ODOT contract 250097 bid tabulation
MOT-Sycamore Creek Bridge Replac (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on February 13, 2025, MOT. 7 bids received; low bid $473,959 by R B Jergens Contractors Inc, +0.4% against the engineer's estimate of $472,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 48
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | R B Jergens Contractors Inc | $473,959 | Low | 0.0% |
| 2 | Double Z Construction Company | $487,831 | +3.0% | +3.0% |
| 3 | Brumbaugh Construction Inc | $530,000 | +12% | +12% |
| 4 | KT Holden Construction LLC | $558,540 | +18% | +18% |
| 5 | John R Jurgensen Company | $594,155 | +25% | +26% |
| 6 | Sunesis Construction Co | $660,321 | +39% | +40% |
| 7 | Complete General Construction Company | $672,604 | +42% | +43% |
Engineer's estimate: $472,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R B Jergens Contractors Inc | 2. Double Z Construction Company | 3. Brumbaugh Construction Inc | 4. KT Holden Construction LLC | 5. John R Jurgensen Company | 6. Sunesis Construction Co |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,321 | $5,000.00 | $5,000.00 | $88,130 | $6,493.49 | $33,674 |
| 2 | Pavement removed (202E23000) | SY | 314 | $8.76 | $7.00 | $10.00 | $5.70 | $6.92 | $12.41 |
| 3 | Excavation (203E10000) | CY | 144 | $32.85 | $35.00 | $25.00 | $19.00 | $41.66 | $49.73 |
| 4 | Embankment (203E20000) | CY | 436 | $14.86 | $36.00 | $25.00 | $21.50 | $38.13 | $41.39 |
| 5 | Subgrade compaction (204E10000) | SY | 1,232 | $4.32 | $7.00 | $1.00 | $2.25 | $2.73 | $4.79 |
| 6 | Excavation of subgrade (204E13000) | CY | 31 | $39.03 | $65.00 | $25.00 | $5.50 | $56.46 | $116.18 |
| 7 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 27 | $242.35 | $135.00 | $100.00 | $200.00 | $244.65 | $198.46 |
| 8 | Topsoil (659E00300) | CY | 231 | $67.53 | $65.00 | $60.00 | $35.00 | $50.19 | $65.00 |
| 9 | Seeding and mulching, as per plan (659E10001) | SY | 1,139 | $3.95 | $8.50 | $5.00 | $2.30 | $5.75 | $5.03 |
| 10 | Repair seeding and mulching (659E14000) | SY | 104 | $3.95 | $3.80 | $1.00 | $2.30 | $5.75 | $3.80 |
| 11 | Inter-seeding (659E15000) | SY | 104 | $3.95 | $3.80 | $1.00 | $2.30 | $5.75 | $3.80 |
| 12 | Commercial fertilizer (659E20000) | TON | 0.29 | $789.55 | $760.00 | $900.00 | $760.00 | $850.00 | $760.00 |
| 13 | Lime (659E31000) | ACRE | 0.43 | $51.93 | $50.00 | $1.00 | $50.00 | $50.00 | $50.00 |
| 14 | Water (659E35000) | MGAL | 12 | $51.94 | $50.00 | $1.00 | $50.00 | $1.00 | $50.00 |
| 15 | Storm water pollution prevention plan (832E15000) | LS | 1 | $1,869.99 | $3,000.00 | $2,500.00 | $3,500.00 | $2,575.00 | $2,575.00 |
| 16 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,233.30 | $8,700.00 | $8,500.00 | $4,200.00 | $5,550.00 | $2,100.00 |
| 17 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $6,233.30 | $6,000.00 | $6,000.00 | $5,400.00 | $5,316.91 | $5,316.91 |
| 18 | Erosion control (832E30000) | EACH | 8,200 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 19 | Aggregate base (304E20000) | CY | 142 | $72.44 | $105.00 | $75.00 | $85.00 | $110.13 | $96.36 |
| 20 | Tack coat (407E10000) | GAL | 35 | $6.06 | $5.00 | $20.00 | $18.40 | $5.00 | $15.00 |
| 21 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 18 | $624.51 | $515.00 | $450.00 | $482.35 | $515.00 | $580.00 |
| 22 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 36 | $588.13 | $485.00 | $450.00 | $351.55 | $485.00 | $580.00 |
