500.00 | $800.00 | $50.00 | $1,250.00 | $1,250.00 |
| 18 | Lime (659E31000) | ACRE | 0.07 | $1,000.00 | $300.00 | $400.00 | $10.57 | $150.00 | $150.00 |
| 19 | Water (659E35000) | MGAL | 1.70 | $120.00 | $1.00 | $1.00 | $1.70 | $1.00 | $1.00 |
| 20 | Erosion control (832E30000) | EACH | 7,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 36 | $410.00 | $420.00 | $315.00 | $395.00 | $365.00 | $395.00 |
| 22 | Aggregate base (304E20000) | CY | 38 | $150.00 | $120.00 | $150.00 | $110.00 | $156.00 | $160.00 |
| 23 | Tack coat (407E10000) | GAL | 12 | $6.50 | $2.50 | $5.00 | $2.50 | $3.50 | $2.50 |
| 24 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 18 | $630.00 | $430.00 | $640.00 | $410.00 | $550.00 | $410.00 |
| 25 | Ground mounted support, no. 3 post (630E03100) | FT | 36 | $40.00 | $30.00 | $32.00 | $32.00 | $17.50 | $15.00 |
| 26 | Sign, flat sheet (630E80100) | SF | 12 | $75.00 | $35.00 | $65.00 | $65.00 | $25.00 | $30.00 |
| 27 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $290.00 | $20.00 | $65.00 | $250.00 | $25.00 | $15.00 |
| 28 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $240.00 | $20.00 | $50.00 | $200.00 | $25.00 | $15.00 |
| 29 | Edge line, 4" (643E00100) | MI | 0.08 | $56,000 | $50,000 | $47,895 | $47,895 | $47,895 | $47,895 |
| 30 | Center line (643E00300) | MI | 0.04 | $58,000 | $50,000 | $48,980 | $48,980 | $48,980 | $48,980 |
| 31 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $16,000 | $23,000 | $25,000 | $30,000 | $41,000 | $50,000 |
| 32 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $2,000.00 | $500.00 | $5,000.00 | $8,000.00 | $24,000 | $500.00 |
| 33 | Unclassified excavation (503E21100) | CY | 216 | $30.00 | $20.00 | $55.00 | $124.00 | $30.00 | $125.00 |
| 34 | Rock excavation (503E31100) | CY | 60 | $130.00 | $50.00 | $80.00 | $135.00 | $140.00 | $65.00 |
| 35 | Epoxy coated steel reinforcement (509E10000) | LB | 17,349 | $2.00 | $1.30 | $2.00 | $1.50 | $1.43 | $1.65 |
| 36 | Class QC2 concrete, superstructure, as per plan (511E31611) | CY | 60 | $1,300.00 | $1,355.00 | $1,340.00 | $1,100.00 | $1,600.00 | $1,600.00 |
| 37 | Class QC1 concrete, abutment including footing (511E43510) | CY | 80 | $710.00 | $625.00 | $860.00 | $825.00 | $1,400.00 | $850.00 |
| 38 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 110 | $45.00 | $35.00 | $40.00 | $38.00 | $40.00 | $40.00 |
| 39 | Prestressed concrete composite box beam bridge members, level 1, CB33-48 (515E12090) | EACH | 7 | $30,000 | $31,500 | $29,400 | $29,000 | $26,500 | $29,000 |
| 40 | 2" preformed expansion joint filler (516E13900) | SF | 35 | $10.00 | $20.00 | $15.00 | $25.00 | $16.00 | $12.00 |
| 41 | Semi-integral abutment expansion joint seal (516E14020) | FT | 87 | $30.00 | $47.50 | $28.00 | $30.00 | $48.00 | $48.00 |
| 42 | 1/8" preformed bearing pad, type CDP (516E41100) | EACH | 14 | $90.00 | $30.00 | $68.00 | $80.00 | $50.00 | $95.00 |
| 43 | 1" elastomeric bearing pad, type pep (516E41500) | EACH | 28 | $170.00 | $110.00 | $130.00 | $110.00 | $130.00 | $150.00 |
| 44 | Railing (twin steel tube) (517E70000) | FT | 176 | $260.00 | $225.00 | $219.25 | $219.25 | $210.00 | $210.00 |
| 45 | Special - steel drip strip (518E22300) | FT | 199 | $10.00 | $20.00 | $17.00 | $16.00 | $16.00 | $25.00 |
| 46 | Drilled shafts, 30" diameter into bedrock, as per plan (524E94605) | FT | 138 | $160.00 | $400.00 | $195.00 | $865.00 | $515.00 | $725.00 |
| 47 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 76 | $410.00 | $232.00 | $290.00 | $550.00 | $325.00 | $600.00 |
| 48 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 58 | $170.00 | $110.00 | $105.00 | $120.00 | $195.00 | $100.00 |
| 49 | Low strength mortar backfill (613E41200) | CY | 166 | $140.00 | $150.00 | $150.00 | $150.00 | $195.00 | $125.00 |
| 50 | Thermal integrity profiling (tip) test (894E10000) | EACH | 6 | $2,900.00 | $3,500.00 | $2,500.00 | $1,800.00 | $3,100.00 | $3,010.00 |
| 51 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $10,000 | $6,000.00 | $5,800.00 | $4,800.00 | $7,000.00 |
| 52 | Maintaining traffic (614E11000) | LS | 1 | $12,000 | $20,000 | $12,000 | $9,000.00 | $6,500.00 | $9,000.00 |
| 53 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,000 | $5,000.00 | $10,000 | $8,000.00 | $16,000 | $10,000 |
| 54 | Mobilization (624E10000) | LS | 1 | $16,000 | $8,000.00 | $40,000 | $40,000 | $44,982 | $80,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.