| 23 | Structure removed, as per plan (202E11001) | LS | 1 | $39,311 | $17,000 | $30,000 | $13,000 | $16,708 | $123,880 |
| 24 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $14,116 | $23,000 | $25,000 | $32,320 | $20,194 | $29,485 |
| 25 | Unclassified excavation (503E21300) | LS | 1 | $15,121 | $12,000 | $5,000.00 | $14,500 | $6,517.91 | $8,093.75 |
| 26 | Pile driving equipment mobilization (505E11100) | LS | 1 | $10,395 | $20,000 | $10,000 | $33,700 | $31,736 | $419.87 |
| 27 | 12" cast-in-place reinforced concrete piles, driven (507E00500) | FT | 160 | $15.16 | $35.00 | $5.00 | $10.70 | $115.51 | $63.95 |
| 28 | 12" cast-in-place reinforced concrete piles, furnished (507E00550) | FT | 200 | $49.14 | $50.00 | $90.00 | $76.00 | $62.98 | $50.46 |
| 29 | Epoxy coated steel reinforcement (509E10000) | LB | 6,084 | $2.08 | $1.80 | $1.50 | $1.80 | $2.35 | $1.91 |
| 30 | Class QC2 concrete, superstructure (511E31610) | CY | 24 | $1,510.76 | $1,850.00 | $2,200.00 | $1,550.00 | $2,685.03 | $2,371.68 |
| 31 | Class QC1 concrete, abutment not including footing (511E44110) | CY | 11 | $1,258.73 | $1,300.00 | $1,500.00 | $1,670.00 | $1,918.31 | $1,471.14 |
| 32 | Class QC1 concrete, footing (511E46510) | CY | 15 | $728.39 | $925.00 | $1,100.00 | $840.00 | $1,349.54 | $1,291.04 |
| 33 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 49 | $77.92 | $41.00 | $25.00 | $65.00 | $75.00 | $75.00 |
| 34 | Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040) | EACH | 5 | $17,733 | $17,150 | $30,000 | $17,000 | $19,468 | $19,702 |
| 35 | 1" preformed expansion joint filler (516E13600) | SF | 27 | $6.93 | $11.00 | $4.00 | $5.80 | $17.16 | $4.96 |
| 36 | Semi-integral abutment expansion joint seal (516E14020) | FT | 44 | $49.06 | $30.00 | $40.00 | $58.00 | $55.00 | $106.73 |
| 37 | Elastomeric bearing with internal laminates only (neoprene) (516E43100) | EACH | 20 | $148.99 | $130.00 | $120.00 | $178.00 | $216.53 | $172.09 |
| 38 | Railing, misc.: wood fence with steel posts (517E76300) | FT | 124 | $150.60 | $139.50 | $160.00 | $139.50 | $139.50 | $139.50 |
| 39 | Porous backfill with geotextile fabric (518E21200) | CY | 25 | $121.58 | $115.00 | $80.00 | $95.00 | $177.30 | $119.57 |
| 40 | Special - steel drip strip (518E22300) | FT | 124 | $31.85 | $21.00 | $15.00 | $29.20 | $18.00 | $18.00 |
| 41 | 6" perforated corrugated plastic pipe (518E40000) | FT | 44 | $12.91 | $7.50 | $15.00 | $19.50 | $11.87 | $9.46 |
| 42 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 48 | $17.37 | $7.50 | $15.00 | $29.00 | $46.19 | $4.89 |
| 43 | Dynamic load testing (523E20000) | EACH | 1 | $3,568.57 | $5,000.00 | $8,000.00 | $3,435.00 | $3,435.00 | $6,207.15 |
| 44 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,839 | $5,000.00 | $10,000 | $9,865.00 | $3,498.75 | $4,408.02 |
| 45 | Maintaining traffic (614E11000) | LS | 1 | $8,830.25 | $7,000.00 | $2,000.00 | $5,400.00 | $63,266 | $3,969.11 |
| 46 | Field office, type A (619E16000) | MNTH | 6 | $2,646.03 | $1,500.00 | $500.00 | $1,940.00 | $1,834.81 | $2,051.67 |
| 47 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,752.75 | $9,000.00 | $7,500.00 | $13,000 | $4,884.12 | $5,300.00 |
| 48 | Mobilization (624E10000) | LS | 1 | $11,738 | $30,000 | $26,968 | $27,900 | $20,000 | $44,472 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.